Runwal Forests Tower 9 - 11

By Wheelabrator Alloy Castings Limited

RG-MH-10110 · RERA P51800001137 · Last updated on MahaRERA portal: 24 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 10 cases
  • 41 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 0.83 crore secured on the land, in favour of HDFC BANK LTD

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 12 months from the original
18 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 96%
31 of 1,047Units unsoldnot recorded sold or booked
41Complaints at MahaRERAon this registration
Jump to the 1283 documents Report an error

Runwal Forests Tower 9 - 11 is a Residential / Group Housing project by Wheelabrator Alloy Castings Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001137 on 26 Jul 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 12 months from the original filing. 1,016 of the 1,047 units on this registration are recorded sold or booked, and 18 of 33 construction stages are filed complete. 41 complaints are on record with the regulator.

At a glance

Project

  • NameRunwal Forests Tower 9 - 11
  • TypeResidential / Group Housing
  • Location
    • LBS Marg
    • Bhandup(W)
    • Kurla
    • Mumbai Suburban
    • 400078
  • Pincode400078
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800001137
  • ReraGenie IDRG-MH-10110

Builder

  • NameWheelabrator Alloy Castings Limited
  • Entity typeCompany
  • DirectorLucy Roychoudhury
  • Other registrations2 more →
  • Completed2 of 3

Key dates

this monthRegisteredJul 2017First promiseJun 2026Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Jul 2017
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2026)
  • Buildings3 building records
  • Documents filed1283 files

Current status

97%1016 of 1,047 units booked
82.4%Work done, per cost certificate

Figures as on 24 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower-9NA53501910191
Tower -10NA59564280428
Tower-11NA59564280428

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 96%.

Tower-9100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower -1077%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)95%
Plinth100%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks58%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.47%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.52%
Tower-1167%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)95%
Plinth100%
Stilt Floor90%
Slabs of Super Structure96%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises53%
Sanitary Fittings within the flats / premises2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks37%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.27%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.42%

Progress on shared amenities15

As on 24 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes83%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes97%
Landscaping & Tree PlantingYes80%
Street LightingYes80%
Community BuildingsYes75%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes95%
Fire protection and fire safety requirementsYes93%
Electrical meter room, sub-station, receiving stationYes96%
Aggregate area of recreational Open SpaceYes94%
Open ParkingNoNot applicable

Parking filed1113

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,113
Closed/Covered1,113
BuildingClosed/CoveredTotal
Tower-9203203
Tower -10455455
Tower-11455455

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area62,558 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofHDFC BANK LTD
Secured amountRs 0.83 crore
CERSAI search filedYes
Declared on22 Jan 2026

Approvals and building plan

Permissible FSI71520.81
Proposed, not sanctioned71,521 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchINDUSIND HOUSE, 425, DADASAHEB BHADKAMKAR MARG MUMBAI - 400 004
Estimated costRs 433.26 cr
Cost incurredRs 356.88 cr
Work done82.37%
BuildingWingEstimatedIncurred
Tower -10NARs 131.36 crRs 108.87 cr
Tower-11NARs 115.45 crRs 84.10 cr
Tower-9NARs 98.60 crRs 92.87 cr
-NARs 87.85 crRs 71.05 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAakar Architects & Consultants
ArchitectAmit A Wasrani & Associates
EngineerEpicons Consultant Pvt. Ltd. Structural Architect
EngineerUttam Kawathankar
Chartered AccountantKshirsagar & Associates
Chartered AccountantM B Agarwal and Co
PartnerRole in project
Wheelabrator Alloy Castings Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA29062621610Jun 2026 → Jun 2027

Reason as filed by the promoterWe hereby apply for extension under Section 6 of the Real Estate (Regulation and Development) Act, 2016. The primary reason for the delay in completion of the project arises from the sequential nature of obtaining final regulatory clearances and executing the remaining advanced finishing works across the final phases. While we have successfully secured the full Occupation Certificate (OC) for Tower 9, the timelines for the remaining structures have been impacted by interdependent administrative and construction milestones. Specifically, for Tower 10, the project has progressed to the final app

