Home / Browse projects / Palghar, Maharashtra / APEKSHA COMPLEX

Registered No litigation declared Residential / Group Housing project

APEKSHA COMPLEX

By KOTHARI CONSTRUCTION CO

RG-MH-26038 · RERA P99000009883 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
22 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 99%
28 of 208Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 84 documents Report an error

APEKSHA COMPLEX is a Residential / Group Housing project by KOTHARI CONSTRUCTION CO in Palghar, Maharashtra, registered with MahaRERA as P99000009883 on 22 Aug 2017. Possession is promised by 30 Dec 2026. The completion date has moved by 48 months from the original filing. 180 of the 208 units on this registration are recorded sold or booked, and 22 of 44 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAPEKSHA COMPLEX
  • TypeResidential / Group Housing
  • Location
    • ARIHANT INDUSTRIAL ESTATE
    • WALIV
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000009883
  • ReraGenie IDRG-MH-26038

Builder

  • NameKOTHARI CONSTRUCTION CO
  • Entity typePartnership
  • PartnersKAVITA MAHENDRA KOTHARI, MADANLAL FOJMAL JAIN, PRAKASH FOJMAL JAIN, FEROZ AMJAD KHAN
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 30 Dec 2022)
  • Buildings4 building records
  • Documents filed84 files

Current status

87%180 of 208 units booked
98.0%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA9742850
BNA97561268
CNA9742648
DNA9742042

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 99%.

A81%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%
B81%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%
C81%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%
D81%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes98%
Water SupplyYes98%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes98%
Storm Water DrainsYes98%
Landscaping & Tree PlantingYes98%
Street LightingYes98%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes98%
Solid Waste Management And DisposalYes98%
Water conservation /Rain water harvestingYes98%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes98%
Electrical meter room, sub-station, receiving stationYes98%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes98%

Parking filed64

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots64
Closed/Covered4
Open Space60
BuildingClosed/CoveredOpen SpaceTotal
A11516
B11516
C11516
D11516

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,725 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Apr 2026

Approvals and building plan

Sanctioning authorityVASAI VIRAR CITY MUNICIPAL CORPORATION
Permissible FSI7104.56
Proposed, not sanctioned5,225 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOSTWAL HOUSE, MIRA BHAYANDER ROAD, OPP SHIVAR GARDEN, MIRA ROAD EAST, THANE 401107
Estimated costRs 22.60 cr
Cost incurredRs 22.15 cr
Work done98.0%
BuildingWingEstimatedIncurred
BNARs 6.75 crRs 6.62 cr
ANARs 5.10 crRs 5.00 cr
CNARs 4.35 crRs 4.26 cr
DNARs 4.15 crRs 4.07 cr
-NARs 2.25 crRs 2.21 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY S NARANG S NARANG
EngineerSANJAY S NARANG
Chartered AccountantRamesh Lukad
Chartered AccountantR D LUKAD CO
PartnerRole in project
KOTHARI CONSTRUCTION CO-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000013123Dec 2022 → Dec 2023

Reason as filed by the promoterWe have received the revised Commencement certificate on 06.09.2021 and the construction work of A 7 B - wing is in progress hence we need extension

EXT99000018371Dec 2022 → Dec 2026

Reason as filed by the promoterPossession of C & D - Wing are handover and Society is formed and construction of A - Wing are completed upto 76% & B - Wing is completed upto 90% , due to getting revised the Commencement Certificate dated 06.09.2021, delay is caused

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12502532PRAKASH FOJMAL JAINKOTHARI CONSTRUCTION CO23/07/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed84

