ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Arham Aryan

Registered No litigation declared Residential / Group Housing project

Arham Aryan

By Trinity Builders

RG-MH-43860 · RERA P51800050811 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 50%
19 of 29Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

Arham Aryan is a Residential / Group Housing project by Trinity Builders in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800050811 on 3 May 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 10 of the 29 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameArham Aryan
  • TypeResidential / Group Housing
  • Location
    • 10th Road
    • Chembur East
    • Chembur
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • RERA no.P51800050811
  • ReraGenie IDRG-MH-43860

Builder

  • NameTrinity Builders
  • Entity typePartnership
  • PartnersKIRAN MULJI SHAH, DHIREN MAHESH GALA, DHAVAL PRAVINCHANDRA RAMBHIA, PRAVINCHANDRA VALJI RAMBHIA, SUSHIL KUMAR DABHOLKAR, VINAYAK VASUDEVANAND NEVREKAR
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredMay 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 May 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed77 files

Current status

34%10 of 29 units booked
42.0%Work done, per cost certificate

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Arham AryanNA101029029

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 50%.

Arham Aryan: 43% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed44

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots44
Closed/Covered44

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area854 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Mrs. Madhurika JoshiChemburMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2521.44
Proposed, not sanctioned2,241 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchChembur
Estimated costRs 37.30 cr
Cost incurredRs 15.65 cr
Work done41.95%
BuildingWingEstimatedIncurred
Arham AryanNARs 37.30 crRs 15.65 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHISH BHATT & ASSOCIATES
EngineerSURAJ PATHAK
Chartered Accountantsd jaithwar & associates
PartnerRole in project
Trinity Builders-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800027154Dec 2025 → Dec 2026

