Home / Browse projects / Mumbai Suburban, Maharashtra / ANUPAM VILLA CHSL

Registered No litigation declared Residential / Group Housing project

ANUPAM VILLA CHSL

By M E INFRAPROJECTS PVT LTD

RG-MH-12434 · RERA P51800011219 · Last updated on MahaRERA portal: 20 Aug 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 81 months
  • 7 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
9 of 11Construction stages donefurthest along: Internal walls, 98%
47 of 72Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 112 documents Report an error

ANUPAM VILLA CHSL is a Residential / Group Housing project by M E INFRAPROJECTS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011219 on 31 Aug 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 81 months from the original filing. 25 of the 72 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameANUPAM VILLA CHSL
  • TypeResidential / Group Housing
  • Location
    • Kale Marg Road
    • Kurla
    • Mumbai Suburban
    • 400070
  • Pincode400070
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800011219
  • ReraGenie IDRG-MH-12434

Builder

  • NameM E INFRAPROJECTS PVT LTD
  • Entity typeCompany
  • Managing DirectorPIYUSH PUKHRAJ MEHTA
  • Declared earlier projects1 →

Key dates

1 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed112 files

Current status

35%25 of 72 units booked
100.0%Work done, per cost certificate

Figures as on 20 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANUPAM VILLANA7764872

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

ANUPAM VILLA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure97%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed47

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots47
Closed/Covered47

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,320 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
ANUPAM VILLA CHSLKurlaMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI4138.4
Proposed, not sanctioned1,310 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMUMBAI
Estimated costRs 16.25 cr
Cost incurredRs 16.25 cr
Work done100.0%
BuildingWingEstimatedIncurred
ANUPAM VILLANARs 16.25 crRs 16.25 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHISH SOLANKI
ArchitectEASTERN ARCHITECTS
EngineerBHAVIN SHAH
EngineerM M ENTERPRISES
Chartered AccountantPraful H jain & Co
PartnerRole in project
M E INFRAPROJECTS PVT LTD-

Extensions applied for7

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800006101Dec 2019 → Dec 2020

Reason as filed by the promoterCHANGES IN CC DATES

EXT51800010237Dec 2019 → Dec 2021

Reason as filed by the promoterDue to Covid-19 Lockdown and shortage of Labour and Material Unavailability for Construction Work

EXT51800012061Dec 2019 → Sep 2022

Reason as filed by the promoter95% of the work is completed, only parking work is left, delay is mainly due to COVID restrictions

EXT51800012618Dec 2019 → Mar 2023

Reason as filed by the promoterRespected Sir, All the work has been completed except installation of parking systems.

EXT51800016585Dec 2019 → Dec 2024

Reason as filed by the promoterProject is completed, reason for extension is unsold inventory and o.c. process where certain approvals are awaited from mcgm like road handing over, tree cutting noc

EXT51800027344Dec 2019 → Dec 2025

Reason as filed by the promoterThis is to hereby state and affirm that the Project has been completed in all respects, including structural, civil, and service-related works, as per the approved plans and relevant building regulations. All members have been handed over fit-out possession of their respective units, and many have commenced interior works accordingly. However, the Occupancy Certificate (O.C.) is currently under process due to the following pending matters: 1. Road Setback Handover: The Road Setback area, as required by the competent authority, could not be handed over in time due to delays from the City Survey

EA03062621221Dec 2019 → Sep 2026

Reason as filed by the promoterThis is to hereby state and affirm that the Project has been completed in all respects, including structural, civil, and service-related works, as per the approved plans and relevant building regulations. All members have been handed over fit-out possession of their respective units, and many have commenced interior works accordingly. However, the Occupancy Certificate (O.C.) is currently under process due to the following pending matters: 1. Road Setback Handover: The Road Setback area, as required by the competent authority, could not be handed over in time due to delays from the City Survey

