Home / Browse projects / Mumbai Suburban, Maharashtra / AUBBURN WING C

Registered Litigation declared Residential / Group Housing project

AUBBURN WING C

By S D CORPORATION PRIVATE LIMITED

RG-MH-28355 · RERA P51800026064 · Last updated on MahaRERA portal: 6 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 4 complaints at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken
  • Rs 100.00 crore secured on the land, in favour of JM Financial Credit Solutions Limited

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 36 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 87%
2 of 97Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 105 documents Report an error

AUBBURN WING C is a Residential / Group Housing project by S D CORPORATION PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800026064 on 15 Aug 2020. Possession is promised by 30 Jun 2027. The completion date has moved by 36 months from the original filing. 95 of the 97 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameAUBBURN WING C
  • TypeResidential / Group Housing
  • Location
    • THAKUR VILLAGE ROAD
    • KANDIVALI
    • Borivali
    • Mumbai Suburban
    • 400101
  • Pincode400101
  • RERA no.P51800026064
  • ReraGenie IDRG-MH-28355

Builder

  • NameS D CORPORATION PRIVATE LIMITED
  • Entity typeCompany
  • CINU70109MH1998PTC116091
  • GSTIN27AADCS4496C1Z9
  • DirectorSrinivasan Iyer
  • Other registrations14 more →
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2020First promiseJun 2024Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Aug 2020
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed105 files

Current status

98%95 of 97 units booked
82.2%Work done, per cost certificate

Figures as on 6 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AUBBURN WING CNA222197097

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 87%.

AUBBURN WING C: 44% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure87%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered20

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area400 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofJM Financial Credit Solutions Limited
Secured amountRs 100.00 crore
CERSAI search filedYes
Declared on29 Dec 2025

Approvals and building plan

Sanctioning authorityMaharashtra Housing and Area Development Authority
Permissible FSI5582.64
Proposed, not sanctioned584 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch240 NAVSARI BUILDING D N ROAD FORT MUMBAI MAHARASHTRA 400001
Estimated costRs 32.75 cr
Cost incurredRs 26.93 cr
Work done82.22%
BuildingWingEstimatedIncurred
AUBBURN WING CNARs 32.75 crRs 26.93 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANIL KODKANI
ArchitectNewtech Planners & Consultancy Services Private Limited
EngineerJ W CONSULTANTS LLP
EngineerAaba Borse
Chartered AccountantB R NAGDA AND COMPANY
Chartered AccountantHarshad Doshi & Co.
PartnerRole in project
S D CORPORATION PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009451Jun 2024 → Jun 2025

Reason as filed by the promoterThe proposed date of completion of the project given on RERA is 30th June, 2024. However, the construction of the project could not commence on account of the present situation of COVID 19 Pandemic. In view of the reason cited above, we are proposing to extend the project completion period for further period of 12 months. The revised proposed date of completion is 30th June, 2025.

EA30122519125Jun 2024 → Jun 2027

Reason as filed by the promoterDue to onslaught of Covid-19 pandemic, there was an unprecedented reverse migration of labour force from the State of Maharashtra, and we witnessed the same trend at our construction site during Covid-19 period. The strength of labour force on site dwindled in the wake of Covid19. b) Even the periodic directives from the Government authority offering relaxation for restarting the work did not help us, as the migrated labours could not return to site due to various restrictions imposed by different states in travelling including mandatory RTPCR Test & 15 days quarantine during Covid-19 period.

Litigation declared2

CaseCourtStatus
1267 /2009HIGH COURT BOMBAYPENDING FOR FINAL HEARING
1267/2009Bombay High CourtOngoing

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12602103Shilpa Vishal SolankiS D CORPORATION PRIVATE LIMITED10/04/2026
CC12604576Amit Sunil PanchalS D CORPORATION PRIVATE LIMITED21/07/2026
CC12604618Sagar Mohan JadhavS D CORPORATION PRIVATE LIMITED23/07/2026
CC12604993RUTVIK RAMKRISHNA SHINDES D CORPORATION PRIVATE LIMITED06/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Oct 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jun 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jan 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jun 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed105

