Home / Browse projects / Pune, Maharashtra / Atharva Bliss Phase II- Residential Building

Registered No litigation declared Residential / Group Housing project

Atharva Bliss Phase II- Residential Building

By M/s. Abhay Constructions

RG-MH-75427 · RERA P52100080855 · Last updated on MahaRERA portal: 25 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2029Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Slabs of Super Structure, 65%
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

Atharva Bliss Phase II- Residential Building is a Residential / Group Housing project by M/s. Abhay Constructions in Pune, Maharashtra, registered with MahaRERA as P52100080855 on 22 Jul 2025. Possession is promised by 31 Mar 2029.

At a glance

Project

  • NameAtharva Bliss Phase II- Residential Building
  • TypeResidential / Group Housing
  • Location
    • S No 13/1 & S No 14/1 (S No 14/1+2 Old)
    • Bavadhan BK
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • RERA no.P52100080855
  • ReraGenie IDRG-MH-75427

Builder

  • NameM/s. Abhay Constructions
  • Entity typePartnership
  • PartnersAbhay Madhav Joglekar, Atharva Constructions Pune Pvt Ltd through Director Ajay Nathuram Kadam, Atharva Constructions Pune Pvt Ltd through Director Kalyani Ajay Kadam, Atharva Constructions Pune Pvt Ltd through Director Swati Rajendra Kutte, Mona Abhay Joglekar, Madhav Digambar Joglekar, Atharva Constructions Pune Pvt Ltd through Director Rajendra Shankarrao Kutte, Madhura nee Anita Madhav Joglekar Manvendra Gokhale
  • Other registrations2 more →
  • Completed1 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2025PromisedMar 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Jul 2025
  • Promised completion31 Mar 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing DNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 65%.

Wing D: 9% average across the applicable activities

ActivityProgress
Excavation5%
Basement (if any)5%
Podiums (if any)5%
Plinth5%
Stilt Floor5%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises2%
Sanitary Fittings within the flats / premises2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.2%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.2%

Progress on shared amenities15

As on 25 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes1%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes1%
Storm Water DrainsYes1%
Landscaping & Tree PlantingYes100%
Street LightingYes1%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes1%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered12

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,328 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI13910.15
Proposed, not sanctioned865 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSadashiv Peth, Pune 411030

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNilesh Bide
EngineerAjay Kadam
Chartered AccountantSushant sadanand padhye
PartnerRole in project
M/s. Abhay Constructions-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Jun 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jun 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2029

