Home / Browse projects / Pune, Maharashtra / ANGELLE HILLS VERSION T- 9-12 FLOOR

Registration lapsed No litigation declared Residential / Group Housing project

ANGELLE HILLS VERSION T- 9-12 FLOOR

By BUTTEPATIL PROJECT PVT LTD

RG-MH-12982 · RERA P52100021873 · Last updated on MahaRERA portal: 10 Dec 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 14 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 20 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Aug 2025Possession promised14 months past this date
7 of 11Construction stages donefurthest along: Basement (if any), 0%
5 of 16Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 130 documents Report an error

ANGELLE HILLS VERSION T- 9-12 FLOOR is a Residential / Group Housing project by BUTTEPATIL PROJECT PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100021873 on 8 Aug 2019. Possession was promised by 31 Aug 2025 and is now 14 months past that date. The completion date has moved by 20 months from the original filing. 11 of the 16 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameANGELLE HILLS VERSION T- 9-12 FLOOR
  • TypeResidential / Group Housing
  • Location
    • BAVDHAN KHURD
    • BAVDHAN PUNE
    • Bavdhan Kh.
    • Haveli
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100021873
  • ReraGenie IDRG-MH-12982

Builder

  • NameBUTTEPATIL PROJECT PVT LTD
  • Entity typeCompany
  • Managing DirectorsAJIT ANANDRAO BUTTEPATIL, ROHINI AJIT BUTTEPATIL, VIRAJ AJIT BUTTEPATIL, SURAJ AJIT BUTTEPATIL
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

14 months past promisethis monthRegisteredAug 2019First promiseDec 2023Revised toAug 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Aug 2019
  • Promised completion31 Aug 2025
  • Revised completionRevised to 31 Aug 2025 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed130 files

Current status

69%11 of 16 units booked
78.4%Work done, per cost certificate

Figures as on 10 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANGELLE HILLS VERSION T -9-12 FLOORNA4416016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

ANGELLE HILLS VERSION T -9-12 FLOOR: 64% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered32

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area783 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Jun 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI2204.27
Proposed, not sanctioned2,204 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDECCAN GYMKHANA PUNE
Estimated costRs 12.42 cr
Cost incurredRs 9.74 cr
Work done78.43%
BuildingWingEstimatedIncurred
ANGELLE HILLS VERSION T -9-12 FLOORNARs 12.42 crRs 9.74 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNilesh Saswade
EngineerDilip Khot
Chartered AccountantSAC CO & LLP
Chartered AccountantPriyanka Chordiya
PartnerRole in project
BUTTEPATIL PROJECT PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018978Dec 2023 → Dec 2024

Reason as filed by the promoterWe received the additional revised sanction as on 04.05.2023 in which only the balcony area is increased and so revision in the plan was done.As per the definition of Carpet Area,balcony is excluded and so we are not making any correction application but we need to build the additional construction and so the revision.

EXT52100025782Dec 2023 → Aug 2025

Reason as filed by the promoter1) The construction of the project is complete. We applied for the part completion certificate with concern department, the copy of the application along with major departments NOC attached herewith for your ready reference. Only the site visit and completion certificate are pending from the concern department. To get the completion certificate we are applying for extension. 2) More than one rera registration is taken in a single building Construction. To get the Full Completion certificate of the project we require to complete the full building which is almost completed only the last floor wo

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12602996Shrikant NavleBUTTEPATIL PROJECT PVT LTD20/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed130

