ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / AURA APARTMENTS - PHASE 2 11TH FLOOR

Completed No litigation declared Residential / Group Housing project

AURA APARTMENTS - PHASE 2 11TH FLOOR

By BHOLENATH DEVELOPERS LTD.

RG-MH-25977 · RERA P51800009179 · Last updated on MahaRERA portal: 31 May 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 62 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

AURA APARTMENTS - PHASE 2 11TH FLOOR is a Residential / Group Housing project by BHOLENATH DEVELOPERS LTD. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009179 on 19 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2023. The completion date has moved by 62 months from the original filing.

At a glance

Project

  • NameAURA APARTMENTS - PHASE 2 11TH FLOOR
  • TypeResidential / Group Housing
  • Location
    • GHATLA ROAD
    • GHATLA
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009179
  • ReraGenie IDRG-MH-25977

Builder

  • NameBHOLENATH DEVELOPERS LTD.
  • Entity typeCompany
  • Managing DirectorANIL L SAJNANI
  • Other registrations3 more →
  • Completed4 of 4

Key dates

this monthRegisteredAug 2017First promiseOct 2018Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Oct 2018)
  • Buildings1 building record
  • Documents filed64 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AURA APARTMENTSNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

AURA APARTMENTS: 55% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 31 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered25

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,278 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI168.25
Proposed, not sanctioned168 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 95C TOLARAM SHOPPING CENTRE NGA MARG CHEMBUR EAST MUMBAI 71

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectsunildutt Yadav
ArchitectB H WADHWA & CO
EngineerSunildutt Shyamdev Yadav
EngineerPARAS CONSULTANT
Chartered AccountantCHANDAK AGARWAL & CO
Chartered AccountantH P CHAUDHARY & CO
Chartered AccountantKAILASH CHAN JAIN & CO
Chartered AccountantK C JAIN KALA & CO
PartnerRole in project
BHOLENATH DEVELOPERS LTD.-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000647Oct 2018 → Oct 2020

Reason as filed by the promoterM/s. Bholenath Developers Ltd., had entered in agreement with Sach Atma Co.op.H.S.Ltd., for redevelopment of existing residential building at above site comprising of 24 tenements. Development Agreement was entered between Society and Developers on 14.05.2009. Building plans were approved under No. CE/6421/BPES/AM dated 01.02.2010 and last plan were approved on 06.01.2012 for the building comprising of Stilt + Podium + 11 upper floors and full C.C. had been granted as per last amended plans on 31.01.2012. The stage of construction as on today comprises of R.C.C. work completed for entire build

EXT51800002502Oct 2018 → Oct 2020

Reason as filed by the promoterThe Above mentioned Project is complete and application for the grant of OC has been made by architect. We request you to grant us maximum extension of one year. We assure you that once we receive the OC the same will be uploaded on the MAHARERA website.

EXT51800009793Oct 2018 → Jun 2022

Reason as filed by the promoterFile was put-up for Occupation Certificate but was delayed due to lockdown and it is to be now put-up again to be processed further

EXT51800013009Oct 2018 → Dec 2023

Reason as filed by the promoterThe file was put-up for Occupation Certificate but occupation certificate not obtained and its final process of obtaining

