Home / Browse projects / Mumbai Suburban, Maharashtra / AVANTE
AVANTE
RG-MH-11630 · RERA P51800001140 · Last updated on MahaRERA portal: 13 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 55 complaints at MahaRERA
- Completion date moved by 60 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AVANTE is a Residential / Group Housing project by Sanjeevani Vyapaar LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001140 on 26 Jul 2017. Possession is promised by 30 Dec 2027. The completion date has moved by 60 months from the original filing. 378 of the 383 units on this registration are recorded sold or booked, and 26 of 33 construction stages are filed complete. 55 complaints are on record with the regulator.
At a glance
Project
- NameAVANTE
- TypeResidential / Group Housing
- Location
- LBS Marg
- Kanjur Marg
- Kurla
- Mumbai Suburban
- 400078
- Pincode400078
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800001140
- ReraGenie IDRG-MH-11630
Builder
- NameSanjeevani Vyapaar LLP
- Entity typePartnership
- CmdASHWIN N SHETH
- Declared earlier projects10 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on26 Jul 2017
- Promised completion30 Dec 2027
- Revised completionRevised to 30 Dec 2027 (originally 30 Dec 2022)
- Buildings3 building records
- Documents filed176 files
Current status
Figures as on 13 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 31 | 25 | 146 | 0 | 146 |
| WING B | NA | 30 | 24 | 140 | 0 | 140 |
| WING C | NA | 30 | 24 | 94 | 3 | 97 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 13 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
26 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 95%.
WING A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C92%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 95% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Progress on shared amenities15
As on 13 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 85% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 95% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 95% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed383
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| WING A | 146 | 146 |
| WING B | 111 | 111 |
| WING C | 126 | 126 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING B | NA | Rs 52.23 cr | Rs 47.21 cr |
| WING A | NA | Rs 49.75 cr | Rs 49.74 cr |
| WING C | NA | Rs 47.31 cr | Rs 40.67 cr |
| - | NA | Rs 11.45 cr | Rs 3.40 cr |
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANDEEP SHIKRE & ASSOCIATES |
| Architect | AAKAR ARCHITECT AND CONSULTANT |
| Engineer | Muhammad Shoeb CHOUHAN |
| Engineer | Deepak N Gaikwad |
| Engineer | SMARTY LACHHWANI |
| Engineer | Anas Shaikh |
| Engineer | RAMBOLL INDIA PVT LTD |
| Chartered Accountant | M. B. Agrawal & Co. |
| Chartered Accountant | Haresh Bhanushali & Associates |
| Partner | Role in project |
|---|---|
| Sanjeevani Vyapaar LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Applicants, are developing “AVANTE” project and have various approvals for same. The Applicants state that for CC, NOC from Naval Authorities (hereafter N.A.) was required. The Applicants vide application 16.7.2016 to EEBP(ES), requested N.A. to grant NOC for further CC. N.A. vide letter 09.12.2016, refused NOC. Also Stop Work Notice (hereafter SWN) dated 4.01.2019 was issued. During, this time a W.P (No. 3013/2018, Tirandaz matter), concerning same cause of action was pending at HC. The HC vide order dated 27.2.2019, quashed SWN issued to Tirandaaz. The Applicants have filed a Writ Petiti
Reason as filed by the promotera) The Applicant submits that the said Project is unlikely to be completed by 31.12.2024. Hence, in the said circumstances, the Applicant is constrained to make this Application and seek extension of the registration of project for 36 months i.e. till 30.12.2027. b) The Applicant submits that on 09.12.2016, a letter was received from the Western Naval Command informing the Developer that NOC for construction will not be granted. Consequently, MCGM vide letter dated 06.01.2017 ordered the Developer to stop further construction work and provide an inventory (status) of the construction work alre
Litigation declared1
| Case | Court | Status |
|---|---|---|
| WP 1358/2019/2019 | Bombay High Court | Listed for admission Next date of hearing is not yet available |
