Home / Browse projects / Pune, Maharashtra / AQUILA

Registered Litigation declared Residential / Group Housing project

AQUILA

By Dilip Baburao Tupe

RG-MH-32530 · RERA P52100080347 · Last updated on MahaRERA portal: 17 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 completed earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2028Possession promisedmoved 6 months from the original
2 of 11Construction stages donefurthest along: Podiums (if any), 85%
39 of 53Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

AQUILA is a Residential / Group Housing project by Dilip Baburao Tupe in Pune, Maharashtra, registered with MahaRERA as P52100080347 on 26 May 2025. Possession is promised by 30 Sep 2028. The completion date has moved by 6 months from the original filing. 14 of the 53 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameAQUILA
  • TypeResidential / Group Housing
  • Location
    • BS Tupe (DP) Road
    • Malwadi
    • Hadapsar
    • Haveli
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100080347
  • ReraGenie IDRG-MH-32530

Builder

  • NameDilip Baburao Tupe
  • Entity typeIndividual
  • GSTIN27ADKPT4449B3ZB
  • Other registrations3 more →
  • Completed1 of 4
  • Declared earlier projects6 →

Key dates

this monthRegisteredMay 2025First promiseMar 2028Revised toSep 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 May 2025
  • Promised completion30 Sep 2028
  • Revised completionRevised to 30 Sep 2028 (originally 31 Mar 2028)
  • Buildings1 building record
  • Documents filed74 files

Current status

26%14 of 53 units booked
14.2%Work done, per cost certificate

Figures as on 17 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AQUILA - Tower FNA201453053

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 85%.

AQUILA - Tower F: 26% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)85%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes20%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed197

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots197
Closed/Covered115
Open Space82

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,596 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jun 2025
LandownerVillageDistrict
Anuradha Dilip TupeHadapsarPune
Indrajeet Dilip TupeHadapsarPune
Samruddhi Dilip TupeHadapsarPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI8854.63
Proposed, not sanctioned8,855 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 11 TO 20 T SQUARE TUPE PATIL ROAD NEXT TO MARVEL RITZ HADAPSAR PUNE MAHARASHTRA 411028
Estimated costRs 54.50 cr
Cost incurredRs 7.76 cr
Work done14.24%
BuildingWingEstimatedIncurred
AQUILA - Tower FNARs 49.05 crRs 7.71 cr
-NARs 5.45 crRs 5.00 lakh

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAmit Bhat Architects
ArchitectMangesh Gotal
ArchitectA Design Studio
ArchitectAr. Mangesh Gotal
EngineerStrudcom Pvt Ltd
EngineerAshwin Bagde Envirosphere Consultant and Engineer
EngineerAbhishek Potphode PROTECH SAFE
EngineerNEHA BHAKARE
Chartered AccountantShikha Kodwani S Kodwani & Co
Chartered AccountantS Kodwani & Co
PartnerRole in project
Dilip Baburao Tupe-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30062501862Mar 2028 → Sep 2028

Reason as filed by the promoterWe, the Promoter of the registered project “AQUILA” bearing MahaRERA Registration No. P52100080347, hereby submit this declaration for extension of the project completion date under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. At the time of project registration, the date of completion was declared as 31/03/2028. However, we now seek to revise and extend the project completion timeline by a period of six months, i.e., up to 30/09/2028. The reason for seeking this extension is that, although the project registration for AQUILA was granted recently on 26/05/2025, a con

Litigation declared1

CaseCourtStatus
325/2011Civil Judge Senior Division PuneOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Apr 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 May 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2028

