Kumar Parc Residences - A2
By Kumar Properties Infratech Developers Pvt Ltd
RG-MH-79531 · RERA P52100055344 · Last updated on MahaRERA portal: 17 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- Rs 94.61 crore secured on the land, in favour of Piramal Enterprises Ltd, Piramal Finance Ltd
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kumar Parc Residences - A2 is a Residential / Group Housing project by Kumar Properties Infratech Developers Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100055344 on 18 Mar 2024. Possession is promised by 25 May 2028. 326 of the 360 units on this registration are recorded sold or booked, and 15 of 33 construction stages are filed complete.
At a glance
Project
- NameKumar Parc Residences - A2
- TypeResidential / Group Housing
- Location
- Hadapsar Mundhawa Road
- Magarpatta
- Hadapsar
- Haveli
- Pune
- 411028
- Pincode411028
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100055344
- ReraGenie IDRG-MH-79531
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Mar 2024
- Promised completion25 May 2028
- Revised completionNone
- Buildings3 building records
- Documents filed92 files
Current status
Figures as on 17 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A2 - A wing | NA | 32 | 30 | 120 | 0 | 120 |
| A2 - B wing | NA | 32 | 30 | 120 | 0 | 120 |
| A2 - C wing | NA | 32 | 30 | 120 | 0 | 120 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 81%.
A2 - A wing61%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 36% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 45% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 16% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A2 - B wing62%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 81% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 41% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 49% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 14% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A2 - C wing62%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 81% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 49% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 11% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed302
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A2 - A wing | 101 | 101 |
| A2 - B wing | 100 | 100 |
| A2 - C wing | 101 | 101 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A2 - A wing | NA | Rs 49.34 cr | Rs 17.89 cr |
| A2 - C wing | NA | Rs 49.34 cr | Rs 17.13 cr |
| A2 - B wing | NA | Rs 48.72 cr | Rs 18.39 cr |
| - | NA | Rs 21.96 cr | Rs 19.38 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vishal J Deshpande |
| Engineer | Mahesh Rasal |
| Engineer | Harshad Pendse |
| Engineer | Amit Shilimkar |
| Chartered Accountant | Supriya Mundada |
| Chartered Accountant | GMKS & Co. |
| Partner | Role in project |
|---|---|
| Kumar Properties Infratech Developers Pvt Ltd | - |
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 325/2011 | Civil Judge Junior Division | Pending |
| 325/2011 | Civil Judge | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Feb 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Sep 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Apr 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 25 May 2028
Documents filed92
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: 1_Ar Certificate.pdf | 17 Jul 2026 |
| Withdrawal Update Form 2File: 2_Engg Certificate.pdf | 17 Jul 2026 |
| Withdrawal Update Form 3File: 3_CA Certificate_compressed.pdf | 17 Jul 2026 |
| Building plan approvalFile: 2_260306_Parking Layout Basement.pdf | 28 Apr 2026 |
| Building plan approvalFile: 3_260306_Podium Parking Layout.pdf | 28 Apr 2026 |
| Building plan approvalFile: 4_260306_Building A2-Floor Plans.pdf | 28 Apr 2026 |
| Building plan approvalFile: 5_260306_Building A2-Floor Plans.pdf | 28 Apr 2026 |
| Building plan approvalFile: 6_260306_Building A2-Floor Plans Terrace.pdf | 28 Apr 2026 |
| Building plan approvalFile: 7_260306_Building A2-Elevation.pdf | 28 Apr 2026 |
| Building plan approvalFile: 8_260306_Building A2-Section.pdf | 28 Apr 2026 |
| Building plan approvalFile: 1_260306_Building Layout.pdf | 28 Apr 2026 |
| Form 2A (FY 2025-2026)File: Form 2A March 2026.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: 1_Ar Certificate_Signed.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: 2_Engg Certificate.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: 3_CA Certificate.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: 1_Ar Certificate_Signed.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: 2_Engg Certificate.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: 3_CA Certificate_compressed (8).pdf | 16 Jan 2026 |
| Withdrawal Update Form 1File: 1_Ar Certificate_Signed.pdf | 16 Oct 2025 |
| Withdrawal Update Form 1File: 1_Ar Certificate_Signed.pdf | 16 Oct 2025 |
| Withdrawal Update Form 2File: 2_Engg Certificate.pdf | 16 Oct 2025 |
| Withdrawal Update Form 2File: 2_Engg Certificate.pdf | 16 Oct 2025 |
| Withdrawal Update Form 3File: 3_CA certificate_Signed_compressed.pdf | 16 Oct 2025 |
| Withdrawal Update Form 3File: 3_CA certificate_Signed_compressed.pdf | 16 Oct 2025 |
| Layout approvalFile: 250811_Layout_1.pdf | 26 Sep 2025 |
| Layout approvalFile: 250811_Layout_2.pdf | 26 Sep 2025 |
| Form 5 (FY 2024-2025)File: Form 5_Parc Residences_A2_Signed.pdf | 23 Sep 2025 |
| Withdrawal Update Form 1File: 1_Arch Certificate_signed Copy.pdf | 31 Jul 2025 |
| Withdrawal Update Form 2File: 2_Engg Certificate.pdf | 31 Jul 2025 |