Complaints filed with MahaRERA55
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000079131 | Sanjay Mahadev Chiplunkar | M/s. Sanjivani Vyapar LLP | 02/05/2019 |
| CC006000000171791 | Mujahid Rafiq Mukadam | Ashwin sheth | 23/01/2020 |
| CC006000000195221 | Mujahid Mukadam | Sanjeevani Vyapar LLp | 11/12/2020 |
| CC006000000192222 | MARLIN VARGHESE KADA | Sanjeevani Vyapaar LLP | 24/01/2020 |
| CC006000000192530 | Mahesh Parulekar | Sanjeevani Vyapaar LLP | 10/02/2020 |
| CC006000000195087 | Ravindra Agrawal | M/s SanjeevaniVyapaarLLP | 03/12/2020 |
| CC006000000193735 | Snehalata Devram Deokar | Sanjeevani Vyapaar LLP | 15/08/2020 |
| CC006000000195304 | Shailini Shailesh Marwaha | Sanjeevani Vyapaar LLP | 28/12/2020 |
| CC006000000195559 | Ashutosh Singh Rawat | Sanjeevani Vyapaar Limited Liability Partnership | 09/01/2021 |
| CC006000000196331 | Deepali Shrikant Tekade | Sanjeevani Vyapaar Limited Liability Partnership | 18/03/2021 |
| CC006000000198962 | Kaiser Sultana Shaikh | Sanjeevani Vyapaar Limited | 09/11/2021 |
| CC006000000198443 | RAVINDRA SHANTARAM CHAVAN | SANJEEVNI VYAPAAR LLP | 23/09/2021 |
| CC006000000198664 | Chander Navani | Sanjeevani Vyapaar Limited Liability Partnership | 13/10/2021 |
| CC006000000198781 | Harish Shankappa Shetty | P51800001140 | 08/11/2021 |
| CC006000000209616 | Ashish Mane | Sanjeevani Vyapaar LLP | 04/01/2022 |
| CC006000000209649 | Puja Nikhil Kadam | M/s. Sanjivani Vyapar LLP | 08/01/2022 |
| CC006000000209917 | Girish Sharma and Usha Sharma | Sanjeevani Vyapaar LLP | 12/02/2022 |
| CC006000000209918 | Ritesh Raghunandan Nasikkar and Kirtikumar J. Sharma | Sanjeevani Vyapar LLP | 12/02/2022 |
| CC006000000210257 | SHAILESH MATEKAR | SANJEEVNI VYPAAR LLP | 04/03/2022 |
| CC006000000220834 | Prakash Raju Shetty | Sanjeevani Vyapaar Limited Liability | 15/04/2022 |
| CC006000000292455 | Sonali Amit Dsouza | Sanjeevani Vyapaar Limited Liability Partnership | 26/08/2022 |
| CC006000000303220 | Pragati Utkarsh Ghagare | Sanjeevani Vyapaar Limited Liability Partership | 04/11/2022 |
| CC006000000333838 | Manoj Gopaldas Nankani | M/s Sanjivani Vyapar LLP | 29/12/2022 |
| CC006000000397860 | Keith Sherwin Mascarenhas | Sanjeevani Vyapaar LLP | 16/10/2023 |
| CC12400595 | Riten Rajendra Patel | Sanjeevani Vyapaar LLP | 27/10/2024 |
| CC12502787 | Sachin Gaikwad | Sanjeevani Vyapaar LLP | 07/08/2025 |
| CC12501101 | SENTHIL KUMAR | Sanjeevani Vyapaar LLP | 02/04/2025 |
| CC12501206 | HARIOM CHHOTELAL GUPTA | Sanjeevani Vyapaar LLP | 11/04/2025 |
| CC12501323 | Samitha Ankush Shetty | Sanjeevani Vyapaar LLP | 21/04/2025 |
| CC12501336 | SNEHA PRADIP ACHREKAR | Sanjeevani Vyapaar LLP | 22/04/2025 |
| CC12501337 | Jayashankar Arjun Shukla | Sanjeevani Vyapaar LLP | 22/04/2025 |
| CC12501413 | Pankaj Manohar Khubchandani | Sanjeevani Vyapaar LLP | 27/04/2025 |
| CC12501512 | JAIBHIM TUKARAM NARNAWARE | Sanjeevani Vyapaar LLP | 06/05/2025 |
| CC12501695 | Neha Gupta De | Sanjeevani Vyapaar LLP | 25/05/2025 |
| CC12501820 | Ganesh Dhondu Kadge | Sanjeevani Vyapaar LLP | 03/06/2025 |
| CC12502185 | Hanumantha Narsappa | Sanjeevani Vyapaar LLP | 01/07/2025 |
| CC12502151 | MANOHAR A SURVE | Sanjeevani Vyapaar LLP | 30/06/2025 |
| CC12502213 | PRAVIN MARUTI SALVE | Sanjeevani Vyapaar LLP | 03/07/2025 |
| CC12502614 | Omkar Ashok Kabadi | Sanjeevani Vyapaar LLP | 29/07/2025 |
| CC12502981 | Prasad Chandrakant Shirangare | Sanjeevani Vyapaar LLP | 23/08/2025 |
| CC12503521 | Gopal Harishchandra Salunkhe | Sanjeevani Vyapaar LLP | 02/10/2025 |
| CC12503557 | SHITAL PRADIP UGHADE | Sanjeevani Vyapaar LLP | 06/10/2025 |
| CC12503562 | Rohan Sakpal | Sanjeevani Vyapaar LLP | 07/10/2025 |
| CC12503783 | JACKSON SANTAN DSOUZA | Sanjeevani Vyapaar LLP | 29/10/2025 |
| CC12503773 | LINI BALAKRISHNAN KARANATH | Sanjeevani Vyapaar LLP | 29/10/2025 |
| CC12503840 | MARLIN VARGHESE KADA | Sanjeevani Vyapaar LLP | 01/11/2025 |
| CC12504183 | Saurabh Kumar Singh | Sanjeevani Vyapaar LLP | 26/11/2025 |
| CC12504505 | Pankaj Manohar Khubchandani | Sanjeevani Vyapaar LLP | 17/12/2025 |
| CC12600214 | Joyce Sharon Benjamin | Sanjeevani Vyapaar LLP | 12/01/2026 |
| CC12600556 | Manish Dinkar Kothawade | Sanjeevani Vyapaar LLP | 01/02/2026 |
| CC12600820 | JAIBHIM TUKARAM NARNAWARE | Sanjeevani Vyapaar LLP | 13/02/2026 |
