Sanjeevani Vyapaar LLP: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
Sanjeevani Vyapaar LLP has 1 registration in this build, including AVANTE. Its filings disclose 10 earlier MahaRERA projects: 2 of 9 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| AVANTE | Mumbai Suburban, Maharashtra | 383 | 99% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| VASANT GARDEN | 31 Mar 2007 | 1 Dec 2007 | +8 months |
| VASANT VALLEY | 30 Jun 2010 | 9 Dec 2010 | +5 months |
| VASANT GALAXY | 31 Oct 2010 | 30 Mar 2011 | +5 months |
| CYNERGY | 8 Sep 2011 | 8 Sep 2011 | On time |
| VASANT MARVEL | 31 Oct 2011 | 12 Jul 2012 | +8 months |
| BEAUMONDE | 31 Dec 2011 | 10 Jan 2012 | On time |
| Vasant Lawns | 31 Mar 2012 | 12 Nov 2013 | +19 months |
| VIVIANA MALL | 9 May 2013 | 9 May 2013 | On time |
| SIGMA | 30 Jul 2014 | 15 Dec 2014 | +5 months |
| AVANTE P51800001140 | 31 Dec 2024 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify Sanjeevani Vyapaar LLP as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Sanjeevani Vyapaar LLP?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.