Reason as filed by the promoterDue to Change in Plan the project was not able to get completed in time. We would like to request you to further grant us extension for 12 months till 31-12-2026.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: RERA Architect Certificate-Arham Aryan -as of 30-06-26.pdf16 Jul 2026
Withdrawal Update Form 2File: Engineer Form 2-Arham Aryan 30-06-26.pdf16 Jul 2026
Withdrawal Update Form 3File: CA_Certificate_form_3_-Arham_Aryan-30-06-26.pdf16 Jul 2026
Withdrawal Update Form 1File: Architect Certificate Jun-25-Arham Aryan-Signed.pdf22 Jun 2026
Withdrawal Update Form 1File: Architect Certificate Form 1 sep 25 Arham Aryan Signed.pdf22 Jun 2026
Withdrawal Update Form 1File: Architect Certificate-Form 1-Dec-25-Arham Aryan-Signed.pdf22 Jun 2026
Withdrawal Update Form 1File: Rera Certificate-Arham Aryan-31-3-26.pdf22 Jun 2026
Withdrawal Update Form 2File: Engineer Form 2-Arham Aryan 30-06-25.pdf22 Jun 2026
Withdrawal Update Form 2File: Engineer Form 2 Arham Aryan 30 09 25.pdf22 Jun 2026
Withdrawal Update Form 2File: Engineer Form 2-Arham Aryan 31-12-25.pdf22 Jun 2026
Withdrawal Update Form 2File: Engineer Form 2-Arham Aryan 31-03-26.pdf22 Jun 2026
Withdrawal Update Form 3File: CA Certificate Form 3-Arham Aryan 30-06-25.pdf22 Jun 2026
Withdrawal Update Form 3File: CA Certificate Form 3 Arham Aryan 30 09 2025.pdf22 Jun 2026
Withdrawal Update Form 3File: CA Certificate Form 3-Arham Aryan 31-12-2025.pdf22 Jun 2026
Withdrawal Update Form 3File: CA Certificate Form 3-Arham Aryan 31-03-2026.pdf22 Jun 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf5 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf5 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf5 Apr 2025
Disclosure of sold/ booked inventoryFile: Arham Aryan-Inventory Discloure 31-3-25.pdf5 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3-Arham Aryan.pdf22 Mar 2025
Declaration in FORM BFile: Form B-Affidavit Cum Declaration.pdf21 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf11 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf11 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: Arham Aryan-Inventory Disclosure as of 31-12-24.pdf11 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Arham Aryan-Form 2A Structural Engineer Certificate.pdf11 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Arham Aryan-Form 5 CA Certificate 23-24.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1-Arham Aryan-30-9-24.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3-Arham Aryan 30-9-24.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate-Form 2-Arham Aryan 30-09-24.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA-Form 2 Engineers Certifcate-Arham Aryan.pdf18 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA form 3 Arham Aryan.pdf18 Apr 2024
Disclosure of sold/ booked inventoryFile: Arham Aryan - Disclosure of Sold.pdf24 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 23 Q2.pdf13 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 23 Q3.pdf13 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 23 Q4.pdf13 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 23 Q2.pdf13 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 23 Q3.pdf13 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 23 Q4.pdf13 Feb 2024
Building plan approvalFile: ARHAM ARYAN AMENDED IOD CERTIFICATE.pdf30 Aug 2023
Layout approvalFile: ARHAM ARYAN AMENDED IOD PLAN.pdf30 Aug 2023
Copy of Layout Approval (in case of layout)File: ARHAM ARYAN AMENDED IOD PLAN.pdf30 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: ARHAM ARYAN AMENDED IOD CERTIFICATE.pdf30 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: ARHAM ARYAN AMENDED CC.pdf30 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA landcost cleafication.pdf30 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sai Prasad FORM - 3.pdf27 Mar 2023
Proforma of Agreement for saleFile: maharera_agreement_-Sai_Prasad[1] revised.pdf27 Mar 2023
Details of encumbrances concerned to FinanceFile: Sai Prasad No encumbrance Letter.pdf16 Mar 2023
Details of encumbrances concerned to LegalFile: Sai Prasad No encumbrance Letter.pdf16 Mar 2023
Layout approvalFile: IOD DWG_1-1.pdf2 Mar 2023
Layout approvalFile: IOD DWG_2-3.pdf2 Mar 2023
Layout approvalFile: IOD DWG_4-6.pdf2 Mar 2023
Layout approvalFile: IOD DWG_7-end.pdf2 Mar 2023
Building plan approvalFile: IOD.pdf2 Mar 2023
PAN CardFile: Trinity Builders Pan Copy.pdf2 Mar 2023
Copy of the legal title reportFile: Title report.pdf2 Mar 2023
Details of encumbrances concerned to FinanceFile: No encumbrance Letter.pdf2 Mar 2023
Details of encumbrances concerned to LegalFile: No encumbrance Letter.pdf2 Mar 2023
Copy of Layout Approval (in case of layout)File: IOD DWG_1-1.pdf2 Mar 2023
Copy of Layout Approval (in case of layout)File: IOD DWG_2-3.pdf2 Mar 2023
Copy of Layout Approval (in case of layout)File: IOD DWG_4-6.pdf2 Mar 2023
Copy of Layout Approval (in case of layout)File: IOD DWG_7-end.pdf2 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: IOD.pdf2 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: FIRST CC.pdf2 Mar 2023
Declaration about Commencement CertificateFile: CC declaration.pdf2 Mar 2023
Declaration in FORM BFile: Form B promoter.pdf2 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 new.pdf2 Mar 2023
CERSAI detailsFile: Cersai Declaration Letter.pdf2 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A disclosure.pdf2 Mar 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER FINAL (1).pdf2 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Trinity Rera Format A- bank letter.pdf2 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation Report for allotment.pdf2 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report on Agreement for Sale.pdf2 Mar 2023

How this compares with Mumbai Suburban

34%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Arham Aryan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chembur East6,700+ in Mumbai Suburban

Builder: Trinity Builders

Trinity Builders has 3 registrations on MahaRERA, including Trinity Paradise Phase 1 and Arham Aryan. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Arham Aryan is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Arham Aryan?

The registered promoter entity is Trinity Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Arham Aryan?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Arham Aryan?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Arham Aryan?

The professionals named in the filing: Architect: ASHISH BHATT & ASSOCIATES; Engineer: SURAJ PATHAK; Chartered Accountant: sd jaithwar & associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Arham Aryan?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Arham Aryan. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Arham Aryan to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.