| CC12601322 | Jogesh Satishkumar Chawla | Sanjeevani Vyapaar LLP | 11/03/2026 |
| CC12602015 | Abhishek Vilas Hongekar | Sanjeevani Vyapaar LLP | 05/04/2026 |
| CC12602316 | Gurudev Uddhav Bodake | Sanjeevani Vyapaar LLP | 19/04/2026 |
| CC12603809 | Sucheta Mehra | Sanjeevani Vyapaar LLP | 20/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2027
Documents filed176
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 176 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Avante Form-1.pdf | 13 May 2026 |
| Withdrawal Update Form 2File: AVANTE (1).pdf | 13 May 2026 |
| Withdrawal Update Form 3File: Form - 3_Avante_Mar 26.pdf | 13 May 2026 |
| Withdrawal Update Form 1File: form 1 avante.pdf | 28 Jan 2026 |
| Withdrawal Update Form 2File: AVANTE.pdf | 28 Jan 2026 |
| Withdrawal Update Form 3File: Form-3_Avante_Dec 25_Signed.pdf | 28 Jan 2026 |
| Withdrawal Update Form 1File: Form - 1 Avante 271025.pdf | 12 Dec 2025 |
| Withdrawal Update Form 2File: AVANTE.pdf | 12 Dec 2025 |
| Withdrawal Update Form 3File: Form-3_Avante_Sept 25 Signed.pdf | 12 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form - 5_Avante_2024-25-Signed.pdf | 25 Nov 2025 |
| Form 2A (FY 2024-2025)File: FORM-2A - Avante.pdf | 5 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 - Avante.pdf | 24 Oct 2025 |
| Withdrawal Update Form 2File: AVANTE.pdf | 24 Oct 2025 |
| Withdrawal Update Form 3File: Form - 3 Avante.pdf | 24 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Discloser of Sold - Booked Inventory - Avante.pdf | 24 Jul 2025 |
| Form 1File: 05012022_RERA_CERTIFICATE avante_compressed.pdf | 24 Jul 2025 |
| Form 2File: Form 2-Avante-Dec 2021.pdf | 24 Jul 2025 |
| Form 3File: Avante form 3 Dec 21.pdf | 24 Jul 2025 |
| Form 1File: AVANTE.pdf | 24 Jul 2025 |
| Form 2File: AVANTE.PDF | 24 Jul 2025 |
| Form 3File: Avante March 22.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SHETH AVANTE.PDF | 24 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Avante.pdf | 29 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3 - Avante.pdf | 29 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Sheth Avante.pdf | 29 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: AVANTE.pdf | 29 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: AVANTE.pdf | 22 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: AVANTE.pdf | 22 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: AVANTE.pdf | 22 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Avante.pdf | 18 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Avante.pdf | 18 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Avante.pdf | 18 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 - Sheth Avante.pdf | 16 Jan 2025 |
| Certificates of CA (Form 3)File: FORM-3- Avante.pdf | 16 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 - Sheth Avante.pdf | 16 Jan 2025 |
| Certificates of CA (Form 3)File: FORM-3- Avante.pdf | 16 Jan 2025 |
| Certificates of CA (Form 3)File: FORM-3- Avante.pdf | 16 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 - Sheth Avante.pdf | 16 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AVANTE Form 1.pdf | 29 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 Avante.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: Form - 3 Avante.pdf | 29 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: AVANTE - A WING.pdf | 29 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: AVANTE - B WING.pdf | 29 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: AVANTE - C WING.pdf | 29 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AVANTE Form 1.pdf | 29 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 Avante.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: Form - 3 Avante.pdf | 29 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: AVANTE - A WING.pdf | 29 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: AVANTE - B WING.pdf | 29 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: AVANTE - C WING.pdf | 29 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AVANTE Form 1.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: Form - 3 Avante.pdf | 29 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 Avante.pdf | 29 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: AVANTE - A WING.pdf | 29 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: AVANTE - B WING.pdf | 29 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: AVANTE - C WING.pdf | 29 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 - AVANTE.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 - AVANTE.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 - AVANTE.pdf | 7 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Avante.pdf | 6 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Avante.pdf | 26 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2-AVANTE.pdf | 26 Jul 2024 |