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE 14-04-2026.pdf24 Apr 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE 14-04-2026.pdf24 Apr 2026
Withdrawal Update Form 3File: C A CERTIFICATE 21-04-2026.pdf24 Apr 2026
Form 5 (FY 2025-2026)File: FORM 5 2025-26-KCC.pdf22 Apr 2026
Withdrawal Update Form 1File: Architect Certificate 31-12-2025.pdf11 Feb 2026
Withdrawal Update Form 2File: Engineer Certificate 31-12-2025.pdf11 Feb 2026
Withdrawal Update Form 3File: C A Certificate 24-01-2026.pdf11 Feb 2026
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 C A Certificate 23-24.pdf11 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance - 2024.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 07-01-2025.pdf1 Feb 2025
Certificates of CA (Form 3)File: C A Certificate 31-01-2025.pdf1 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 07-01-2025.pdf1 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory 31-01-2025.pdf1 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2023-24-KCC.pdf19 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 29-03-2024.pdf11 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 29-03-2024.pdf11 Apr 2024
Certificates of CA (Form 3)File: C A Certificate 04-04-2024.pdf11 Apr 2024
Certificates of CA (Form 3)File: C A Certificate.pdf28 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf28 Dec 2023
Declaration in FORM BFile: Form - B 26-12-2023.pdf26 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Quality Assurance - 2023.pdf26 Dec 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf26 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 18-12-2023.pdf23 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 18-12-2023.pdf23 Dec 2023
Certificates of CA (Form 3)File: C A Certificate.pdf23 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 C A Certificate 20-21.pdf4 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 C A Certificate 21-22.pdf4 Feb 2023
Declaration about Commencement CertificateFile: Declaration CC.pdf11 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - 31-12-2022.pdf11 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - 31-12-2022.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Quality Assurance - 2020.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Quality Assurance - 2021.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Assurance - 2022.pdf11 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf11 Jan 2023
Certificates of CA (Form 3)File: C A Certificate 10-01-2023.pdf11 Jan 2023
Proforma of Agreement for saleFile: Agreement for Sale.pdf11 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 15-09-2022.pdf19 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 15-09-2022.pdf19 Sep 2022
Certificates of CA (Form 3)File: C A Certificate.pdf31 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certiciate 17-01-2022.pdf20 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 17-01-2022.pdf20 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: CC REVISED.pdf2 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 30-06-2021.pdf12 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 30-06-2021.pdf12 Jul 2021
Certificates of CA (Form 3)File: C A Certificate 30-07-2021.pdf12 Jul 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT C C-converted.pdf26 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 C A Certificate 19-20.pdf3 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 C A Certificate 18-19.pdf29 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 30-06-2020.pdf21 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 30-06-2020.pdf21 Sep 2020
Certificates of CA (Form 5)File: C A Certificate 30-06-2020.pdf21 Sep 2020
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate C-D.pdf2 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf17 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf17 Jul 2019
Certificates of CA (Form 3)File: C A Certificate.pdf17 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 26-09-2018.pdf26 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 26-09-2018.pdf26 Dec 2018
Certificates of CA (Form 3)File: C A Certificate 25-12-2018.pdf26 Dec 2018
Certificates of CA (Form 5)File: Form 5 C A Certificate.pdf26 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 28-05-2018 KCC.pdf14 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 28-05-2018 KCC.pdf14 Jun 2018
Certificates of CA (Form 3)File: C A Certificate 13-06-2018 KCC.pdf14 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 12-02-2018.pdf23 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 12-02-2018.pdf23 Feb 2018
Certificates of CA (Form 3)File: C A Certificate 21-02-2018.pdf23 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE - 09-10-2017.pdf17 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE - 09-10-2017.pdf17 Nov 2017
Certificates of CA (Form 3)File: C A Certificate - 28-10-2017.pdf17 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE - 09-10-2017.pdf12 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE - 09-10-2017.pdf12 Nov 2017
Certificates of CA (Form 3)File: C A Certificate - 28-10-2017.pdf12 Nov 2017
Layout approvalFile: Layout Plan (6).pdf29 Jul 2017
Building plan approvalFile: Layout Plan.pdf29 Jul 2017
PAN CardFile: PAN CARD.pdf29 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf29 Jul 2017
Details of encumbrancesFile: No Encumbrance Certificate.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan (6).pdf29 Jul 2017
Building Plan Approval (IOD)File: Layout Plan.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Revised Dev Permission.pdf29 Jul 2017
Declaration in FORM BFile: FORM B.pdf29 Jul 2017

How this compares with Palghar

87%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 48 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep APEKSHA COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WALIV3,200+ in Palghar

2 kmAPEKSHA COMPLEXCompleted 25Lapsed / revoked 9Other 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: KOTHARI CONSTRUCTION CO

KOTHARI CONSTRUCTION CO has 2 registrations on MahaRERA, including APEKSHA COMPLEX and APEKSHA SHOPPING CENTRE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if APEKSHA COMPLEX is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of APEKSHA COMPLEX?

The registered promoter entity is KOTHARI CONSTRUCTION CO, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in APEKSHA COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against APEKSHA COMPLEX?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for APEKSHA COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at APEKSHA COMPLEX?

The professionals named in the filing: Architect: SANJAY S NARANG S NARANG; Engineer: SANJAY S NARANG; Chartered Accountant: Ramesh Lukad; Chartered Accountant: R D LUKAD CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in APEKSHA COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About APEKSHA COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save APEKSHA COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.