ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Astoria Royals A wing

Registered No litigation declared Residential / Group Housing project

Astoria Royals A wing

By NIRMAN SQUARE LLP

RG-MH-75317 · RERA P52100048260 · Last updated on MahaRERA portal: 25 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2028Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 50%
36 of 144Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 122 documents Report an error

Astoria Royals A wing is a Residential / Group Housing project by NIRMAN SQUARE LLP in Pune, Maharashtra, registered with MahaRERA as P52100048260 on 22 Dec 2022. Possession is promised by 30 Sep 2028. 108 of the 144 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameAstoria Royals A wing
  • TypeResidential / Group Housing
  • Location
    • Ravet
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100048260
  • ReraGenie IDRG-MH-75317

Builder

  • NameNIRMAN SQUARE LLP
  • Entity typePartnership
  • GSTIN27AASFN2988A1ZW
  • PartnersBhushan Rajiv Agarwal, Sunil Rameshwardas Agarwal, Pratik Sunil Agarwal, GAURAV SANTRAM BANSAL, MAHAVIR BALKRISHNA MITTAL, Mohit Balbir MIttal, Aditya Dharamapal Anand, Rakesh Sumerchand Gupta, Ramesh Motilalji Chaudhary, Sandeep Shrikrishna Goyal, Vijaykumar Roshanlal Garg, Yash Vinod Agarwal and 4 more
  • Other registrations2 more →

Key dates

this monthRegisteredDec 2022PromisedSep 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Dec 2022
  • Promised completion30 Sep 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed122 files

Current status

75%108 of 144 units booked
62.8%Work done, per cost certificate

Figures as on 25 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Astoria Royals A wingNA29241440144

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 50%.

Astoria Royals A wing: 44% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed170

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots170
Closed/Covered170

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,476 sq m
Land owned byThe promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on20 Sep 2024
LandownerVillageDistrict
SAI VENKATA NIRMITI PVT LTDPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI22074.0
Proposed, not sanctioned1,032 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchChinchwad Branch ,Pune
Estimated costRs 67.86 cr
Cost incurredRs 42.62 cr
Work done62.81%
BuildingWingEstimatedIncurred
Astoria Royals A wingNARs 57.68 crRs 36.23 cr
-NARs 10.18 crRs 6.39 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYogesh Manakshe
ArchitectYOGESH SHANKARLAL MANAKSHE
EngineerSunil Shridhar Kalore
Chartered AccountantNAVDEEP JINDAL & ACCOCIATES
Chartered AccountantSHEETAL JINDAL & COMPANY
Chartered AccountantCA Dolly Gandhi
Chartered AccountantPrachi Agarwal
PartnerRole in project
NIRMAN SQUARE LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2028

Documents filed122

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1- A Wing.pdf25 Apr 2026
Withdrawal Update Form 2File: Form 2 - A wing signed.pdf25 Apr 2026
Withdrawal Update Form 3File: FORM 3 nirman square A wing Mar 26 signed.pdf25 Apr 2026
Withdrawal Update Form 1File: FORM 1 A-Wing.pdf16 Jan 2026
Withdrawal Update Form 2File: A wing Form 2.pdf16 Jan 2026
Withdrawal Update Form 3File: A wing Form 3 Sign.pdf16 Jan 2026
Withdrawal Update Form 1File: FORM 1 A-Wing.pdf16 Oct 2025
Withdrawal Update Form 2File: FORM 2 A WING.pdf16 Oct 2025
Withdrawal Update Form 3File: FORM 3 A WING sign_compressed (1).pdf16 Oct 2025
Form 5 (FY 2023-2024)File: NIRMAN SQUARE LLP FORM 5 A wing.pdf29 Sep 2025
Form 5 (FY 2024-2025)File: FORM5 A WING_compressed.pdf29 Sep 2025
Form 2A (FY 2024-2025)File: Form 2A A Wing.pdf18 Aug 2025
Form 2A (FY 2023-2024)File: Signed Form 2A A Wing.pdf18 Aug 2025
Withdrawal Update Form 1File: Form 1 A Wing Signed.pdf19 Jul 2025
Withdrawal Update Form 2File: Form 2 A wing Signed_compressed.pdf19 Jul 2025
Withdrawal Update Form 3File: Form 3 A Wing Signed.pdf19 Jul 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate A Wing.pdf24 Jun 2025
Withdrawal Update Form 2File: Form 2 A wing.pdf24 Jun 2025
Withdrawal Update Form 3File: FORM 3 nirman square A wing Mar 25 signed_compressed.pdf24 Jun 2025
Form 1File: Form 1 Architech Certificate A Wing.pdf21 Jun 2025
Form 2File: Form 2 Engineer Certificate A Wing.pdf21 Jun 2025
Form 3File: Form 3 CA Certificate A Wing.pdf21 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold-Unsold Inventory A-wing.pdf21 Jun 2025
Form 1File: Form 1 A Wing Architect's Certificate.pdf21 Jun 2025
Form 2File: Form 2 Astoria Royals A Wing.pdf21 Jun 2025
Form 3File: Nirman Square LLP Form-3 A Wing (1).pdf21 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory A Wing Mar-24.pdf21 Jun 2025
Form 1File: Nirman Square LLP A wing Form 1 24 signed.pdf21 Jun 2025
Form 2File: Nirman Square LLP A Wing Form 2_24 signed.pdf21 Jun 2025
Form 3File: Nirman Square LLP A wing Form 3_24 signed.pdf21 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory A Wing Sep-24.pdf21 Jun 2025
Form 1File: Form 1 Architect Certificate A Wing.pdf21 Jun 2025
Form 2File: Signed Form 2 Astoria Royals A.pdf21 Jun 2025
Form 3File: Signed Form 3 CA Astoria Royals - A Wing.pdf21 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory A Wing Dec-24.pdf21 Jun 2025
Form 1File: Form 1 Architect Certificate A Wing.pdf21 Jun 2025
Form 2File: Form 2 A wing.pdf21 Jun 2025
Form 3File: FORM 3 nirman square A wing Mar 25 signed_compressed.pdf21 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory A Wing Mar 25.pdf21 Jun 2025
Form 2 A wing29 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate A Wing.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 A wing.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure A Wing.pdf28 Apr 2025
Layout approvalFile: 01-LAYOUT PLAN.pdf5 Mar 2025
Building plan approvalFile: A WING merged 1.pdf5 Mar 2025
Building plan approvalFile: A WING merged 2.pdf5 Mar 2025
Copy of Layout Approval (in case of layout)File: 01-LAYOUT PLAN.pdf5 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: commecement astoria feb 25.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: A WING merged 1.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: A WING merged 2.pdf5 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Signed Form 2A A Wing.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signed Form 1 Enggineer A Wing.pdf30 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirman Square LLp (A wing) Form-3 signed.pdf30 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Signed Form 2 Astoria Royals A.pdf30 Jan 2025
Disclosure of sold/ booked inventoryFile: Signed DISCLOSURE OF SOLD - A.pdf30 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: NIRMAN SQUARE LLP FORM 5 A wing.pdf7 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signed Nirman Square LLP A wing Form 1.pdf14 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Nirman Square LLP A wing Form 3.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Signed Nirman Square LLP A Wing Form 2.pdf14 Nov 2024
Disclosure of sold/ booked inventoryFile: Signed Disclosure A Wing.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 A Wing Architect's Certificate.pdf3 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Astoria Royals A Wing.pdf3 Aug 2024
Disclosure of sold/ booked inventoryFile: A Wing Disclosure Sold Inventory.pdf3 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirman Square LLP Form-3 A Wing (1).pdf3 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclouser Of Sold-Unsold Inventory A-wing.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate A Wing.pdf18 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architech Certificate A Wing.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate A Wing.pdf17 Apr 2024
Building plan approvalFile: Astoria Sanctioned Plan March 24 A Wing 9-32.pdf8 Mar 2024
Building plan approvalFile: Astoria Sanctioned Plan March 24 A Wing 10-32.pdf8 Mar 2024
Building plan approvalFile: Astoria Sanctioned Plan March 24 A Wing 11-32.pdf8 Mar 2024
Building plan approvalFile: Astoria Sanctioned Plan March 24 A Wing 12-32.pdf8 Mar 2024
Building plan approvalFile: Astoria Sanctioned Plan March 24 A Wing 13-32.pdf8 Mar 2024
Building plan approvalFile: Astoria Sanctioned Plan March 24 A Wing 14-32.pdf8 Mar 2024
Building plan approvalFile: Astoria Sanctioned Plan March 24 A Wing 15-32.pdf8 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Astoria Sanctioned Plan March 24 A Wing 9-32.pdf8 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Astoria Sanctioned Plan March 24 A Wing 10-32.pdf8 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Astoria Sanctioned Plan March 24 A Wing 11-32.pdf8 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Astoria Sanctioned Plan March 24 A Wing 12-32.pdf8 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Astoria Sanctioned Plan March 24 A Wing 13-32.pdf8 Mar 2024

How this compares with Pune

75%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Astoria Royals A wing on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ravet13,700+ in Pune

2 kmAstoria Royals A wingCompleted 108Lapsed / revoked 55Other 119Dot size: filed unitsN

Filed coordinates, straight-line distance. 282 registered projects within 2 km.

Builder: NIRMAN SQUARE LLP

NIRMAN SQUARE LLP has 3 registrations on MahaRERA, including Astoria Royals A wing and Astoria Royals B wing. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Astoria Royals A wing is delayed beyond 30 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Astoria Royals A wing?

The registered promoter entity is NIRMAN SQUARE LLP, a partnership as per the filing. Its GSTIN 27AASFN2988A1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Astoria Royals A wing?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Astoria Royals A wing?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Astoria Royals A wing?

The professionals named in the filing: Architect: Yogesh Manakshe; Architect: YOGESH SHANKARLAL MANAKSHE; Engineer: Sunil Shridhar Kalore; Chartered Accountant: NAVDEEP JINDAL & ACCOCIATES; Chartered Accountant: SHEETAL JINDAL & COMPANY; Chartered Accountant: CA Dolly Gandhi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Astoria Royals A wing?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Astoria Royals A wing. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Astoria Royals A wing to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.