| Withdrawal Update Form 3File: 3_CA Certificate.pdf | 31 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate_compressed.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of Sold Inventory.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate_R1.pdf | 23 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate_compressed (1).pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of Sold Inventory.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Ar Certificate.pdf | 21 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate_compressed.pdf | 21 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 21 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: 5_Disclosure of sold Inventory.pdf | 21 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: From 5-Parc Residences A2 March 24.pdf | 14 Oct 2024 |
| Layout approvalFile: 240913_Layout.pdf | 7 Oct 2024 |
| Building plan approvalFile: 240913_Building Plan_1.pdf | 7 Oct 2024 |
| Building plan approvalFile: 240913_Building Plan_2.pdf | 7 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: 240913_Layout.pdf | 7 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 240913_CC.pdf | 7 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 240913_Building Plan_1.pdf | 7 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 240913_Building Plan_2.pdf | 7 Oct 2024 |
| Declaration about Commencement CertificateFile: 240916_Declaration about CC.pdf | 7 Oct 2024 |
| Proforma of Agreement for saleFile: 240913_AFS.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate_compressed.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of sold inventory.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 22 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 22 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 5_Form 2A.pdf | 22 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 29_Kumar Parc Residences - A2.pdf | 22 Apr 2024 |
| Building plan approvalFile: 240222 STILT TYP FP.pdf | 27 Feb 2024 |
| Building plan approvalFile: 240222 2ND 7TH FP.pdf | 27 Feb 2024 |
| Building plan approvalFile: 240222 11TH FP.pdf | 27 Feb 2024 |
| Building plan approvalFile: 240222 BASEMENT FLOOR PLAN.pdf | 27 Feb 2024 |
| Building plan approvalFile: 240222 PODIUM PARKING PLAN.pdf | 27 Feb 2024 |
| Layout approvalFile: 240222_3_Layout.pdf | 27 Feb 2024 |
| Copy of Layout Approval (in case of layout)File: 240222_3_Layout.pdf | 27 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 240222 STILT TYP FP.pdf | 27 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 240222 2ND 7TH FP.pdf | 27 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 240222 11TH FP.pdf | 27 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 240222 BASEMENT FLOOR PLAN.pdf | 27 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 240222 PODIUM PARKING PLAN.pdf | 27 Feb 2024 |
| CERSAI detailsFile: 240227_CERSAI Declaration.pdf | 27 Feb 2024 |
| Other - TechnicalFile: 240217_Annexure A.pdf | 27 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: 3_Encumbrance Certificate_Finance.pdf | 12 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: 3_Encumbrance Certificate_Legal.pdf | 12 Feb 2024 |
| Details of encumbrances concerned to LegalFile: 3_Encumbrance Certificate_Finance.pdf | 12 Feb 2024 |
| Details of encumbrances concerned to LegalFile: 3_Encumbrance Certificate_Legal.pdf | 12 Feb 2024 |
| Declaration in FORM BFile: 6_Form B_Declaration.pdf | 9 Feb 2024 |
| CERSAI detailsFile: 15_CERSAI_Report.pdf | 9 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 19_DOI_HKJ.pdf | 9 Feb 2024 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Kumar Parc Residences - B2P52100049839 | Magarpatta, Pune | 230 | Mar 2023 | Certificate Signed | Dec 2027 | Not due yet |
| Kumar Parc residences - A1P52100032022 | Hadapsar, Pune | 360 | Dec 2021 | Certificate Signed | Nov 2026 | Not due yet |
| Kumar Parc Residences - C MhadaP52100047940 | Hadapsar, Pune | 140 | Dec 2022 | Certificate Signed | Nov 2025 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 92 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Kumar Parc Residences - A2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Magarpatta13,700+ in Pune
Filed coordinates, straight-line distance. 194 registered projects within 2 km.
Amanora Arbano Towers 73,74,75 and 76
City Corporation Limited
Astrana
Dilip Baburao Tupe
Leisure Town Phase 1
Sai Proviso Homes
ARV Newtown Phase III
Vedant Infracon
Kumar Parc residences - A1
Kumar Properties Infratech Developers Pvt
Amanora Gateway Towers 2 - Towers 102 and 103
City Corporation Limited
Builder: Kumar Properties Infratech Developers Pvt Ltd
Kumar Properties Infratech Developers Pvt Ltd has 5 registrations on MahaRERA, including Kumar Parc residences - A1 and Kumar Parc Residences - C Mhada. Its filings disclose 4 earlier MahaRERA projects, none completed yet. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Kumar Parc Residences - A2 is delayed beyond 25 May 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kumar Parc Residences - A2?
The registered promoter entity is Kumar Properties Infratech Developers Pvt Ltd, a company as per the filing. Its CIN U45209PN2019PTC183489 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kumar Parc Residences - A2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kumar Parc Residences - A2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kumar Parc Residences - A2?
The professionals named in the filing: Architect: Vishal J Deshpande; Engineer: Mahesh Rasal; Engineer: Harshad Pendse; Engineer: Amit Shilimkar; Chartered Accountant: Supriya Mundada; Chartered Accountant: GMKS & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kumar Parc Residences - A2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback