Sugee Vaayu

By Sugee Developers Private Limited

RG-MH-06987 · RERA P51800053945 · Last updated on MahaRERA portal: 25 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken
  • Rs 379.65 crore secured on the land, in favour of SBICAP Trustee Company Ltd
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2031Possession promisedmoved 24 months from the original
2 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
546 of 546Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 172 documents Report an error

Sugee Vaayu is a Others project by Sugee Developers Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800053945 on 11 Dec 2023. Possession is promised by 31 Dec 2031. The completion date has moved by 24 months from the original filing. 0 of the 546 units on this registration are recorded sold or booked, and 2 of 22 construction stages are filed complete.

At a glance

Project

  • NameSugee Vaayu
  • TypeOthers
  • Location
    • Village Mulund at ACC Road
    • Mulund (W)
    • Mumbai
    • Mulund
    • Kurla
    • Mumbai Suburban
    • 400078
  • Pincode400078
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800053945
  • ReraGenie IDRG-MH-06987

Builder

  • NameSugee Developers Private Limited
  • Entity typeCompany
  • DirectorsNitin Pratap Salunkhe, Nishant Subhash Deshmukh, Pritesh Mangilal Jain
  • Other registrations2 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredDec 2023First promiseDec 2029Revised toDec 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Dec 2023
  • Promised completion31 Dec 2031
  • Revised completionRevised to 31 Dec 2031 (originally 31 Dec 2029)
  • Buildings2 building records
  • Documents filed172 files

Current status

0%0 of 546 units booked
3.2%Work done, per cost certificate

Figures as on 25 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A NA56543871388
Tower B NA31291535158

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 25 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

Tower A9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower B9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed710

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots710
Closed/Covered710
BuildingClosed/CoveredTotal
Tower A355355
Tower B355355

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area10,070 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofSBICAP Trustee Company Ltd
Secured amountRs 379.65 crore
CERSAI search filedYes
Declared on25 Aug 2026

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority, Mumbai
Permissible FSI52372.08
Proposed, not sanctioned30,763 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPlot No 1, Sion Trombay Road, Hotel Bahri Residency, Diamond Garden, Chembur, Dist Mumbai
Estimated costRs 539.97 cr
Cost incurredRs 17.22 cr
Work done3.19%
BuildingWingEstimatedIncurred
Tower ANARs 269.99 crRs 8.61 cr
Tower BNARs 269.99 crRs 8.61 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr. Sanjay Neve of M/s. Sanjay Neve & Associates
EngineerMr. Ravindra Dattatraya Deshpande
EngineerHarold Pereira
Chartered AccountantCA Pratik D. Jain
Chartered AccountantMeisheri Palani & Company
Chartered AccountantSachin K. Mishra & Co.
PartnerRole in project
Sugee Developers Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA21022619941Dec 2029 → Dec 2031

Reason as filed by the promoterThe Promoter submits that the construction timeline of the project has been affected due to changes in the sanctioned plan involving revision in F.S.I. utilization and addition of upper floors. The correction is already approved by the RERA Authority.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2031

Documents filed172

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 172 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_March 26.pdf25 May 2026
Withdrawal Update Form 2File: Form 2_March 26.pdf25 May 2026
Withdrawal Update Form 3File: Form 3_Mar 26.pdf25 May 2026
Withdrawal Update Form 1File: Form 1_Dec 2025.pdf11 Feb 2026
Withdrawal Update Form 2File: Form 2_Dec 25.pdf11 Feb 2026
Withdrawal Update Form 3File: Form 3_December 2025.pdf11 Feb 2026
Withdrawal Update Form 1File: Form 1_Dec 2025.pdf7 Feb 2026
Withdrawal Update Form 2File: Form 2_Dec 25.pdf7 Feb 2026
Withdrawal Update Form 3File: Form 3_December 2025.pdf7 Feb 2026
Withdrawal Update Form 1File: Form 1_Dec 2025.pdf6 Feb 2026
Withdrawal Update Form 2File: Form 2_Dec 25.pdf6 Feb 2026
Withdrawal Update Form 3File: Form 3_December 2025.pdf6 Feb 2026
Layout approvalFile: Revised Layout Approval Plan.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 1.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 2.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 3.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 4.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 5.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 6.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 7.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 8.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 9.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 10.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 11.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 12.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 13.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 14.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 15.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 16.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 17.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 18.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 19.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 20.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 21.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 22.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 23.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 24.pdf21 Jan 2026
Layout approvalFile: Revised Sanctioned Plan 25.pdf21 Jan 2026
Withdrawal Update Form 1File: Form 1_Dec 2025.pdf19 Jan 2026
Withdrawal Update Form 1File: Form 1_Dec 2025.pdf19 Jan 2026
Withdrawal Update Form 2File: Form 2_Dec 25.pdf19 Jan 2026
Withdrawal Update Form 2File: Form 2_Dec 25.pdf19 Jan 2026
Withdrawal Update Form 3File: Form 3_Dec 25.pdf19 Jan 2026
Withdrawal Update Form 3File: Form 3_Dec 25.pdf19 Jan 2026
Form 2A (FY 2023-2024)File: Form 2A March 24.pdf10 Dec 2025
Form 2A (FY 2024-2025)File: Form 2A March 25.pdf10 Dec 2025
Form 1File: RERA 1 as on 310325.pdf8 Dec 2025
Form 2File: RERA Form 2 as on 310325 (1).pdf8 Dec 2025
Form 3File: RERA Form 3 as on 31032025 Greendale.pdf8 Dec 2025
Disclosure of Sold and Booked InventoryFile: march 25.pdf8 Dec 2025
Form 1File: RERA 1 as on 300625 (1) (1).pdf8 Dec 2025
Form 2File: RERA Form 2 as on 300625 (1).pdf8 Dec 2025
Form 3File: RERA Form 3 as on 30062025 Greendale.pdf8 Dec 2025
Disclosure of Sold and Booked InventoryFile: june 25.pdf8 Dec 2025
Form 1File: RERA 1 as on 300925 (1) (1).pdf8 Dec 2025
Form 2File: RERA Form 2 as on 300925 (1).pdf8 Dec 2025
Form 3File: RERA Form 3 as on 30092025 Greendale.pdf8 Dec 2025
Disclosure of Sold and Booked InventoryFile: sep 25.pdf8 Dec 2025
Form 5 (FY 2023-2024)File: RERA Form 5 For FY 23-24- Greendale.pdf8 Dec 2025
Form 5 (FY 2024-2025)File: CA form 5 FY 24-25- Greendale.pdf8 Dec 2025
Form 1File: Form 1 Greendale.pdf1 Dec 2025
Form 2File: Form 2 Greendale.pdf1 Dec 2025
Form 3File: Form 3 Greendale .pdf1 Dec 2025
Disclosure of Sold and Booked InventoryFile: dec 23.pdf1 Dec 2025
Form 1File: Form 1 for March 2024.pdf1 Dec 2025
Form 2File: Form 2 for March 2024.pdf1 Dec 2025
Form 3File: Form 3 for March 2024.pdf1 Dec 2025
Disclosure of Sold and Booked InventoryFile: march 24.pdf1 Dec 2025
Form 1File: Form 1 for 30062024.pdf1 Dec 2025
Form 2File: RERA Form 2 30062024- Greendale Estates.pdf1 Dec 2025
Form 3File: RERA Form 3 as on 30062024- Greendale Estates.pdf1 Dec 2025
Disclosure of Sold and Booked InventoryFile: june 24.pdf1 Dec 2025
Form 1File: RERA Form 1 for 30092024.pdf1 Dec 2025
Form 2File: Form 2 as on 30092024.pdf1 Dec 2025
Form 3File: Form 3 as on 30092024.pdf1 Dec 2025
Disclosure of Sold and Booked InventoryFile: sep 24.pdf1 Dec 2025
Form 1File: Form for December 2024 (Greendale Estate).pdf1 Dec 2025
Form 2File: RERA Form 2 as on 31122024 Greendale.pdf1 Dec 2025
Form 3File: RERA Form 3 as on 31122024- Greendale.pdf1 Dec 2025
Disclosure of Sold and Booked InventoryFile: dec 24.pdf1 Dec 2025

How this compares with Mumbai Suburban

0%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sugee Vaayu on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund (W), Mumbai6,700+ in Mumbai Suburban

2 kmSugee VaayuCompleted 93Lapsed / revoked 82Other 114Dot size: filed unitsN

Filed coordinates, straight-line distance. 289 registered projects within 2 km.

Builder: Sugee Developers Private Limited

Sugee Developers Private Limited has 3 registrations on MahaRERA, including Sugee Vaayu and Shree Krishnakunj. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Sugee Vaayu is delayed beyond 31 Dec 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sugee Vaayu?

The registered promoter entity is Sugee Developers Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sugee Vaayu?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sugee Vaayu?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sugee Vaayu?

The professionals named in the filing: Architect: Mr. Sanjay Neve of M/s. Sanjay Neve & Associates; Engineer: Mr. Ravindra Dattatraya Deshpande; Engineer: Harold Pereira; Chartered Accountant: CA Pratik D. Jain; Chartered Accountant: Meisheri Palani & Company; Chartered Accountant: Sachin K. Mishra & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sugee Vaayu?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sugee Vaayu. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sugee Vaayu to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.