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 130 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf10 Dec 2025
Withdrawal Update Form 2File: Dilip V Khot Annexure B form 2.pdf10 Dec 2025
Withdrawal Update Form 3File: Form 3 Angelina 9-12 30092025 sign.pdf10 Dec 2025
Form 2A (FY 2024-2025)File: _Form 2A Angelle Hills Version T 1-9 Floor_24_25_compressed.pdf10 Dec 2025
Form 5 (FY 2024-2025)File: Form 5_ Angelle Hills Versino T 9 -12_FY 2024-2025 sign_compressed.pdf10 Dec 2025
Withdrawal Update Form 1File: Form 1Angella Hills Version T 9-12 floorr.pdf9 Dec 2025
Withdrawal Update Form 2File: FORM 2 Engineer certificate 30062025 sign.pdf9 Dec 2025
Withdrawal Update Form 3File: Form 3 Angelina 9-12 30062025 sign_compressed.pdf9 Dec 2025
Withdrawal Update Form 1File: FORM 1 Angella Hills Version T 9 12 Architect Certificate 31032025.pdf20 Jun 2025
Withdrawal Update Form 2File: FORM 2 Engineer certificate 31032025.pdf20 Jun 2025
Withdrawal Update Form 3File: form 3 Angelle Hills Version T 9 to 12 Floor 31122023 both signed_compressed.pdf20 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Angella Hills Version T 9-12 Architect Certificate 31122024.pdf10 May 2025
Certificates of CA (Form 3)File: Form 3 Angelina 9 12 31032025 sign_compressed.pdf10 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory sign.pdf10 May 2025
Declaration in FORM BFile: 3 Declaration in FORM B.pdf15 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Buttepatil 9_12 31122024.pdf15 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer certificate 31122024.pdf7 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory 9 12.pdf7 Feb 2025
Declaration in FORM BFile: Form B.pdf3 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Angella Hills Version T 9_12 Architect Certificate 31122024_Promoter sign attached.3 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Angells Hills Version T Architect Certificate 31122024.pdf1 Feb 2025
Certificates of CA (Form 3)File: form 3 Angells Hills Version T 31-12-2024 Sign copy.pdf1 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer certificate 31122024.pdf1 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory Angelina 1-8.pdf1 Feb 2025
Details of encumbrances concerned to FinanceFile: Details of No encumbrances concerned to Legal sign.pdf25 Dec 2024
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance sign.pdf25 Dec 2024
CERSAI detailsFile: No cersai letter Sign with Bank NOC.pdf25 Dec 2024
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance sign.pdf25 Dec 2024
Details of encumbrances concerned to LegalFile: Details of No encumbrances concerned to Legal sign.pdf25 Dec 2024
Building plan approvalFile: SANCTION PLAN 1 OF 8_compressed.pdf19 Dec 2024
Building plan approvalFile: Plan 5_compressed.pdf19 Dec 2024
Building Plan Approval (IOD)File: SANCTION PLAN 1 OF 8_compressed.pdf19 Dec 2024
Building Plan Approval (IOD)File: Plan 5_compressed.pdf19 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Angelle Hills Version T 1-9 Floor.pdf18 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Angelle Hills Version T 1-9 Floor.pdf18 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 ANGELLE HILLS VERSION 9-12 FLOOR sign.pdf14 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31032024.pdf12 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30062024.pdf12 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30092024.pdf12 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure Of sold Unsold 31032024.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold 30062024.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure sold Unsold 30092024.pdf9 Nov 2024
Certificates of CA (Form 3)File: form 3 Angelle Hills Version T 9-12 Floor 31-03-2024_compressed.pdf8 Nov 2024
Certificates of CA (Form 3)File: form 3 Angelle Hills Version T 9-12 Floor 30-06-2024_compressed.pdf8 Nov 2024
Certificates of CA (Form 3)File: form 3 Angelle Hills Version T 9-12 Floor 30-09-2024_compressed.pdf8 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032024.pdf8 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30092024.pdf8 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30062024.pdf8 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30062023 9 TO 12.pdf26 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30092023 9 TO 12.pdf26 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 31122023 9 TO 12.pdf26 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer certificate 30062023 both signed.pdf9 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer certificate 30092023 both signed.pdf9 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer certificate 31122023 both signed.pdf9 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold unsold 30062023.pdf9 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold unsold 30092023.pdf9 Feb 2024
Disclosure of sold/ booked inventoryFile: sold unsold dec 23.pdf9 Feb 2024
Certificates of CA (Form 3)File: form 3 Angelle Hills Version T 9 to 12 Floor 30062023_compressed.pdf9 Feb 2024
Certificates of CA (Form 3)File: form 3 Angelle Hills Version T 9 to 12 Floor 30092023_compressed.pdf9 Feb 2024
Certificates of CA (Form 3)File: form 3 Angelle Hills Version T 9 to 12 Floor 31122023 both signed_compressed.pdf9 Feb 2024
Details of encumbrancesFile: Details of encumbrances concerned to Finance and Legal Merged.pdf31 Jan 2024
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance and Legal Merged.pdf31 Jan 2024
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance and Legal Merged.pdf31 Jan 2024
Declaration about Commencement CertificateFile: Format D Commencement certificate declaration.pdf31 Jan 2024
Declaration in FORM BFile: Form B_Angella 9 to 12.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Angella 9 to12 31032022.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Angella 9 to 12 30062022.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Angella 9 to 12 30092022.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Angella 9 to 12 31122022.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Angella 9 to12 31032023.pdf31 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate organisations_ajit and viraj _merged.pdf31 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 Angelle Hills Version T 9 TO 12 Floor FY 21 22 BOTH SIGNED.pdf31 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 Angelle Hills Version T 9 TO 12 Floor FY 22 23 BOTH SIGNED.pdf31 Jan 2024
Proforma of Allotment letterFile: Draft Allotment Letter.pdf31 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A seperate Bank Account.pdf31 Jan 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.pdf31 Jan 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement.pdf31 Jan 2024
Layout approvalFile: SANCTION PLAN 1 OF 8_compressed.pdf25 Jan 2024
Building plan approvalFile: SANCTION PLAN 2 OF 8_compressed.pdf25 Jan 2024
Building plan approvalFile: SANCTION PLAN 3 OF 8_compressed.pdf25 Jan 2024

How this compares with Pune

69%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 20 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANGELLE HILLS VERSION T- 9-12 FLOOR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BAVDHAN PUNE13,700+ in Pune

2 kmANGELLE HILLS VERSION T-Completed 116Lapsed / revoked 116Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: BUTTEPATIL PROJECT PVT LTD

BUTTEPATIL PROJECT PVT LTD has 2 registrations on MahaRERA, including ANGELLE HILLS VERSION T and ANGELLE HILLS VERSION T- 9-12 FLOOR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that ANGELLE HILLS VERSION T- 9-12 FLOOR shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ANGELLE HILLS VERSION T- 9-12 FLOOR is delayed beyond 31 Aug 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANGELLE HILLS VERSION T- 9-12 FLOOR?

The registered promoter entity is BUTTEPATIL PROJECT PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANGELLE HILLS VERSION T- 9-12 FLOOR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ANGELLE HILLS VERSION T- 9-12 FLOOR?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ANGELLE HILLS VERSION T- 9-12 FLOOR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANGELLE HILLS VERSION T- 9-12 FLOOR?

The professionals named in the filing: Architect: Nilesh Saswade; Engineer: Dilip Khot; Chartered Accountant: SAC CO & LLP; Chartered Accountant: Priyanka Chordiya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANGELLE HILLS VERSION T- 9-12 FLOOR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANGELLE HILLS VERSION T- 9-12 FLOOR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANGELLE HILLS VERSION T- 9-12 FLOOR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.