ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Ashford Regal - Phase IV- Wing C Project

Registered No litigation declared Mixed project

Ashford Regal - Phase IV- Wing C Project

By WMI Real Estate Developers LLP

RG-MH-18647 · RERA PM1183032400064 · Last updated on MahaRERA portal: 7 May 2026

Source: official MahaRERA filing

Red flags

  • Rs 190.00 crore secured on the land, in favour of HDFC LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 completed earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2029Possession promisedno revision filed
3 of 9Construction stages donefurthest along: Slabs of Super Structure, 25%
80 of 295Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 20 documents Report an error

Ashford Regal - Phase IV- Wing C Project is a Mixed project by WMI Real Estate Developers LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as PM1183032400064 on 8 Oct 2024. Possession is promised by 30 Jun 2029. 215 of the 295 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameAshford Regal - Phase IV- Wing C Project
  • TypeMixed
  • Location
    • VILLAGE BHANDUP
    • BHANDUP
    • Kurla
    • Mumbai Suburban
    • 400078
  • Pincode400078
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PM1183032400064
  • ReraGenie IDRG-MH-18647

Builder

  • NameWMI Real Estate Developers LLP
  • Entity typeOthers
  • GSTIN27AACFW2534P1ZQ
  • Named personsAurum Commercial LLP, Ashford Residency LLP
  • Other registrations4 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredOct 2024PromisedJun 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Oct 2024
  • Promised completion30 Jun 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed20 files

Current status

73%215 of 295 units booked
33.5%Work done, per cost certificate

Figures as on 7 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING CNA404027916295

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 25%.

WING C: 38% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNo0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNo0%
Solid Waste Management And DisposalNo20%
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed316

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots316
Closed/Covered316

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area29,278 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofHDFC LIMITED
Secured amountRs 190.00 crore
Declared on11 Jul 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI16000.0
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, RUPAREL IRIS, SENAPATI BAPAT MARG, MATUNGA WEST, MUMBAI
Estimated costRs 145.38 cr
Cost incurredRs 48.64 cr
Work done33.46%
BuildingWingEstimatedIncurred
WING CNARs 130.84 crRs 43.78 cr
-NARs 14.54 crRs 4.86 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectparin shah
EngineerJACOB D'SOUZA
Engineervivek jirapure
Chartered AccountantGBCA & ASSOCIATES LLP
Chartered AccountantNEHALI & CO
PartnerRole in project
WMI Real Estate Developers LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Sep 2024
  3. Building plan approvalNot on the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2029

Documents filed20

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 architects certificate WIng-C march 2026.pdf7 May 2026
Withdrawal Update Form 2File: Engineer Form 2 Wing C-Mar 26 (1).pdf7 May 2026
Withdrawal Update Form 3File: Signed CA Certificate-Wing C - Form 3 Mar 26.pdf7 May 2026
Withdrawal Update Form 1File: Form 1 architects certificate WIng-C.pdf31 Mar 2026
Withdrawal Update Form 2File: Engineer Form 2 Wing C-Dec 25.pdf31 Mar 2026
Withdrawal Update Form 3File: Signed CA Certificate Wing C Form 3 dec 25.pdf31 Mar 2026
Withdrawal Update Form 1File: Form 1 architects certificate WIng-C..pdf7 Jan 2026
Withdrawal Update Form 2File: Engineer Form 2 Wing C-Sept 25.pdf7 Jan 2026
Withdrawal Update Form 3File: Signed CA Certificate-Wing C - Form 3 sept 25..pdf7 Jan 2026
Withdrawal Update Form 1File: Form 1 architects certificate Ashford Regal - Phase IV Wing - ā€˜C’.pdf30 Oct 2025
Withdrawal Update Form 2File: 6 ASHFORD REGAL - PHASE II - WING C - FORM 2..pdf30 Oct 2025
Withdrawal Update Form 3File: Signed CA Certificate-Wing C - Form 3 juneu002725.pdf30 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A - Wing C.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: Ashford Regal Phase IV FORM 5.pdf29 Sep 2025
Form 1File: form 1 wing C.pdf23 Jul 2025
Form 2File: form 2 wing C.pdf23 Jul 2025
Form 3File: form 3 Wing C.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unslod Inventory Tower C..pdf23 Jul 2025
Layout approvalFile: (2022-09-27) LAYOUT APPROVAL PLAN.pdf17 Sep 2024
Layout approvalFile: plans final.pdf17 Sep 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Ashford Regal - Phase I - Wing A ProjectP51800047421Bhandup west, Mumbai Suburban293Oct 2022OngoingJun 2027Not due yet
Ashford Regal - Phase I - Wing A ProjectP51800047421Bhandup west, Mumbai Suburban293Oct 2022OngoingJun 2027Not due yet
Ashford Royale Tower DAshford Infotech Private Limited Project Ashford Royale S Samuel Street Goregaon Mulund Road Nahur Village Bhandup Mumbai 40007896-CompletedDec 2019Oct 2018

How this compares with Mumbai Suburban

73%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ashford Regal - Phase IV- Wing C Project on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHANDUP6,700+ in Mumbai Suburban

2 kmAshford Regal - Phase IVCompleted 53Lapsed / revoked 34Other 102Dot size: filed unitsN

Filed coordinates, straight-line distance. 189 registered projects within 2 km.

Builder: WMI Real Estate Developers LLP

WMI Real Estate Developers LLP has 5 registrations on MahaRERA, including Ashford Regal - Phase I - Wing A Project and Ashford Regal - Phase II - Wing B Project. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Ashford Regal - Phase IV- Wing C Project is delayed beyond 30 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ashford Regal - Phase IV- Wing C Project?

The registered promoter entity is WMI Real Estate Developers LLP, an others as per the filing. Its GSTIN 27AACFW2534P1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ashford Regal - Phase IV- Wing C Project?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Ashford Regal - Phase IV- Wing C Project?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ashford Regal - Phase IV- Wing C Project?

The professionals named in the filing: Architect: parin shah; Engineer: JACOB D'SOUZA; Engineer: vivek jirapure; Chartered Accountant: GBCA & ASSOCIATES LLP; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ashford Regal - Phase IV- Wing C Project?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ashford Regal - Phase IV- Wing C Project. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ashford Regal - Phase IV- Wing C Project to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.