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate Aubburn C.pdf6 Jul 2026
Withdrawal Update Form 2File: Engineer Certificate- Aubburn C-Mar 26.pdf6 Jul 2026
Withdrawal Update Form 3File: Aubburn Wing C Form 3 March 26.pdf6 Jul 2026
Form 2A (FY 2023-2024)File: Aubburn Wing C June 24.pdf6 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A Aubburn wing C Sep 2024.pdf6 Jul 2026
Form 2A (FY 2022-2023)File: Aubburn Wing C Dec 23.pdf6 Jul 2026
Form 2A (FY 2021-2022)File: Aubburn Wing C Dec 23.pdf6 Jul 2026
Form 2A (FY 2020-2021)File: Aubburn Wing C Dec 23.pdf6 Jul 2026
Form 2A (FY 2026-2027)File: Form 2A (7).pdf6 Jul 2026
Withdrawal Update Form 1File: Architect cert Aubburn C Dec 25.pdf1 Jul 2026
Withdrawal Update Form 1File: Architect Certificate Aubburn C.pdf1 Jul 2026
Withdrawal Update Form 2File: Engineer Certificate Aubburn C Dec 25.pdf1 Jul 2026
Withdrawal Update Form 2File: Engineer Certificate- Aubburn C-Mar 26.pdf1 Jul 2026
Withdrawal Update Form 3File: Aubburn Wing C Form 3 Dec 2025.pdf1 Jul 2026
Withdrawal Update Form 3File: Aubburn Wing C Form 3 March 26.pdf1 Jul 2026
Withdrawal Update Form 1File: Architect cert Aubburn C Dec 25.pdf30 Jun 2026
Withdrawal Update Form 2File: Engineer Certificate Aubburn C Dec 25.pdf30 Jun 2026
Withdrawal Update Form 3File: Aubburn Wing C Form 3 Dec 2025.pdf30 Jun 2026
Form 1File: Architect cert Aubburn Wing C 30-Sep-25.pdf29 Dec 2025
Form 2File: Engineer Certificate- Aubburn C-Sep 25.pdf29 Dec 2025
Form 3File: 202509 Aubburn Wing C Form 3.pdf29 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - Aubburn C Sept 25.pdf29 Dec 2025
Form 5 (FY 2024-2025)File: aubbernb2425.pdf27 Dec 2025
Form 5 (FY 2023-2024)File: aubbernc2324.pdf27 Dec 2025
Form 2A (FY 2024-2025)File: Form 2A Aubburn Wing C.pdf26 Dec 2025
Form 1File: Architect cert Aubburn Wing C 30-Jun-25.pdf22 Dec 2025
Form 2File: Engineer Certificate- Aubburn C-Jun 25.pdf22 Dec 2025
Form 3File: Aubburn Wing C Form 3 June 2025.pdf22 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory Aubburn C June 25.pdf22 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Aubburn Wing C Sep 2024.pdf12 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Aubburn wing C Jun 2024.pdf9 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate Bldg No 5 Wing I.pdf3 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert Aubburn C 31 03 2023.pdf15 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Aubburn C.pdf12 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Aubburn C.pdf12 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Aubburn Wing C.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B5 Wing I Cft.pdf18 May 2023
Disclosure of sold/ booked inventoryFile: Aubburn C Disclosure Of Sold.pdf18 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Aubburn Wing C Dec-22.pdf12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B5 Wing I Cft.pdf10 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aubburn Wing C - Form 3 - Sept-22.pdf3 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Aubburn C WIng Form 5 - Mar-22 (2).pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B5 Wing I.pdf19 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aubburn Wing C.pdf21 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Aubburn C.pdf21 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Samata Nagar Bldg No 5 (Wing I) RERA Architect Certificate.pdf14 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Aubburn C.pdf14 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202203 Aubburn Wing C Form 3.pdf14 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202206 Aubburn Wing C Form 3.pdf14 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aubburn Wing C.pdf9 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Aubburn Wing C.pdf21 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Aubburn - Wing C.pdf21 Jun 2022
Disclosure of sold/ booked inventoryFile: RERA - Aubburn Wing C - Disclosure of Inventory - Mar 31, 2022.pdf27 Apr 2022
Details of encumbrancesFile: Index II - KKR Supplementary.pdf28 Mar 2022
Details of encumbrancesFile: Index II - KKR.pdf28 Mar 2022
OtherFile: Office Note - B5 Concession.pdf7 Mar 2022
OtherFile: 18 FEB 2021_Layout plan.pdf7 Mar 2022
OtherFile: Grant Conc Bldg 05.pdf7 Mar 2022
OtherFile: B5 Concession plan.pdf7 Mar 2022
Disclosure of sold/ booked inventoryFile: Aubburn C.pdf27 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance certificate - Aubburn Wing C Dec 2021.pdf10 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Aubburn Wing C.pdf23 Dec 2021
Disclosure of sold/ booked inventoryFile: Aubburn C.pdf8 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Wing C Aubburn.pdf6 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate Aubburrn C.pdf6 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Aubburn C June 21.pdf13 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Bldg No 5 Wing C Aubburn June 2021.pdf6 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC Aubburn Wing C June 2021.pdf6 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QAC Aubburn Wing C June 2021.pdf6 Aug 2021
Disclosure of sold/ booked inventoryFile: Aubburn Wing C RERA Disclosure of inventory Mar 2021.pdf9 Jul 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Aubburn C March 2021.pdf1 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance AUBBURN WING C March 21.pdf1 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Aubburn C March 21.pdf1 Jun 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Aubburn Wing C March 21.pdf15 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Aubburn C Dec 20.pdf10 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Wing C December 2021.pdf10 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate For Bldg No 5 Wing I 31 12 2020.pdf25 Jan 2021
Building plan approvalFile: Amended IOD 14 Sept 2020 1.pdf13 Jan 2021
Building plan approvalFile: Amended IOD 14 Sept 2020 2.pdf13 Jan 2021
Building Plan Approval / NA Order for plotted developmentFile: Amended IOD 14 Sept 2020 1.pdf13 Jan 2021

How this compares with Mumbai Suburban

98%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 36 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AUBBURN WING C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANDIVALI6,700+ in Mumbai Suburban

Builder: S D CORPORATION PRIVATE LIMITED

S D Corporation Private Limited has 15 registrations on MahaRERA, including SIENNAA WING A and SIENNAA WING B. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 11 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if AUBBURN WING C is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AUBBURN WING C?

The registered promoter entity is S D CORPORATION PRIVATE LIMITED, a company as per the filing. Its CIN U70109MH1998PTC116091 and GSTIN 27AADCS4496C1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AUBBURN WING C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AUBBURN WING C?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AUBBURN WING C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AUBBURN WING C?

The professionals named in the filing: Architect: ANIL KODKANI; Architect: Newtech Planners & Consultancy Services Private Limited; Engineer: J W CONSULTANTS LLP; Engineer: Aaba Borse; Chartered Accountant: B R NAGDA AND COMPANY; Chartered Accountant: Harshad Doshi & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AUBBURN WING C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AUBBURN WING C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AUBBURN WING C to a free account