Home / Browse projects / Mumbai Suburban, Maharashtra / AUBBURN WING A
AUBBURN WING A
By S D CORPORATION PRIVATE LIMITED
RG-MH-28352 · RERA P51800025641 · Last updated on MahaRERA portal: 6 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- 5 complaints at MahaRERA
- Completion date moved by 36 months
- 2 extensions taken
- Rs 100.00 crore secured on the land, in favour of JM Financial Credit Solutions Limited
Clear
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AUBBURN WING A is a Residential / Group Housing project by S D CORPORATION PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800025641 on 1 Jul 2020. Possession is promised by 30 Jun 2027. The completion date has moved by 36 months from the original filing. 48 of the 66 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NameAUBBURN WING A
- TypeResidential / Group Housing
- Location
- THAKUR VILLAGE ROAD
- KANDIVALI
- Borivali
- Mumbai Suburban
- 400101
- Pincode400101
- RERA no.P51800025641
- ReraGenie IDRG-MH-28352
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Jul 2020
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2024)
- Buildings1 building record
- Documents filed100 files
Current status
Figures as on 6 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AUBBURN WING A | NA | 23 | 17 | 66 | 0 | 66 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 87%.
AUBBURN WING A: 44% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 87% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 6 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed41
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| AUBBURN WING A | NA | Rs 42.23 cr | Rs 41.52 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANIL KODKANI |
| Architect | Newtech Planners & Consultancy Services Private Limited |
| Engineer | J W CONSULTANTS LLP |
| Engineer | Aaba Borse |
| Chartered Accountant | B R NAGDA AND COMPANY |
| Chartered Accountant | Bhavesh Ramesh Nagda |
| Chartered Accountant | Harshad Doshi & Co |
| Partner | Role in project |
|---|---|
| S D CORPORATION PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe proposed date of completion of the project given on RERA is 30th June, 2024. However, the construction of the project could not commence on account of the present situation of COVID 19 Pandemic. In view of the reason cited above, we are proposing to extend the project completion period for further period of 12 months. The revised proposed date of completion is 30th June, 2025.
Reason as filed by the promoterDue to onslaught of Covid-19 pandemic, there was an unprecedented reverse migration of labour force from the State of Maharashtra, and we witnessed the same trend at our construction site during Covid-19 period. The strength of labour force on site dwindled in the wake of Covid19. b) Even the periodic directives from the Government authority offering relaxation for restarting the work did not help us, as the migrated labours could not return to site due to various restrictions imposed by different states in travelling including mandatory RTPCR Test & 15 days quarantine during Covid-19 period.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 1267 /2009 | HIGH COURT BOMBAY | PENDING FOR FINAL HEARING |
| 1267/2009 | Bombay High Court | Ongoing |
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12600349 | Sunit Roy | S D CORPORATION PRIVATE LIMITED | 19/01/2026 |
| CC12601027 | SARNAMBAR ROY | S D CORPORATION PRIVATE LIMITED | 25/02/2026 |
| CC12602213 | Rajesh Padmanand Mishra | S D CORPORATION PRIVATE LIMITED | 15/04/2026 |
| CC12604531 | Gaurav Kumar | S D CORPORATION PRIVATE LIMITED | 19/07/2026 |
| CC12605032 | Yusufmiyan Achchhamiyan Syed | S D CORPORATION PRIVATE LIMITED | 07/08/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Oct 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Jun 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Jan 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Jun 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed100
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2023-2024)File: Aubburn A Quality Certificate Dec 2024.pdf | 6 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A Aubburn Wing A.pdf | 6 Jul 2026 |
| Withdrawal Update Form 1File: Architect Certificate Aubburn A March 26.pdf | 30 Jun 2026 |
| Withdrawal Update Form 1File: Architect Certificate Aubburn A March 26.pdf | 30 Jun 2026 |
| Withdrawal Update Form 1File: Architect Certificate Aubburn A March 26.pdf | 30 Jun 2026 |
| Withdrawal Update Form 2File: Engineer Certificate- Aubburn A-Mar 26.pdf | 30 Jun 2026 |
| Withdrawal Update Form 2File: Engineer Certificate- Aubburn A-Mar 26.pdf | 30 Jun 2026 |
| Withdrawal Update Form 2File: Engineer Certificate- Aubburn A-Mar 26.pdf | 30 Jun 2026 |
| Withdrawal Update Form 3File: Aubburn Wing A Form 3 March 26.pdf | 30 Jun 2026 |
| Withdrawal Update Form 3File: Aubburn Wing A Form 3 March 26.pdf | 30 Jun 2026 |
| Withdrawal Update Form 3File: Aubburn Wing A Form 3 March 26.pdf | 30 Jun 2026 |
| Withdrawal Update Form 1File: Architect cert Bldg No 5 Wing G Dt 31 Dec 25.pdf | 25 Jun 2026 |
| Withdrawal Update Form 2File: Engineer Certificate Aubburn A Dec 25.pdf | 25 Jun 2026 |
| Withdrawal Update Form 3File: Aubburn Wing A Form 3 Dec 25.pdf | 25 Jun 2026 |
| Form 1File: Architect cert Aubburn Wing A 30-Sep-25.pdf | 29 Dec 2025 |
| Form 2File: Engineer Certificate- Aubburn A-Sep 25.pdf | 29 Dec 2025 |
| Form 3File: 202509 Aubburn Wing A Form 3.pdf | 29 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - Aubburn A Sept 25.pdf | 29 Dec 2025 |
| Form 5 (FY 2024-2025)File: auba2425.pdf | 27 Dec 2025 |
| Form 5 (FY 2023-2024)File: auba2324.pdf | 27 Dec 2025 |
| Form 2A (FY 2024-2025)File: Form 2A Aubburn wing A.pdf | 26 Dec 2025 |
| Form 3File: Aubburn Wing A Form 3 June 2025.pdf | 22 Dec 2025 |
| Form 1File: Architect cert Aubburn wing A 30-Jun-25.pdf | 22 Dec 2025 |