Litigation declared10

CaseCourtStatus
WP No 2182/2007/2007HIGH COURT BOMBAYPENDING
132/2017 L 181/2016/2017HIGH COURT BOMBAYPENDING
WP L 2613/2007/2007HIGH COURT BOMBAYPENDING
CCL/526/2017 in Suit No 132/2017/2017HIGH COURT BOMBAYPENDING
Ref No 164 of 2018/2018Labour Court Thanepending
WRIT PETITION L NO 424 OF 2019/2019HIGH COURT OF JUDICATURE AT BOMBAYpending
CC006000000192276/2020Maharera AuthorityDisposed Off
CC006000000171902/2020Maharera Authoritypending
CC006000000193363/2020Maharera AuthorityDisposed Off
CC006000000193690/2020Maharera AuthorityDisposed Off

Complaints filed with MahaRERA41

Case no.ComplainantRespondentFiled
CC006000000408225Pranay KumarWheelabrator Alloy Castings Limited22/11/2023
CC006000000209932Gajanan Pralhadrao HedaooWheelabrator Alloy Castings Limited08/02/2022
CC006000000055101A sivaramanWheelabrator alloy castings ltd (subodh runwal)26/06/2018
CC006000000171902Jagjit Singh AroraWheelabrator Alloy Castings Limited17/12/2019
CC006000000198813Anup BhatiaRunwal Builder26/10/2021
CC006000000194288Mr. Karan Singh ChauhanWheelabrator Alloy Castings Limited05/10/2020
CC006000000192276Mr. Abhishek Gupta and Mrs Chanchul GuptaRunwal Group ( Wheelabrator Alloy Castings Ltd.23/01/2020
CC006000000193363Santosh NaikWheelabrator Alloy Castings Limited02/07/2020
CC006000000193690ROHWIN PETER MARTISWheelabrator Alloy Castings Limited08/08/2020
CC006000000194340Surendra PoojariWheelabrator Alloy Castings ltd co12/10/2020
CC006000000195309ABHIMANYU S RAVIBHUSHAN SINGHM/S WHEELABRATOR ALLOY CASTING LTD28/02/2021
CC006000000196348Prabhat Kumar Dubey and Shweta MishraWheelabrator Alloy Castings Limited07/06/2021
CC006000000196443Gopal Ramdeo NigamRunwal Group22/03/2021
CC006000000333888GOPAL RAMDEO NIGAMWheelabrator Alloys Casting Ltd04/01/2023
CC006000000197844Pallavi GhaisasWheelabrator Alloy Castings Ltd10/08/2021
CC006000000197891Neeta Guruprasad RaoSubodh Runwal04/08/2021
CC006000000198677Rumman Ahmed ShaikhWheelabrator Alloy Castings Ltd, Runwal Forests19/10/2021
CC006000000199117SACHIN SUVARNAWHEELABRATOR ALLOY CASTINGS LIMITED24/11/2021
CC006000000210286Mrs Shardha Anand NaikWheelabrator Alloy Castings Limited07/03/2022
CC006000000210504IMRAN ASIF KHANWHEELABRATOR ALLOY CASTINGS LIMITED12/04/2022
CC006000000210505RUBY ASIF KHANWHEELABRATOR ALLOY CASTINGS LIMITED12/04/2022
CC006000000220990HETVI KETAN SHETHWheelabrator Alloy Castings Limited05/05/2022
CC006000000292280Shailesh MayekarWheelabrator Alloy Castings Limited09/08/2022
CC006000000303561Priya MishraWHEELABRATOR ALLOY CASTING11/04/2023
CC006000000303744GOPAL RAMDEO NIGAMRunwal Group - Wheelabrator Alloy Casting Ltd.22/12/2022
CC006000000375044Ramesh Chandra GuptaWheelabrator Alloy Castings Limited03/04/2023
CC12500166ANUJ CHATUR NARAYAN SHRIVASTAVAWheelabrator Alloy Castings Limited18/01/2025
CC12501073Shraddha Makarand TawateWheelabrator Alloy Castings Limited31/03/2025
CC12501226Raj Kumar AgrawalWheelabrator Alloy Castings Limited13/04/2025
CC12503373MAHENDRA WARBHUVANWheelabrator Alloy Castings Limited21/09/2025
CC12503568Wheelabrator Alloy Castings LimitedNeeraj Sharma07/10/2025
CC12503587Wheelabrator Alloy Castings LimitedUday Gawade08/10/2025
CC12503588Wheelabrator Alloy Castings LimitedProsenjit Sengupta08/10/2025
CC12503645Wheelabrator Alloy Castings LimitedReshma Ramesh Sangare13/10/2025
CC12503956Wheelabrator Alloy Castings LimitedParvez Peer Mohammed Shaikh11/11/2025
CC12504196Wheelabrator Alloy Castings LimitedChandan Kumar Singh27/11/2025
CC12504208Wheelabrator Alloy Castings LimitedRahul Raju Kuril28/11/2025
CC12600948Neeraj SharmaWheelabrator Alloy Castings Limited21/02/2026
CC12605082Sharad Rajesaheb PawalWheelabrator Alloy Castings Limited09/08/2026
CC12602168SWAPNIL SOPAN SURKULEWheelabrator Alloy Castings Limited13/04/2026
CC12602375Wheelabrator Alloy Castings LimitedShobha Shankar Gudise22/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Feb 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Jul 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Apr 2025