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 31 May 2023

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4.pdf31 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Copy.pdf31 May 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf31 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: AURA Certification Signed.pdf21 Apr 2023
Building plan approvalFile: AURA 2PHASE.pdf13 Apr 2023
Building Plan Approval (IOD)File: AURA 2PHASE.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 ENGINEERS CERTIFICATE 300919.pdf3 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 ENGINEERS CERTIFICATE 310320.pdf3 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 ENGINEERS CERTIFICATE 310321.pdf3 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 ENGINEERS CERTIFICATE 310322.pdf3 Feb 2023
Building plan approvalFile: Highlighted jan 2023 for RERA Approved Plan September 2022_compressed.pdf17 Jan 2023
Building Plan Approval (IOD)File: Highlighted jan 2023 for RERA Approved Plan September 2022_compressed.pdf17 Jan 2023
Disclosure of sold/ booked inventoryFile: Circular.pdf17 Jan 2023
PAN CardFile: BDPL pan card.pdf11 Jan 2023
Declaration about Commencement CertificateFile: Form D.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2a.pdf11 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: aura form 5 18-19.pdf11 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: aura form 5 20- 21.pdf11 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 AURA.pdf11 Jan 2023
Proforma of Agreement for saleFile: agreement.pdf11 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certificate sachatma.pdf23 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality_Assurance_Certificate_-_FORM_2_-10-04-2019 AURA.pdf23 Jun 2021
Certificates of CA (Form 3)File: Form3.pdf23 Jun 2021
Certificates of CA (Form 5)File: Form5-.pdf23 Jun 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf12 Jun 2021
Certificates of CA (Form 5)File: Form_5_-_Aura_Project_2019.pdf19 Oct 2019
Certificates of CA (Form 3)File: Form3_CA_Certificate_Aura.pdf14 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_Aura.pdf26 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engineer_Certificate_Aura.pdf26 Jul 2019
Form 2AFile: Form2A_Quality_Assurance_Certificate_Aura.pdf26 Jul 2019
OtherFile: Revision of information Aura - RERA.pdf26 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_Aura.pdf13 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engineer_Certificate_Aura.pdf13 Apr 2019
Form 2AFile: Form2A_Quality_Assurance_Certificate_Aura.pdf13 Apr 2019
Certificates of CA (Form 3)File: Form3_CA_Certificate_Aura.pdf2 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_Aura.pdf14 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engineer_Certificate_Aura.pdf14 Jan 2019
Form 2AFile: Form2A_Quality_Assurance_Certificate_Aura_Jan2019.pdf14 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Architect_Certificate_Aura.pdf28 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Engineer_Certificate_Aura.pdf28 Dec 2018
Certificates of CA (Form 3)File: Form3_CACertificate_Aura.pdf28 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate_-_Form_1_AURA.pdf23 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate_-_Form_2_AURA.pdf23 Oct 2018
Certificates of CA (Form 3)File: FORM_3_AURA.pdf23 Oct 2018
Certificates of CA (Form 5)File: Form_5_-_Aura_Project.pdf23 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_-_Aura.pdf18 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_-_Aura.pdf18 Jun 2018
Certificates of CA (Form 3)File: Form_3_-_Aura.pdf18 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Aura.pdf15 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate Aura-min.pdf15 Feb 2018
Certificates of CA (Form 3)File: Form 3 CA Certificate Aura.pdf15 Feb 2018
Certificates of CA (Form 3)File: Form 3 - CA Certificate - Aura.pdf30 Jul 2017
Proforma of Allotment letterFile: Proforma Allotment Letter - Aura.pdf30 Jul 2017
Proforma of Allotment letterFile: Proforma Agreement for Sale - Aura.pdf30 Jul 2017
Layout approvalFile: Layout Declaration letter - Aura.pdf28 Jul 2017
Building plan approvalFile: Aura - IOD.pdf28 Jul 2017
Copy of the legal title reportFile: Aura - Title Certificate.pdf28 Jul 2017
Details of encumbrancesFile: Aura - Self Declaration for Encumbrances.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Declaration letter - Aura.pdf28 Jul 2017
Building Plan Approval (IOD)File: Aura - IOD.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Aura - Commencement Certificate.pdf28 Jul 2017
Declaration in FORM BFile: Aura_FORM_B.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect - Estimated Cost of Construction.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate - Aura.pdf28 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 62 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AURA APARTMENTS - PHASE 2 11TH FLOOR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GHATLA6,700+ in Mumbai Suburban

2 kmAURA APARTMENTS - PHASE Completed 149Lapsed / revoked 113Other 134Dot size: filed unitsN

Filed coordinates, straight-line distance. 396 registered projects within 2 km.

Builder: BHOLENATH DEVELOPERS LTD.

BHOLENATH DEVELOPERS LTD. has 4 registrations on MahaRERA, including AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. and ZEN APARTMENTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if AURA APARTMENTS - PHASE 2 11TH FLOOR is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AURA APARTMENTS - PHASE 2 11TH FLOOR?

The registered promoter entity is BHOLENATH DEVELOPERS LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AURA APARTMENTS - PHASE 2 11TH FLOOR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AURA APARTMENTS - PHASE 2 11TH FLOOR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AURA APARTMENTS - PHASE 2 11TH FLOOR?

The professionals named in the filing: Architect: sunildutt Yadav; Architect: B H WADHWA & CO; Engineer: Sunildutt Shyamdev Yadav; Engineer: PARAS CONSULTANT; Chartered Accountant: CHANDAK AGARWAL & CO; Chartered Accountant: H P CHAUDHARY & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AURA APARTMENTS - PHASE 2 11TH FLOOR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AURA APARTMENTS - PHASE 2 11TH FLOOR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AURA APARTMENTS - PHASE 2 11TH FLOOR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.