Home / Browse projects / Pune, Maharashtra / Archana Prestige

Completed No litigation declared Others project

Archana Prestige

By KANIFNATH REALITY

RG-MH-39108 · RERA P52100050992 · Last updated on MahaRERA portal: 16 Dec 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 3 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
44 of 63Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

Archana Prestige is a Others project by KANIFNATH REALITY in Pune, Maharashtra, registered with MahaRERA as P52100050992 on 19 May 2023. The registration is recorded completed; possession was promised by 31 Dec 2025. 19 of the 63 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameArchana Prestige
  • TypeOthers
  • Location
    • Near Delhi Public School
    • Mohamadwadi-Uruli Devachi Road
    • mohamadwadi
    • MOHAMMADWADI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050992
  • ReraGenie IDRG-MH-39108

Builder

  • NameKANIFNATH REALITY
  • Entity typePartnership
  • PartnersPRADIP PARMESHWAR PATHARE, SANJAY SHANKARRAO HAKKE, PRASHANT SHANKARRAO HAKKE, KIRTI PRADIP PATHARE, HEMANT SHANKARRAO HAKKE
  • Other registrations5 more →
  • Completed6 of 6
  • Declared earlier projects5 →

Key dates

this monthRegisteredMay 2023PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 May 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed72 files

Current status

30%19 of 63 units booked
72.8%Work done, per cost certificate

Figures as on 16 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA87521163

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

A: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed37

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots37
Closed/Covered31
Open Space6