Documents filed1283

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 1,283 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A_2025-26.pdf24 Aug 2026
Withdrawal Update Form 1File: Form 1 - Runwal Forest T9 to T11 - 30 June 2026.pdf18 Jul 2026
Withdrawal Update Form 2File: Form 2 - Runwal Forest - 9 to 11 - 30 June 2026.pdf18 Jul 2026
Withdrawal Update Form 3File: Form 3 - Runwal Forest - 9 to 11 - 30 June 2026.pdf18 Jul 2026
Commencement certificateFile: Runwal Forest - Full CC - T11 upto 54 Floors - 21 April 2026.pdf2 Jul 2026
Withdrawal Update Form 1File: Runwal Forest form 1.pdf20 Apr 2026
Withdrawal Update Form 1File: Runwal Forest form 1.pdf20 Apr 2026
Withdrawal Update Form 1File: Runwal Forest form 1.pdf20 Apr 2026
Withdrawal Update Form 1File: Runwal Forest form 1.pdf20 Apr 2026
Withdrawal Update Form 1File: Runwal Forest form 1.pdf20 Apr 2026
Withdrawal Update Form 1File: Runwal Forest form 1.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 - Runwal Forest 9 to 11 - 31 March 2026_11zon.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 - Runwal Forest 9 to 11 - 31 March 2026_11zon.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf20 Apr 2026
Withdrawal Update Form 3File: Forest - Form 3 - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Forest - Form 3 - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Forest - Form 3 - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Forest - Form 3 - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Forest - Form 3 - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Forest - Form 3 - 31 March 2026.pdf20 Apr 2026
Form 1File: Form 1 - Runwal Forest 9 to 11 - 31 December 2025.pdf17 Jan 2026
Form 2File: Form 2 - Runwal Forest-9 to 11 - 31 December 2025.pdf17 Jan 2026
Form 3File: Form 3 - Forest - 9 to 11 - 31 December 2025.pdf17 Jan 2026
Disclosure of Sold and Booked InventoryFile: Inventory - Runwal Forest - T9 to T 11 - 31 December 2025_11zon.pdf17 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration - Runwal Forest.pdf17 Jan 2026
Form 1File: Runwal Forest T9 to T11 - Form 1 - 30 Septemeber 2025.pdf18 Oct 2025
Form 2File: Runwal Forest-T9 to T11 - Form 2 Engineering Certificate - 30 September 2025.pdf18 Oct 2025
Form 3File: Forest - Form 3 - Form 3 - 30 September 2025.pdf18 Oct 2025
Disclosure of Sold and Booked InventoryFile: Runwal Forest 9 to 11 Inventory - 30 September 2027_11zon.pdf18 Oct 2025
Self-declaration of Quarterly ProgressFile: Runwal Forest - 9 to 11.pdf18 Oct 2025
Form 2A (FY 2024-2025)File: Runwal Forest - Form 2A - Quality Assurance Certificate - 30 September 2025.pdf14 Oct 2025
Form 5 (FY 2024-2025)File: WACL - T9 to T11 - Form 5 - April 2024 to March 2025 - 30 Septemeber 2025.pdf13 Oct 2025
Form 1File: Runwal Forest - 9 to 11 - P51800001137 - Form 1 - 1 April 2025 to 30 June 2025.pdf18 Jul 2025
Form 2File: Runwal Forest - Form 2 - 30 June 2025.pdf18 Jul 2025
Form 3File: Forest - Form 3 - 30 June 2025.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - Forest - 9 to 11 - P51800001137 - as on 30 June 2025.pdf18 Jul 2025
Self-declaration of Quarterly ProgressFile: Declaration - WACL.pdf18 Jul 2025
Form 1File: Runwal Forest_T9-11_2025_03_Signed.pdf9 Jun 2025
Form 2File: Runwal Forests - Engineering Certificate Mar'25.pdf9 Jun 2025
Form 3File: Form 3 Runwal Forest 9-11- 31 March 2025.pdf9 Jun 2025
Disclosure of Sold and Booked InventoryFile: Runwal Forest 9 to 11_11zon (1).pdf9 Jun 2025
Self-declaration of Quarterly ProgressFile: Runwal Forest 9 to 11_11zon (1).pdf9 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Runwal Forest - 9 to 11 - Form 1 - 31 March 2025.pdf19 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Runwal Forests - Engineering Certificate Mar'25.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Runwal Forest 9 to 11_11zon.pdf16 Apr 2025
Certificates of CA (Form 3)File: Form 3 Runwal Forest 9 to 11- 31 March 2025.pdf15 Apr 2025
Building plan approvalFile: Plan - RERA Forest - T9 Layout Plan.pdf8 Apr 2025
Building plan approvalFile: Plan - RERA Forest - T9 Basement 1 level plan.pdf8 Apr 2025
Building plan approvalFile: Plan - RERA Forest - T9 Basement 2 level plan.pdf8 Apr 2025
Building plan approvalFile: Plan - RERA Forest - T9 Basement 3 level plan.pdf8 Apr 2025
Building plan approvalFile: Plan - RERA Forest - T9 Ground and Typical plan.pdf8 Apr 2025
Building plan approvalFile: Plan - RERA Forest - T9 Ground Level Plan.pdf8 Apr 2025
Building plan approvalFile: Plan - RERA Forest - T9 Section Plan.pdf8 Apr 2025
Building Plan Approval (IOD)File: Plan - RERA Forest - T9 Layout Plan.pdf8 Apr 2025
Building Plan Approval (IOD)File: Plan - RERA Forest - T9 Basement 1 level plan.pdf8 Apr 2025
Building Plan Approval (IOD)File: Plan - RERA Forest - T9 Basement 2 level plan.pdf8 Apr 2025
Building Plan Approval (IOD)File: Plan - RERA Forest - T9 Basement 3 level plan.pdf8 Apr 2025
Building Plan Approval (IOD)File: Plan - RERA Forest - T9 Ground and Typical plan.pdf8 Apr 2025
Building Plan Approval (IOD)File: Plan - RERA Forest - T9 Ground Level Plan.pdf8 Apr 2025
Building Plan Approval (IOD)File: Plan - RERA Forest - T9 Section Plan.pdf8 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Runwal Forest - Tower 9 - Part OC till 45 Floors - 7 April 2025.pdf8 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: Forest - Further CC - 25 March 2025 - T10 and T11.pdf25 Mar 2025
Building plan approvalFile: Approved Drawing_1-1.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_2-2.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_3-3.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_4-4.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_5-5.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_6-6.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_7-7.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_8-8.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_8-8.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_8-8.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_9-9.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_10-10.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_11-11.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_12-12.pdf19 Feb 2025
Building plan approvalFile: Approved Drawing_13-13.pdf19 Feb 2025

How this compares with Mumbai Suburban

97%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Runwal Forests Tower 9 - 11 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhandup(W)6,700+ in Mumbai Suburban

2 kmRunwal Forests Tower 9 -Completed 40Lapsed / revoked 22Other 76Dot size: filed unitsN

Filed coordinates, straight-line distance. 138 registered projects within 2 km.

Builder: Wheelabrator Alloy Castings Limited

Wheelabrator Alloy Castings Limited has 3 registrations on MahaRERA, including Runwal Forest Tower 1-4 and Runwal Forests Tower 5-8. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Runwal Forests Tower 9 - 11 is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Runwal Forests Tower 9 - 11?

The registered promoter entity is Wheelabrator Alloy Castings Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Runwal Forests Tower 9 - 11?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Runwal Forests Tower 9 - 11?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Runwal Forests Tower 9 - 11?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Runwal Forests Tower 9 - 11?

The professionals named in the filing: Architect: Aakar Architects & Consultants; Architect: Amit A Wasrani & Associates; Engineer: Epicons Consultant Pvt. Ltd. Structural Architect; Engineer: Uttam Kawathankar; Chartered Accountant: Kshirsagar & Associates; Chartered Accountant: M B Agarwal and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Runwal Forests Tower 9 - 11?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Runwal Forests Tower 9 - 11. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Runwal Forests Tower 9 - 11 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.