| Certificates of CA (Form 3)File: FORM -3 - AVANTE.pdf | 26 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 4.pdf | 3 May 2024 |
| Disclosure of sold/ booked inventoryFile: AVANTE.pdf | 3 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Avante.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 - Sheth Avante.pdf | 22 Apr 2024 |
| Certificates of CA (Form 3)File: FORM-3 - Avante.pdf | 22 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Full CC for wing C.pdf | 29 Mar 2024 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate Avante.pdf | 29 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Avante.pdf | 2 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Avante.pdf | 16 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Avante.pdf | 16 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 - Avante.pdf | 16 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1) 1st quater.pdf | 7 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2) 2nd quater.pdf | 7 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3) 3rd quater.pdf | 7 Dec 2023 |
Promoter's earlier projects9
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SIGMA | ZANDU PHARMACTICAL GOKHALE ROAD SOUTH DADAR W MUMBAI - 25. | 260 | Completed | Jul 2014 | Late, Dec 2014 |
| VIVIANA MALL | Viviana Mall Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601 | 240 | Completed | May 2013 | May 2013 |
| Vasant Lawns | Vasant Lawns Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601 | 465 | Completed | Mar 2012 | Late, Nov 2013 |
| BEAUMONDE | APPASAHEB MARATHE MARG PRABHADEVI MUMBAI 25 | 196 | Completed | Dec 2011 | Late, Jan 2012 |
| VASANT MARVEL | WESTRN EXPRESS HIGHWAY VILLAGE MAGATHANE BORIWALI EAST MUMBAI - 66 | 641 | Completed | Oct 2011 | Late, Jul 2012 |
| CYNERGY | APPASAHEB MARATHE MARG PRABHADEVI MUMBAI 25 | 33 | Completed | Sep 2011 | Sep 2011 |
| VASANT GALAXY | JUNCTION OF MG ROAD AND LINK ROAD BANGUR NAGAR GOREGAON WEST MUMBAI | 803 | Completed | Oct 2010 | Late, Mar 2011 |
| VASANT VALLEY | MALAD EAST MUMBAI 96 | 127 | Completed | Jun 2010 | Late, Dec 2010 |
| VASANT GARDEN | SWAPNA NAGARI OFF LBS MARG MULUND WEST MUMBAI 80 | 1,825 | Completed | Mar 2007 | Late, Dec 2007 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 176 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep AVANTE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kanjur Marg6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 173 registered projects within 2 km.
Runwal Forests Tower 9 - 11
Wheelabrator Alloy Castings Limited
SHRADDHA VARDAAN
SHRADDHA LANDMARK PRIVATE LIMITED
SHRADDHA EVOQUE
SHRADDHA LANDMARK PRIVATE LIMITED
Sugee Vaayu
Sugee Developers Private Limited
SHRADDHA CLASSIC
SHRADDHA LANDMARK PRIVATE LIMITED
Om Siddhivinayak CHS Ltd
Shree Shiv Samarth Reality
See every Mumbai Suburban project, with the district possession charts
Builder: Sanjeevani Vyapaar LLP
Sanjeevani Vyapaar LLP has 1 registration on MahaRERA, including AVANTE. Its filings disclose 10 earlier MahaRERA projects: declares 2 of 9 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if AVANTE is delayed beyond 30 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AVANTE?
The registered promoter entity is Sanjeevani Vyapaar LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AVANTE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AVANTE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AVANTE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AVANTE?
The professionals named in the filing: Architect: SANDEEP SHIKRE & ASSOCIATES; Architect: AAKAR ARCHITECT AND CONSULTANT; Engineer: Muhammad Shoeb CHOUHAN; Engineer: Deepak N Gaikwad; Engineer: SMARTY LACHHWANI; Engineer: Anas Shaikh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AVANTE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback