Red flags
- Registration lapsed
- Possession 22 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ARISO APARTMENT is a Residential / Group Housing project by KYRAA HOUSING PROJECTS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006930 on 16 Aug 2017. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 57 of the 126 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameARISO APARTMENT
- TypeResidential / Group Housing
- Location
- Subhash Nagar
- chembur West
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800006930
- ReraGenie IDRG-MH-56250
Builder
- NameKYRAA HOUSING PROJECTS
- Entity typePartnership
- GSTIN27AANFK5632R1ZI
- PartnersPRASANNA LAXMAN NAIK, UTSAV AJAY AGARWAL, YASH UMESH AGARWAL
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on16 Aug 2017
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed129 files
Current status
Figures as on 15 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ARISO APARTMENT A and B WING | NA | 17 | 17 | 126 | 0 | 126 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
ARISO APARTMENT A and B WING: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed58
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr. Sachin Rakshe |
| Engineer | Adharshila Consultatnt |
| Chartered Accountant | Kapure & Kapure |
| Chartered Accountant | Shripati Gandhi Choudhari & Co. |
| Partner | Role in project |
|---|---|
| KYRAA HOUSING PROJECTS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Sep 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed129
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 129 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2018-2019)File: Site_Engineers_Certificate_kyraa Mar 2019.pdf | 15 Jul 2026 |
| Form 2A (FY 2019-2020)File: Form 2A- Kyraa Mar 20.pdf | 15 Jul 2026 |
| Form 2A (FY 2020-2021)File: Form 2A- Kyraa Mar 21.pdf | 15 Jul 2026 |
| Form 2A (FY 2021-2022)File: form2A-2022.pdf | 15 Jul 2026 |
| Form 2A (FY 2022-2023)File: Kyraa form-2a-2023.pdf | 15 Jul 2026 |
| Form 2A (FY 2023-2024)File: kyraa form-2A -2024.pdf | 15 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form 2A March 25.pdf | 15 Jul 2026 |
| Form 1File: ARCHITECT CERTIFICATE- March 21.pdf | 7 Jul 2026 |
| Form 2File: Form 2 March 21.pdf | 7 Jul 2026 |
| Form 3File: Form_3__Mar_21_compressed.pdf | 7 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-March 21.pdf | 7 Jul 2026 |
| Form 1File: ARCHITECT CERTIFICATE- March 22.pdf | 7 Jul 2026 |
| Form 2File: Form 2March 22.pdf | 7 Jul 2026 |
| Form 3File: Form_3__Mar_22_compressed.pdf | 7 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold- March 22.pdf | 7 Jul 2026 |
| Form 1File: ARCHITECT CERTIFICATE- March 23.pdf | 7 Jul 2026 |
| Form 2File: Form 2 March 23 .pdf | 7 Jul 2026 |
| Form 3File: Form_3__Mar 23_compressed.pdf | 7 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold- March 23.pdf | 7 Jul 2026 |
| Form 1File: ARCHITECT CERTIFICATE- March 24.pdf | 7 Jul 2026 |
| Form 2File: Form 2 March 24.pdf | 7 Jul 2026 |
| Form 3File: Form_3__Mar 24_compressed.pdf | 7 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold- March 24.pdf | 7 Jul 2026 |
| Form 1File: ARCHITECT CERTIFICATE- June 24.pdf | 7 Jul 2026 |
| Form 2File: Form 2 June 24.pdf | 7 Jul 2026 |
| Form 3File: Form_3__June 24_compressed.pdf | 7 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold- June 24.pdf | 7 Jul 2026 |
| Form 1File: ARCHITECT CERTIFICATE- Sep 24.pdf | 7 Jul 2026 |
| Form 2File: Form 2 Sep 24.pdf | 7 Jul 2026 |
| Form 3File: Form_3__Sep 24_compressed.pdf | 7 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold- Sep 24.pdf | 7 Jul 2026 |
| Form 1File: ARCHITECT CERTIFICATE- Dec 24.pdf | 7 Jul 2026 |
| Form 2File: Form 2 Dec 24.pdf | 7 Jul 2026 |
| Form 3File: Form_3__Dec 24_compressed.pdf | 7 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold Dec 24.pdf | 7 Jul 2026 |
| Form 5 (FY 2017-2018)File: FORM_5-KYRAA.PDF | 7 Jul 2026 |
| Form 5 (FY 2019-2020)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19).pdf | 7 Jul 2026 |
| Form 5 (FY 2018-2019)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19).pdf | 7 Jul 2026 |
| Form 5 (FY 2020-2021)File: Form 5 March 21.pdf | 7 Jul 2026 |
| Form 5 (FY 2021-2022)File: Form 5 March 22.pdf | 7 Jul 2026 |
| Form 5 (FY 2022-2023)File: March 5 form march 23.pdf | 7 Jul 2026 |
| Form 5 (FY 2023-2024)File: March 5 form march 24.pdf | 7 Jul 2026 |
| Certificates of CA (Form 3)File: From 3 March 25 Kyraa_compressed.pdf | 19 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 25.pdf | 19 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: DISC.pdf | 19 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: March 5 form march 23.pdf | 19 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: March 5 form march 24.pdf | 19 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 March 25.pdf | 10 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form March 18.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From 2 Sep 19.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 19 .pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form March 19 .pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 20.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 21.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2March 22.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 23 .pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 24.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 24.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sep 24.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 24.pdf | 2 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 March 20.pdf | 29 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 March 21.pdf | 29 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 March 22.pdf | 29 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- March 20.pdf | 24 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Mar 22.pdf | 24 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - March 23.pdf | 24 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A March 24.pdf | 24 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- March 22.pdf | 15 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- March 23.pdf | 15 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- March 24.pdf | 15 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- June 24.pdf | 15 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- Sep 24.pdf | 15 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- Dec 24.pdf | 15 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- March 21.pdf | 15 Mar 2025 |
| Certificates of CA (Form 3)File: Form_3__Mar 24_compressed.pdf | 15 Mar 2025 |
| Certificates of CA (Form 3)File: Form_3__Dec 24_compressed.pdf | 15 Mar 2025 |
| Certificates of CA (Form 3)File: Form_3__Sep 24_compressed.pdf | 15 Mar 2025 |
| Certificates of CA (Form 3)File: Form_3__June 24_compressed.pdf | 15 Mar 2025 |
| Certificates of CA (Form 3)File: Form_3__Mar 23_compressed.pdf | 15 Mar 2025 |
| Certificates of CA (Form 3)File: Form_3__Mar_22_compressed.pdf | 15 Mar 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 129 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ARISO APARTMENT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near chembur West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 198 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: KYRAA HOUSING PROJECTS
KYRAA HOUSING PROJECTS has 1 registration on MahaRERA, including ARISO APARTMENT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that ARISO APARTMENT shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ARISO APARTMENT is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ARISO APARTMENT?
The registered promoter entity is KYRAA HOUSING PROJECTS, a partnership as per the filing. Its GSTIN 27AANFK5632R1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ARISO APARTMENT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ARISO APARTMENT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ARISO APARTMENT?
The professionals named in the filing: Architect: Mr. Sachin Rakshe; Engineer: Adharshila Consultatnt; Chartered Accountant: Kapure & Kapure; Chartered Accountant: Shripati Gandhi Choudhari & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ARISO APARTMENT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.