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Jul 2021

Documents filed112

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A.pdf20 Aug 2026
Withdrawal Update Form 1File: Architect form 1.pdf7 Aug 2026
Withdrawal Update Form 1File: Architect form 1.pdf7 Aug 2026
Withdrawal Update Form 1File: Architect form 1.pdf7 Aug 2026
Withdrawal Update Form 2File: Engineer form 2.pdf7 Aug 2026
Withdrawal Update Form 2File: Engineer form 2.pdf7 Aug 2026
Withdrawal Update Form 2File: Engineer form 2.pdf7 Aug 2026
Withdrawal Update Form 3File: CA form 3.pdf7 Aug 2026
Withdrawal Update Form 3File: CA form 3.pdf7 Aug 2026
Withdrawal Update Form 3File: CA form 3.pdf7 Aug 2026
Form 1File: Architect form 1.pdf29 May 2026
Form 2File: Engineer form 2.pdf29 May 2026
Form 3File: CA form 3.pdf29 May 2026
Disclosure of Sold and Booked InventoryFile: Inventory disclosure.pdf29 May 2026
Form 1File: form 1.pdf29 May 2026
Form 2File: form 2.pdf29 May 2026
Form 3File: form 3.pdf29 May 2026
Disclosure of Sold and Booked InventoryFile: Inventory disclosure.pdf29 May 2026
Form 1File: form 1.pdf29 May 2026
Form 2File: form 2.pdf29 May 2026
Form 3File: form 3.pdf29 May 2026
Disclosure of Sold and Booked InventoryFile: Inventory disclsoure.pdf29 May 2026
Certificates of CA (Form 3)File: form 3 03 25.pdf26 Jul 2025
Certificates of CA (Form 3)File: form 3 06 25.pdf26 Jul 2025
Disclosure of sold/ booked inventoryFile: Inventory disclosure.pdf26 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf25 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 march 25.pdf22 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 june 25.pdf22 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 march 25.pdf22 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 june 25.pdf22 Jul 2025
Other - TechnicalFile: PERT CHART.pdf29 May 2025
Certificates of CA (Form 3)File: FORM-3.pdf8 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 10-01-2024.PDF8 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 12-04-2024.PDF8 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 09-07-2024.PDF8 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 09-07-2024.PDF8 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 14-10-2024.PDF8 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 14-10-2024.PDF8 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 10-01-2025.PDF8 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: MEIPL - FORM 5 - FY 2020-21.pdf8 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: MEIPL - FORM 5 - FY 2021-22.pdf8 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: MEIPL - FORM 5 - FY 2023-24.pdf8 Apr 2025
Declaration in FORM BFile: FORM B - AFFIDAVIT.pdf25 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT-1.pdf25 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT-2.pdf25 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT-3.pdf25 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT-4.pdf25 Feb 2025
Certificates of CA (Form 3)File: FORM 3.pdf25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE-5.PDF25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE-4.PDF25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE-3.PDF25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE-2.PDF25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE-1.PDF25 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: FULL CC COMMENCEMENT CERTIFICATE 2022.pdf25 Feb 2025
Disclosure of sold/ booked inventoryFile: INFORMATION SOLD and UNSOLD INVENTORY.PDF25 Feb 2025
Other - TechnicalFile: MAHARERA_0001.pdf25 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 1 JAN TO MARCH 2024.pdf25 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 1 APRIL TO JUNE 2024.pdf25 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 1 JULY TO SEP 2024.pdf25 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 1 OCT TO DEC 2024.pdf25 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATION-1-min.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATION-2-min.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATION-3.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATION-4.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE-5.PDF28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE-4.PDF28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE-4.PDF28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE-3.PDF28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE-2.PDF28 Jan 2025
Disclosure of sold/ booked inventoryFile: INFORMATION SOLD and UNSOLD INVENTORY.PDF28 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD and UNSOLD_new.pdf1 Nov 2023
Declaration in FORM BFile: AFFIDAVIT FORM B (2).pdf28 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form_2A.pdf28 Oct 2023
Declaration in FORM BFile: FORMAT B.pdf27 Oct 2023
Declaration in FORM BFile: AFFIDAVIT FORM B.pdf27 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form_2A.pdf27 Oct 2023
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY-min.pdf27 Oct 2023
Declaration in FORM BFile: FORMAT B.pdf21 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 RERA.pdf21 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 RERA (2).pdf21 Oct 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Banganga Municipal SchoolDongarsi Road60CompletedDec 2008Dec 2008

How this compares with Mumbai Suburban

35%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 81 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANUPAM VILLA CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmANUPAM VILLA CHSLCompleted 92Lapsed / revoked 87Other 115Dot size: filed unitsN

Filed coordinates, straight-line distance. 294 registered projects within 2 km.

Builder: M E INFRAPROJECTS PVT LTD

M E INFRAPROJECTS PVT LTD has 1 registration on MahaRERA, including ANUPAM VILLA CHSL. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if ANUPAM VILLA CHSL is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANUPAM VILLA CHSL?

The registered promoter entity is M E INFRAPROJECTS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANUPAM VILLA CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ANUPAM VILLA CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANUPAM VILLA CHSL?

The professionals named in the filing: Architect: ASHISH SOLANKI; Architect: EASTERN ARCHITECTS; Engineer: BHAVIN SHAH; Engineer: M M ENTERPRISES; Chartered Accountant: Praful H jain & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANUPAM VILLA CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANUPAM VILLA CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANUPAM VILLA CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.