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 01 Form 1_BAVDHAN RESI_ RERA STATUS_Q2_2025.pdf25 May 2026
Form 2File: ENGINEER CERTIFICATE Maha RERA Phase 2 Residential Building Q2.pdf25 May 2026
Form 3File: FORM 3 Phase 2 Residential Building CA Certificate for Registration Q2 30-09-2025 SIG.pdf25 May 2026
Disclosure of Sold and Booked InventoryFile: Residential Disclosure of Sold and Unsold Inventory Q2.pdf25 May 2026
Self-declaration of Quarterly ProgressFile: Self-Declaration for Quarterly Progress Maha RERA Phase II-Residential Building Q2.pdf25 May 2026
Form 1File: 02 Form 1_ BAVDHAN RESI_ RERA STATUS_Q3_2025.pdf25 May 2026
Form 2File: ENGINEER CERTIFICATE Maha RERA Phase 2-Residential Building Q3.pdf25 May 2026
Form 3File: FORM 3-Phase 2 Residential Building CA Certificate for Registration Q3 31_12_2025 SIG.pdf25 May 2026
Disclosure of Sold and Booked InventoryFile: Residential Disclosure of Sold and Unsold Inventory Q3.pdf25 May 2026
Self-declaration of Quarterly ProgressFile: Self-Declaration for Quarterly Progress Maha RERA Phase II-Residential Building Q3.pdf25 May 2026
Form 1File: 03 Form 1_ BAVDHAN RESI_ RERA STATUS_Q4_25-26.pdf25 May 2026
Form 2File: ENGINEER CERTIFICATE Maha RERA Phase 2-Residential Building Q4.pdf25 May 2026
Form 3File: FORM 3-Phase 2 Residential Building CA Certificate for Registration Q4 31_03_2026 SIG.pdf25 May 2026
Disclosure of Sold and Booked InventoryFile: Residential Disclosure of Sold and Unsold Inventory Q4.pdf25 May 2026
Self-declaration of Quarterly ProgressFile: Self-Declaration for Quarterly Progress Maha RERA Phase II-Residential Building Q4.pdf25 May 2026
Other - LegalFile: Revenue Share of landowners Residential.pdf25 Jun 2025
Other - LegalFile: 3 POA Umabai to Angad 06 oct 2023.pdf25 Jun 2025
Other - LegalFile: 2 Abhay POA 14 nov1995.pdf25 Jun 2025
Other - LegalFile: 04 Abhay Confirmation Deed 14 nov1995.pdf25 Jun 2025
Other - LegalFile: Development Agreement.pdf25 Jun 2025
Other - LegalFile: Final Decalaration- Landowners.pdf25 Jun 2025
Other - LegalFile: 1 Original POA.pdf25 Jun 2025
Layout approvalFile: Copy of Layout.pdf4 Jun 2025
Building plan approvalFile: Building Plan Approval.pdf4 Jun 2025
Copy of Layout Approval (in case of layout)File: Copy of Layout.pdf4 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval.pdf4 Jun 2025
Other - FinanceFile: Revenue Share of landowners Residential.pdf4 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration cum Undertaking for Land Value considered nil.pdf5 May 2025
Other - FinanceFile: Declaration cum Undertaking for Land Value considered nil.pdf5 May 2025
Other - TechnicalFile: Residential DECLARATION ABOUT For Plot Area Considered.pdf23 Apr 2025
Other - TechnicalFile: CC Verification Mail.pdf5 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Residential Disclosure for secured unsecured finance availed for the project.pdf5 Apr 2025
Details of encumbrances concerned to FinanceFile: New_Residential Emcumbrance Certificate .pdf4 Apr 2025
CERSAI detailsFile: Residential CERSAI Details.pdf4 Apr 2025
Details of encumbrances concerned to LegalFile: New_Residential Emcumbrance Certificate .pdf4 Apr 2025
Other - TechnicalFile: Atharva Bliss Phase II Residential Building Annexure A.pdf4 Apr 2025
Proforma of Agreement for saleFile: New_Agreement for sale Residential .pdf4 Apr 2025
Details of encumbrances concerned to FinanceFile: Residential Emcumbrance Certificate.pdf20 Mar 2025
Proforma of Allotment letterFile: Updated Allotment Letter Residential.pdf20 Mar 2025
Details of encumbrances concerned to LegalFile: Residential Emcumbrance Certificate.pdf20 Mar 2025
PAN CardFile: Abhay Constructions PAN.pdf18 Mar 2025
Copy of the legal title reportFile: Updated Bavdhan Title Report.pdf18 Mar 2025
Declaration in FORM BFile: FORM B No Encumbrance Landowners Residential.pdf18 Mar 2025
Declaration in FORM BFile: FORM B No Encumbrance Promoter Residential.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Bavdhan Residential FORM1.pdf18 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-Phase II Residential Building CA Certificate for Registration (1) SIGNED.pdf18 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE Maha RERA Phase II-Residential Building.pdf18 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Bavdhan_CC_26 aug 2024.pdf18 Mar 2025
Declaration about Commencement CertificateFile: Residential DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf18 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Residential as per order 56-2024.pdf18 Mar 2025
Deviation Report with respect to Allotment letterFile: Residential DECLARATION ABOUT NO DeVIATION.pdf18 Mar 2025
Deviation Report with respect to model copy of AgreementFile: Residential DECLARATION ABOUT NO DeVIATION.pdf18 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Projects Amenity.pdf18 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: TBSBL RESIDENTIAL ACCOUNTS.pdf18 Mar 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
ATHARVA BLISS PHASE IP52100006701Bavadhan BK, PuneAug 2017CompletedDec 2017Dec 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Atharva Bliss Phase II- Residential Building on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bavadhan BK13,700+ in Pune

Builder: M/s. Abhay Constructions

M/s. Abhay Constructions has 3 registrations on MahaRERA, including ATHARVA BLISS PHASE I and Atharva Bliss Phase II- Amenity Building. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Atharva Bliss Phase II- Residential Building is delayed beyond 31 Mar 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Atharva Bliss Phase II- Residential Building?

The registered promoter entity is M/s. Abhay Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Atharva Bliss Phase II- Residential Building?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Atharva Bliss Phase II- Residential Building?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Atharva Bliss Phase II- Residential Building?

The professionals named in the filing: Architect: Nilesh Bide; Engineer: Ajay Kadam; Chartered Accountant: Sushant sadanand padhye. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Atharva Bliss Phase II- Residential Building?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Atharva Bliss Phase II- Residential Building. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Atharva Bliss Phase II- Residential Building to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.