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Sep 2024
LandownerVillageDistrict
ANIL D OSWALMOHAMMADWADIPune
ANJALI ANIL OSWALMOHAMMADWADIPune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI3879.91
Proposed, not sanctioned3,880 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEAR BISHOP SCHOOL UNDRI HOLE WASTI PUNE
Estimated costRs 10.25 cr
Cost incurredRs 7.46 cr
Work done72.75%
BuildingWingEstimatedIncurred
ANARs 8.16 crRs 6.88 cr
-NARs 2.09 crRs 58.15 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANIRUDDHA.A.DIXIT DESIGNE STUDIO
ArchitectSANDIP VAYDANDE & ASSOCIATES
ArchitectANIRUDDHA ARUN DIXIT
EngineerSANDIP RANGDAL
EngineerTUSHAR SHAM CHAVAN
Chartered AccountantA V AGRAWAL AND ASSOCIATES
Chartered AccountantAnkit Vikas Agarwal
Chartered AccountantAjit Mundada
PartnerRole in project
KANIFNATH REALITY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: layout_compressed.pdf16 Dec 2025
Building plan approvalFile: Mhada 1_compressed.pdf16 Dec 2025
Building plan approvalFile: Mhada 5 and 6_compressed.pdf16 Dec 2025
Building plan approvalFile: Plan 01.pdf16 Dec 2025
Building plan approvalFile: Plan 02.pdf16 Dec 2025
Building plan approvalFile: Plan 03.pdf16 Dec 2025
Occupational CertificateFile: Oc.pdf16 Dec 2025
Withdrawal Update Form 1File: Architect Prestige.pdf15 Oct 2025
Withdrawal Update Form 2File: Engineers-Prestige.pdf15 Oct 2025
Withdrawal Update Form 3File: CA Archana prestige.pdf15 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Prestige.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Ceriticate Prestige_compressed.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Prestige.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: Sale Data Prestige.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_compressed.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sale Invantory.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prestige CA.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_0001.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_0001_compressed.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Sale Inventory_0001.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Tax Audit Form 05 Prestige 23-24.pdf17 Oct 2024
Form 5 (FY 2024-2025)File: form 05.pdf28 Sep 2024
Form 5 (FY 2023-2024)File: Form 05 Prestige 23-24.pdf28 Sep 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: CA Prestige.pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect Prestige.pdf15 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Eng Certificate Prestige.pdf15 Jul 2024
Disclosure of sold/ booked inventoryFile: 3 Inventory.pdf15 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Prestige.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: img20240427_12433011.pdf27 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Prestige ENG Certifcate.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: Prestige UNSOLD.pdf22 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prestige CA Certifcate.pdf22 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architec prestige.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi form 02 Prestige.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Aertificate Prestige.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect -Prestige.pdf23 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Prestige-Eng.pdf23 Oct 2023
Disclosure of sold/ booked inventoryFile: Prestige -Sold Unsold.pdf23 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prestige-CA.pdf23 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archana Prestige Form 1 Architech.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Arachana Prestige Eng Form 2.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Archana Prestage.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORm 03_compressed.pdf14 May 2023
Copy of the legal title reportFile: Legal Title report.pdf11 May 2023
Details of encumbrances concerned to FinanceFile: Legal Encumrances.pdf11 May 2023
Details of encumbrances concerned to FinanceFile: fin.pdf11 May 2023
Details of encumbrances concerned to LegalFile: Legal Encumrances.pdf11 May 2023
Details of encumbrances concerned to LegalFile: fin.pdf11 May 2023
CERSAI detailsFile: NO Cersai Report.pdf11 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Intrest of Partner.pdf11 May 2023
Other - LegalFile: Legal Encumrances.pdf11 May 2023
PAN CardFile: Pan NO With Sign.pdf4 May 2023
Layout approvalFile: 1-5_compressed.pdf28 Apr 2023
Building plan approvalFile: 2-5_compressed.pdf28 Apr 2023
Building plan approvalFile: 3-5_compressed.pdf28 Apr 2023
Building plan approvalFile: 4-5_compressed.pdf28 Apr 2023
Building plan approvalFile: 5-5_compressed.pdf28 Apr 2023
Copy of Layout Approval (in case of layout)File: 1-5_compressed.pdf28 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: 2-5_compressed.pdf28 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: 3-5_compressed.pdf28 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: 4-5_compressed.pdf28 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: 5-5_compressed.pdf28 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: CC CERTIFICATE_compressed.pdf28 Apr 2023
Declaration about Commencement CertificateFile: Declaration About Commicement.pdf28 Apr 2023
Declaration in FORM BFile: Form B_compressed.pdf28 Apr 2023
Proforma of Agreement for saleFile: RERA-AGREEMENT-ARCHANA PRESTIGE3.pdf28 Apr 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf28 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration About Bank.pdf28 Apr 2023
Deviation Report with respect to Allotment letterFile: Deviation Report Alotment.pdf28 Apr 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report Agreement.pdf28 Apr 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Archana ParadiseSr no 39-09 NIBM Annex Mohamadwadi Tal-Haveli Dist-Pune-411060.140CompletedDec 2022Oct 2021
Pheonix PlazaSr no 2-10A-10 At-Pisoli Tal-Haveli Dist-Pune50CompletedDec 2017Mar 2017
KP SQUAREMilkat no 271-1 near zp school Holkarwadi pune-412308.24CompletedDec 2017Sep 2017

How this compares with Pune

30%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Archana Prestige on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near mohamadwadi13,700+ in Pune

2 kmArchana PrestigeCompleted 60Lapsed / revoked 20Other 71Dot size: filed unitsN

Filed coordinates, straight-line distance. 151 registered projects within 2 km.

Builder: KANIFNATH REALITY

KANIFNATH REALITY has 6 registrations on MahaRERA, including ARCHANA PARADISE and ARCHANA PARADISE WING A. Its filings disclose 5 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Archana Prestige is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Archana Prestige?

The registered promoter entity is KANIFNATH REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Archana Prestige?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Archana Prestige?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Archana Prestige?

The professionals named in the filing: Architect: ANIRUDDHA.A.DIXIT DESIGNE STUDIO; Architect: SANDIP VAYDANDE & ASSOCIATES; Architect: ANIRUDDHA ARUN DIXIT; Engineer: SANDIP RANGDAL; Engineer: TUSHAR SHAM CHAVAN; Chartered Accountant: A V AGRAWAL AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Archana Prestige?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Archana Prestige. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Archana Prestige to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.