| Form 2File: Engineer Certificate- Aubburn A-Jun 25.pdf | 22 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Aubburn Wing A Form 3 June 2025.pdf | 22 Dec 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Aubburn Wing A Sep 2024.pdf | 12 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Aubburn wing A Jun 2024.pdf | 9 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate Bldg No 5 Wing G.pdf | 3 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert Aubburn A 31 03 2023.pdf | 15 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Aubburn A.pdf | 12 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Aubburn Wing A.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B5 Wing G Cft.pdf | 18 May 2023 |
| Disclosure of sold/ booked inventoryFile: Aubburn A Disclosure Of Sold.pdf | 18 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Aubburn Wing A Dec-22.pdf | 12 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B5 Wing G Cft.pdf | 10 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aubburn Wing A - Form 3 - Sept-22.pdf | 3 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Aubburn A WIng Form 5 - Mar-22 (2).pdf | 3 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B5 Wing G.pdf | 19 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aubburn Wing A.pdf | 21 Sep 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Aubburn A.pdf | 21 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Samata Nagar Bldg No 5 (Wing G) RERA Architect Certificate.pdf | 14 Sep 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Aubburn A.pdf | 14 Sep 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202203 Aubburn Wing A Form 3.pdf | 14 Sep 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202206 Aubburn Wing A Form 3.pdf | 14 Sep 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aubburn Wing A.pdf | 9 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Aubburn Wing A.pdf | 19 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Aubburn Wing A.pdf | 21 Jun 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Aubburn - Wing A.pdf | 21 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: RERA - Aubburn Wing A - Disclosure of Inventory - Mar 31, 2022.pdf | 27 Apr 2022 |
| Details of encumbrancesFile: Index II - KKR.pdf | 28 Mar 2022 |
| Details of encumbrancesFile: Index II - KKR Supplementary.pdf | 28 Mar 2022 |
| OtherFile: Office Note - B5 Concession.pdf | 7 Mar 2022 |
| OtherFile: 18 FEB 2021_Layout plan.pdf | 7 Mar 2022 |
| OtherFile: Grant Conc Bldg 05.pdf | 7 Mar 2022 |
| OtherFile: B5 Concession plan.pdf | 7 Mar 2022 |
| Disclosure of sold/ booked inventoryFile: Aubburn A.pdf | 27 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance certificate - Aubburn Wing A Dec 2021.pdf | 10 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Aubburn Wing A.pdf | 23 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: Aubburn A.pdf | 8 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Aubburrn Wing A.pdf | 7 Oct 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Wing A Aubburn.pdf | 6 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate Aubburrn A.pdf | 6 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Aubburn A June 21.pdf | 13 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Bldg No 5 Wing A Aubburn June 2021.pdf | 6 Aug 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC Aubburn Wing A June 2021.pdf | 6 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QAC Aubburn Wing A June 2021.pdf | 6 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Aubburn Wing A RERA Disclosure of inventory Mar 2021.pdf | 9 Jul 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Aubburn A March 2021.pdf | 1 Jun 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance AUBBURN WING A March 21.pdf | 1 Jun 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Aubburn A March 21.pdf | 1 Jun 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Aubburn Wing A March 21.pdf | 15 May 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Aubburn A Dec 20.pdf | 10 Mar 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate December 2021.pdf | 10 Mar 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate For Bldg No 5 Wing G 31 12 2020.pdf | 25 Jan 2021 |
| Building plan approvalFile: Amended IOD 14 Sept 2020 1.pdf | 13 Jan 2021 |
| Building plan approvalFile: Amended IOD 14 Sept 2020 2.pdf | 13 Jan 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Amended IOD 14 Sept 2020 1.pdf | 13 Jan 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Amended IOD 14 Sept 2020 2.pdf | 13 Jan 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Aubburn A Sept 20.pdf | 12 Jan 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Aubburn A.pdf | 12 Jan 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 14 other registrations, which the RERA portal never shows together
- All 100 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep AUBBURN WING A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KANDIVALI6,700+ in Mumbai Suburban
Sheetal Uptown
SIDHESHWAR LIFESPACES PRIVATE LIMITED
ENSO SANZA
Sai Aastha Developers
SPRINGWOODS
PRATIK CONSTRUCTION
Godrej Nest
Shivam Megastructures Pvt Ltd
PATON TOWERS
PRAVIN VIRAM SATRA
Godrej Bliss
SHIVAM DEVELOPERS
See every Mumbai Suburban project, with the district possession charts
Builder: S D CORPORATION PRIVATE LIMITED
S D Corporation Private Limited has 15 registrations on MahaRERA, including SIENNAA WING A and SIENNAA WING B. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 11 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if AUBBURN WING A is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AUBBURN WING A?
The registered promoter entity is S D CORPORATION PRIVATE LIMITED, a company as per the filing. Its CIN U70109MH1998PTC116091 and GSTIN 27AADCS4496C1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AUBBURN WING A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AUBBURN WING A?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AUBBURN WING A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AUBBURN WING A?
The professionals named in the filing: Architect: ANIL KODKANI; Architect: Newtech Planners & Consultancy Services Private Limited; Engineer: J W CONSULTANTS LLP; Engineer: Aaba Borse; Chartered Accountant: B R NAGDA AND COMPANY; Chartered Accountant: Bhavesh Ramesh Nagda. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AUBBURN WING A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback