Home / Browse projects / Pune, Maharashtra / Aqua Life

Registered No litigation declared Residential / Group Housing project

Aqua Life

By Legacy Lifespaces LLP

RG-MH-23202 · RERA P52100078125 · Last updated on MahaRERA portal: 18 Apr 2026

Source: official MahaRERA filing

Red flags

  • Possession 2 months past the filed date
  • Rs 150.00 crore secured on the land, in favour of Aditya Birla Capital LTD, Aditya Birla Capital Ltd and 1 more

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 4 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Aug 2026Possession promised2 months past this date
6 of 11Construction stages donefurthest along: Installation of Lifts, 90%
9 of 82Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 124 documents Report an error

Aqua Life is a Residential / Group Housing project by Legacy Lifespaces LLP in Pune, Maharashtra, registered with MahaRERA as P52100078125 on 25 Nov 2024. Possession was promised by 30 Aug 2026 and is now 2 months past that date. 73 of the 82 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameAqua Life
  • TypeResidential / Group Housing
  • Location
    • Ravet BRT Road
    • Ravet
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • RERA no.P52100078125
  • ReraGenie IDRG-MH-23202

Builder

  • NameLegacy Lifespaces LLP
  • Entity typePartnership
  • Other registrations7 more →
  • Completed4 of 8
  • Past their filed date1
  • Declared earlier projects11 →

Key dates

2 months past promisethis monthRegisteredNov 2024PromisedAug 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Nov 2024
  • Promised completion30 Aug 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed124 files

Current status

89%73 of 82 units booked
94.2%Work done, per cost certificate

Figures as on 18 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WingNA141482082

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

B Wing: 63% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Closed/Covered60

Land and ownership9

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,029 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Capital LTD, Aditya Birla Capital Ltd, Aditya Birla Finance Ltd
Secured amountRs 150.00 crore
CERSAI search filedYes
Declared on2 Mar 2026
LandownerVillageDistrict
Mangala Balu BhondavePimpri Chinchawad (M Corp.)Pune
Sandeep Balu BhondavePimpri Chinchawad (M Corp.)Pune
Manda alias Kusum Sandeep BhondavePimpri Chinchawad (M Corp.)Pune
Sumeet Sandeep BhondavePimpri Chinchawad (M Corp.)Pune
Sujal Sandeep BhondavePimpri Chinchawad (M Corp.)Pune
Sunanda Vishwas BhondavePimpri Chinchawad (M Corp.)Pune
Indrajeet Vishwas BhondavePimpri Chinchawad (M Corp.)Pune
Balu Damu BhondavePimpri Chinchawad (M Corp.)Pune
Vishwas Damu BhondavePimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI10903.6
Proposed, not sanctioned8,955 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, RAINBOW PLAZA, SHOP NO. 22, RAHATANI PIMPLE SAUDAGAR, PUNE, MAHARASHTRA, PIN 411017
Estimated costRs 25.98 cr
Cost incurredRs 24.46 cr
Work done94.17%
BuildingWingEstimatedIncurred
B WingNARs 22.65 crRs 21.84 cr
-NARs 3.33 crRs 2.62 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYogesh Manakshe
EngineerRupesh Mahamuni
Chartered AccountantPravin E Pise
Chartered AccountantG M Achhara and Associates
PartnerRole in project
Legacy Lifespaces LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Nov 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed124