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 AQUILA.pdf17 Jul 2026
Withdrawal Update Form 2File: FORM 2 AQUILA.pdf17 Jul 2026
Withdrawal Update Form 3File: FORM 3 AQUILA.pdf17 Jul 2026
Form 2A (FY 2025-2026)File: AQUILA FORM 2A For 2025-26.pdf8 Jul 2026
Withdrawal Update Form 1File: Form 1 Aquila Mar 26.pdf29 Jun 2026
Withdrawal Update Form 2File: Form 2 Aquila Mar 26.pdf29 Jun 2026
Withdrawal Update Form 3File: Form 3 Aquila Mar 26.pdf29 Jun 2026
Withdrawal Update Form 1File: Form 1 Aquila Mar 26.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 Aquila Mar 26.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 Aquila Mar 26.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1 - Aquila as on Dec 2025.pdf22 Jan 2026
Withdrawal Update Form 2File: Form 2 - Aquila as on Dec 2025.pdf22 Jan 2026
Withdrawal Update Form 3File: Form 3 - Aquila as on Dec 2025.pdf22 Jan 2026
Withdrawal Update Form 1File: Form 1 - Aquila as on Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 - Aquila as on Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 - Aquila as on Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 - Aquila as on Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 - Aquila as on Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 - Aquila as on Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 - Aquila as on Sep 2025.pdf12 Jan 2026
Withdrawal Update Form 2File: Form 2 - Aquila as on Sep 2025.pdf12 Jan 2026
Withdrawal Update Form 3File: Form 3 - Aquila as on Sep 2025.pdf12 Jan 2026
Layout approvalFile: 1-23 - Highlighted.pdf23 Sep 2025
Layout approvalFile: 1-23.pdf23 Sep 2025
Layout approvalFile: 2-23.pdf23 Sep 2025
Layout approvalFile: 3-23.pdf23 Sep 2025
Layout approvalFile: 4-23.pdf23 Sep 2025
Layout approvalFile: 5-23.pdf23 Sep 2025
Layout approvalFile: 6-23.pdf23 Sep 2025
Layout approvalFile: 7-23.pdf23 Sep 2025
Building plan approvalFile: 19-23 - TF.pdf23 Sep 2025
Building plan approvalFile: 20-23 - TF.pdf23 Sep 2025
Building plan approvalFile: 21-23 - TF.pdf23 Sep 2025
Building plan approvalFile: 22-23.pdf23 Sep 2025
Building plan approvalFile: 23-23.pdf23 Sep 2025
Withdrawal Update Form 1File: Form 1 - Aquila as on June 2025.pdf28 Jul 2025
Withdrawal Update Form 2File: Form 2 - Aquila as on June 2025.pdf28 Jul 2025
Withdrawal Update Form 3File: Form 3 - Aquila as on June 2025.pdf28 Jul 2025
Commencement Certificates / NA Order for plotted developmentFile: AQUILA TOWER F PLOT INCREASE FINAL.pdf20 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 AQUILA NEW.pdf14 May 2025
Other - FinanceFile: Decalartion regarding form 3 (2).pdf14 May 2025
Copy of the legal title reportFile: 1 Copy of the legal title report (2)_removed (1).pdf4 Apr 2025
Declaration in FORM BFile: Dilip Baburao tupe (1).pdf26 Mar 2025
Declaration in FORM BFile: co promoters of dilip baburao tupe (1).pdf26 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclousure of other sites.PDF26 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: AQILLA bank Confirmation letter_removed.pdf26 Mar 2025
Layout approvalFile: layout 1 AQUILA.pdf25 Mar 2025
Building plan approvalFile: 7 Copy of Layout Approval (in case of layout).pdf25 Mar 2025
Building plan approvalFile: 8 Copy of Layout Approval (in case of layout).pdf25 Mar 2025
Building plan approvalFile: 9 Copy of Layout Approval (in case of layout).pdf25 Mar 2025
Building plan approvalFile: 10 Copy of Layout Approval (in case of layout).pdf25 Mar 2025
PAN CardFile: Dilip Tupe PAN CARD.pdf25 Mar 2025
Details of encumbrances concerned to FinanceFile: organized (6).pdf25 Mar 2025
Copy of Layout Approval (in case of layout)File: layout 1 AQUILA.pdf25 Mar 2025
Proforma of Allotment letterFile: Allotment Letter_AQUILA_removed.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mangesh Gotal (1).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Neha Bhakare.pdf25 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: doc08806720250324203316_rotated.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 10 Copy of Layout Approval (in case of layout).pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 9 Copy of Layout Approval (in case of layout).pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 7 Copy of Layout Approval (in case of layout).pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 8 Copy of Layout Approval (in case of layout).pdf25 Mar 2025
Other - LegalFile: POA_DilipTupe_RERA_Promoter_OTHER LEGAL 1.pdf25 Mar 2025
Other - LegalFile: Declaration-2.PDF25 Mar 2025
Other - LegalFile: Revenue Share_AQUILA.pdf25 Mar 2025
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate (2).PDF25 Mar 2025
CERSAI detailsFile: CERSAI REPORT_removed.pdf25 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 1 Declaration about all RERA Designated Bank Accounts _Format A_.pdf25 Mar 2025
Deviation Report with respect to Allotment letterFile: Deviation Report Allotment.PDF25 Mar 2025
Details of encumbrances concerned to LegalFile: organized (6).pdf25 Mar 2025
Other - TechnicalFile: Declaration.PDF25 Mar 2025
Deviation Report with respect to model copy of AgreementFile: Deviation Report (Agreement)_11zon.pdf25 Mar 2025
Proforma of Agreement for saleFile: GetUserDocumentFileContent _32__removed.pdf25 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclouser of finance.PDF25 Mar 2025

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise2 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
STELLAP52100080288Malwadi, Pune78May 2025OngoingMar 2028Not due yet
AstranaP52100055666Malwadi, Hadapsar, Pune567Apr 2024OngoingMar 2028Not due yet
Freedom High StreetP52100055913Malwadi, Pune77Apr 2024CompletedDec 2026Jun 2026
Empress ViewS No 585 CTS No 3278 Plot No 85 92 Bibwewadi - Munjeri Pune3-OngoingMar 2025Mar 2025
BELLEZA C WINGSr No 236 3 4 5 Malwadi Hadapsar Pune56-CompletedMar 2023Aug 2022

How this compares with Pune

26%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AQUILA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Malwadi13,700+ in Pune

2 kmAQUILACompleted 57Lapsed / revoked 23Other 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 148 registered projects within 2 km.

Builder: Dilip Baburao Tupe

Dilip Baburao Tupe has 4 registrations on MahaRERA, including Astrana and Freedom High Street. Its filings disclose 6 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AQUILA is delayed beyond 30 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AQUILA?

The registered promoter entity is Dilip Baburao Tupe, an individual as per the filing. Its GSTIN 27ADKPT4449B3ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AQUILA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AQUILA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AQUILA?

The professionals named in the filing: Architect: Amit Bhat Architects; Architect: Mangesh Gotal; Architect: A Design Studio; Architect: Ar. Mangesh Gotal; Engineer: Strudcom Pvt Ltd; Engineer: Ashwin Bagde Envirosphere Consultant and Engineer. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AQUILA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AQUILA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AQUILA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.