ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Athashri at Pebbles

Registration lapsed No litigation declared Others project

Athashri at Pebbles

By Abhinav Rainbow Developers And Promoters LLP

RG-MH-66843 · RERA P52100019099 · Last updated on MahaRERA portal: 22 Feb 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
28 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

Athashri at Pebbles is a Others project by Abhinav Rainbow Developers And Promoters LLP in Pune, Maharashtra, registered with MahaRERA as P52100019099 on 4 Jan 2019. Possession was promised by 30 Dec 2023 and is now 34 months past that date.

At a glance

Project

  • NameAthashri at Pebbles
  • TypeOthers
  • Location
    • Near Mumbai Bangalore Highway
    • Bavdhan Budruk
    • Bavadhan BK
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • RERA no.P52100019099
  • ReraGenie IDRG-MH-66843

Builder

  • NameAbhinav Rainbow Developers And Promoters LLP
  • Entity typeOthers
  • Named personsShamkant Jagannath Shende, Sunil Popatlal Nahar
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

34 months past promisethis monthRegisteredJan 2019PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Jan 2019
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings3 building records
  • Documents filed67 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
G BLDGNA130000
H BldgNA120000
I BldgNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 22 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

28 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

G BLDG91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H Bldg91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
I Bldg73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities19

As on 22 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
Guest RoomsYes100%
Physiotherapy RoomYes100%
Pickle Ball CourtYes100%
Swimming Pool with JacuzziYes100%

Parking filed89

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots89
Closed/Covered53
Open Space36
BuildingClosed/CoveredOpen SpaceTotal
G BLDG161228
H Bldg02424
I Bldg37037

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,792 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10550.74
Proposed, not sanctioned10,551 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGhole Road, Pune

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSeema Gohad
EngineerHansal Parikh
Chartered AccountantKapil Munot
PartnerRole in project
Abhinav Rainbow Developers And Promoters LLP-

Litigation declared2

CaseCourtStatus
1633/2013Civil Judge Sr Division PuneFinal Arguments
60/2016Sub Divisional Officer MavalFor Summons

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Dec 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Dec 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Jun 2021

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARDP_GHI_Form 1_Oct 21_compressed.pdf22 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARDP_GHI_Form 1_Jan 22_compressed.pdf22 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: PII - GHI - Form 2A - 30-09-2021_compressed.pdf21 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: PII - GHI - Form 2A - 31-12-2021_compressed.pdf21 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_ARDPL_PA_Jul20.pdf15 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_ARDPL_PA_Oct20.pdf15 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_ARDPL_PA_Jan21.pdf15 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_ARDPL_PA_Apr21.pdf15 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_ARDPL_PA_Jul21.pdf15 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Athashri Quality assurance Certificate 2A Up to 31-03-2019.pdf15 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Athashri Quality Assurance Certificate 2A Q4 310320.pdf15 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_ARDPL Pebb Athashri_2021.pdf24 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ARDPL_Form2_June20.pdf23 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ARDPL_Form2_Mar21.pdf23 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ARDPL_Form2_Dec20.pdf23 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ARDPL_Form2_Sept20.pdf23 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ARDPL_Form2_Jun21.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ARDPL_Form2_June20.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ARDPL_Form2_Sept20.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ARDPL_Form2A_Dec20.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ARDPL_Form2_Mar21.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ARDPL_Form2A_Jun20.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ARDPL_Form2A_Sept20.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ARDPL_Form2A_Dec20.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ARDPL_Form2A_Mar21.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ARDPL_Form2A_Jun21.pdf23 Aug 2021
Certificates of CA (Form 3)File: Form 3_Q4_20-21_GHI bldg.pdf17 Aug 2021
Certificates of CA (Form 3)File: Form 3_Q3_20-21_GHI bldg.pdf17 Aug 2021
Certificates of CA (Form 3)File: Form 3_Q2_20-21_GHI bldg.pdf17 Aug 2021
Certificates of CA (Form 3)File: Form 3_Q1_20-21_GHI bldg.pdf17 Aug 2021
Certificates of CA (Form 3)File: Form 3_2021-22_Q1_GHI Building.pdf17 Aug 2021
Declaration about Commencement CertificateFile: Pebbles Athashri_GHI_Commencement Certificate.pdf6 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARDPL_PA_ARCH CERT_Q1_2019-20.pdf5 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARDPL_PA_ARCH CERT_Q2_2019-20.pdf5 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARDPL_PA_ARCH CERT_Q3_2019-20.pdf5 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARDPL_PA_ARCH CERT_Q4_2019-20.pdf5 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Q2_2019-20.pdf5 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Q1_2019-20.pdf5 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Q4_2019-20.pdf5 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Q3_2019-20.pdf5 Aug 2021
Certificates of CA (Form 3)File: Form 03_Q4_2019-20.pdf5 Aug 2021
Certificates of CA (Form 3)File: Form 03_Q3_2019-20.pdf5 Aug 2021
Certificates of CA (Form 3)File: Form 03_Q2_2019-20.pdf5 Aug 2021
Certificates of CA (Form 3)File: Form 03_Q1_2019-20.pdf5 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM -5_2019-20.pdf5 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: G H I_compressed.pdf19 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ARDP Form 5_GHI Bldg_FY 2018-19.pdf13 Nov 2019
Proforma of Allotment letterFile: Revised draft.pdf11 Apr 2019
Form 2AFile: Form2A.PDF10 Apr 2019
Proforma of Allotment letterFile: Residential Agreement to Sale.pdf26 Mar 2019
Proforma of Allotment letterFile: Athahri Pebbles -Residential.pdf27 Feb 2019
Proforma of Allotment letterFile: Athahri Pebbles -Commercial.pdf27 Feb 2019
Proforma of Allotment letterFile: Athashri Pebbles (ATS Residential)-Compressed.pdf4 Feb 2019
Proforma of Allotment letterFile: ATS-Pebbles-Commercial Draft-Compressed.pdf4 Feb 2019
Certificates of CA (Form 3)File: FORRM 3.pdf25 Dec 2018
Proforma of Allotment letterFile: ATS Commercial Upload.pdf25 Dec 2018
Proforma of Allotment letterFile: ATS Residential Upload.pdf25 Dec 2018
Building plan approvalFile: Layout.pdf10 Dec 2018
Layout approvalFile: Layout.pdf10 Dec 2018
Details of encumbrancesFile: Encumbrance Certificate.pdf10 Dec 2018
Copy of Layout Approval (in case of layout)File: Layout.pdf10 Dec 2018
Building Plan Approval (IOD)File: Layout.pdf10 Dec 2018
Declaration in FORM BFile: B Form Athashri at Pebbles.pdf10 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf10 Dec 2018
PAN CardFile: ARDP PAN Card.pdf7 Dec 2018
Copy of the legal title reportFile: Title Certificate.pdf7 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate - 151018.pdf7 Dec 2018

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Pebbles II Building ES.No.270 and others at Bavdhan Budruk Tal.Mulshi Dist.Pune96CompletedDec 2018Aug 2018
Pebbles II Building C and DS No 270 and Others Bavdhan Budruk Pune 411021232CompletedOct 2016Mar 2016
Pebbles II Building A and BS NO 270 AND OTHERS BAVDHAN BUDRUK PUNE 411021192CompletedJan 2016Oct 2015

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Athashri at Pebbles on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bavdhan Budruk13,700+ in Pune

Builder: Abhinav Rainbow Developers And Promoters LLP

ABHINAV RAINBOW DEVELOPERS AND PROMOTERS LLP has 2 registrations on MahaRERA, including PEBBLES II E BUILDING and Athashri at Pebbles. Its filings disclose 5 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Athashri at Pebbles shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Athashri at Pebbles is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Athashri at Pebbles?

The registered promoter entity is Abhinav Rainbow Developers And Promoters LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Athashri at Pebbles?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Athashri at Pebbles?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Athashri at Pebbles?

The professionals named in the filing: Architect: Seema Gohad; Engineer: Hansal Parikh; Chartered Accountant: Kapil Munot. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Athashri at Pebbles?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Athashri at Pebbles. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Athashri at Pebbles to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.