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 124 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Q-4-Form-1 Architect Certificate Aqualife - B-07-04-2026.pdf18 Apr 2026
Withdrawal Update Form 2File: Q4- Form 2- Engineers Certificate - 17-04-2026.pdf18 Apr 2026
Withdrawal Update Form 3File: Q4-FY-25-26-Aqualife-B - Form-3.pdf18 Apr 2026
Withdrawal Update Form 1File: Q3- Form 1 Architects Certificate Aqua Life B Building- 06-01-2026.pdf27 Jan 2026
Withdrawal Update Form 2File: Form 2- Engineers Certificate -.pdf27 Jan 2026
Withdrawal Update Form 3File: Q2 - Form 3 - Aqua Life B - 2025-2026.pdf27 Jan 2026
Withdrawal Update Form 1File: Q3- Form 1 Architects Certificate Aqua Life B Building- 06-01-2026.pdf22 Jan 2026
Withdrawal Update Form 2File: Form 2- Engineers Certificate -.pdf22 Jan 2026
Withdrawal Update Form 3File: Q2 - Form 3 - Aqua Life B - 2025-2026.pdf22 Jan 2026
Withdrawal Update Form 1File: Q2 - Form 1 - Aqua Life B - 2025-2026.pdf9 Jan 2026
Withdrawal Update Form 2File: Form 2- Engineers Certificate -.pdf9 Jan 2026
Withdrawal Update Form 3File: Q2 - Form 3 - Aqua Life B - 2025-2026.pdf9 Jan 2026
Withdrawal Update Form 1File: Q2 - Form 1 - Aqua Life B - 2025-2026.pdf18 Oct 2025
Withdrawal Update Form 2File: Q2-Form 2 - Aqua Life B - 2025-2026.pdf18 Oct 2025
Withdrawal Update Form 3File: Q2 - Form 3 - Aqua Life B - 2025-2026.pdf18 Oct 2025
Withdrawal Update Form 1File: Q2 - Form 1 - Aqua Life B - 2025-2026.pdf17 Oct 2025
Withdrawal Update Form 2File: Q2-Form 2 - Aqua Life B - 2025-2026.pdf17 Oct 2025
Withdrawal Update Form 3File: Q2 - Form 3 - Aqua Life B - 2025-2026.pdf17 Oct 2025
Form 2A (FY 2024-2025)File: From2A Aqua Life.pdf4 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 - Aqua Life - 24-25.pdf30 Sep 2025
Form 1File: Form-1-Aqualife-B-Q1-Fy-25-26.pdf19 Jul 2025
Form 2File: Form-2-08-07-2025.pdf19 Jul 2025
Form 3File: Form-3 15-07-2025.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold Aqua Life B Building.pdf19 Jul 2025
Self-declaration of Quarterly ProgressFile: QPR Self Declaration.pdf19 Jul 2025
Form 1File: 1) Architects Certificate 05-01-2025.pdf15 Jul 2025
Form 2File: 1) Aqualife Engineer Certificate 15-1-25.pdf15 Jul 2025
Form 3File: 1) CA Certificate 18-01-2025.pdf15 Jul 2025
Disclosure of Sold and Booked InventoryFile: 1) Aqua Life Sold-Unsold Building-B.pdf15 Jul 2025
Self-declaration of Quarterly ProgressFile: 1) Aqua Life QPR Self Decl.pdf15 Jul 2025
Form 1File: 2) Architect's Certificate-Aqua-life -B 10-04-2025.pdf15 Jul 2025
Form 2File: 2) Engineers Certificate 03-04-2025.pdf15 Jul 2025
Form 3File: 2) CA Certificate 04-04-2025.pdf15 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2) Aqua Life Sold-Unsold 31-03-2025.pdf15 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Aqualife B.pdf26 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Architects Certificate 02-04-2025_organized.pdf26 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aqua Life B-Building Form-3.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: Aqua Life Sold-Unsold 31-03-2025.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: Aqua Life Sold-Unsold Building-B.pdf11 Feb 2025
Disclosure of sold/ booked inventoryFile: Aqua Life Sold-Unsold Building-B.pdf11 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 05-01-2025.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Architects Certificate 05-01-2025.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aqua Life Engineers Certificate.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aqua Life Engineers Certificate.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 05-01-2025.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Architects Certificate 05-01-2025.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aqua Life Engineers Certificate.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aqua Life Engineers Certificate.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 05-01-2025.pdf29 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 18-01-2025.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 05-01-2025.pdf29 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 18-01-2025.pdf29 Jan 2025
Proforma of Agreement for saleFile: Revised Draft agreement - Aqua Life -.pdf28 Dec 2024
Proforma of Agreement for saleFile: Revised Draft agreement - Aqua Life -.pdf28 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AQua life architect certifi.pdf27 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AQua life architect certifi.pdf27 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AQua life architect certifi.pdf27 Nov 2024
Other - FinanceFile: Declaration about land cost NIL.pdf19 Nov 2024
Other - FinanceFile: Suppl Agreement with Covering letter.pdf19 Nov 2024
Other - FinanceFile: 1- 1-10 - only hilight_page.pdf19 Nov 2024
Copy of the legal title reportFile: legacy search report Ravet 147-1_compressed.pdf11 Nov 2024
Other - LegalFile: 1-10_compressed.pdf11 Nov 2024
Other - LegalFile: 1-10_compressed.pdf11 Nov 2024
Other - LegalFile: 11-20_compressed.pdf11 Nov 2024
Other - LegalFile: 21-30_compressed.pdf11 Nov 2024
Other - LegalFile: 31-40_compressed.pdf11 Nov 2024
Other - LegalFile: 41-44_compressed.pdf11 Nov 2024
Other - LegalFile: 11-20_compressed.pdf11 Nov 2024
Other - LegalFile: 21-30_compressed.pdf11 Nov 2024
Other - LegalFile: 31-40_compressed.pdf11 Nov 2024
Other - LegalFile: 41-50_compressed.pdf11 Nov 2024
Other - LegalFile: 51-60_compressed.pdf11 Nov 2024
Other - LegalFile: 61-70_compressed.pdf11 Nov 2024
Other - LegalFile: 71-78_compressed.pdf11 Nov 2024
Other - LegalFile: 1-12 Release Deed 645-2016.pdf11 Nov 2024
Other - LegalFile: 13-24 Release Deed 645-2016.pdf11 Nov 2024
Other - LegalFile: 25-36 Release Deed 645-2016.pdf11 Nov 2024
Other - LegalFile: Declaration About Co-Promoters.pdf11 Nov 2024
Deviation Report with respect to Allotment letterFile: No Deviation In Allotment Letter.pdf11 Nov 2024
Other - FinanceFile: Declaration About Lrndorvners RERA account.pdf11 Nov 2024

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Legacy CelestiaLegacy Celestia Survey No. 92 village Wakad Taluka Mulshi Dist Pune 41105786CompletedSep 2024Feb 2023
Legacy IvyLegacy Ivy Survey No. 19 Village Punawale Taluka Mulshi Dist Pune 411033164CompletedJul 2024Apr 2023
Legacy AeonLegacy Aeon Suevey No. 128 Village Baner Taluka Haveli Dist. Pune 41104566CompletedJun 2024Jul 2022
Legacy VistaLegacy Vista Survey No. 50 Village Rahatani Taluka Haveli Dist Pune 41101794CompletedDec 2022Jun 2022

How this compares with Pune

89%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aqua Life on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ravet13,700+ in Pune

Builder: Legacy Lifespaces LLP

Legacy Lifespaces LLP has 8 registrations on MahaRERA, including Legacy Aura and Legacy Vista. Its filings disclose 11 earlier MahaRERA projects: declares 9 of 9 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Aqua Life is delayed beyond 30 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aqua Life?

The registered promoter entity is Legacy Lifespaces LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aqua Life?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aqua Life?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aqua Life?

The professionals named in the filing: Architect: Yogesh Manakshe; Engineer: Rupesh Mahamuni; Chartered Accountant: Pravin E Pise; Chartered Accountant: G M Achhara and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aqua Life?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aqua Life. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aqua Life to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.