Home / Browse projects / Pune, Maharashtra / ALFA PREMIO PHASE 1

Completed No litigation declared Residential / Group Housing project

ALFA PREMIO PHASE 1

By ARK PREM CONSTRUCTIONS

RG-MH-10027 · RERA P52100000855 · Last updated on MahaRERA portal: 8 Jan 2025

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 87 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Internal walls, 95%
2Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

ALFA PREMIO PHASE 1 is a Residential / Group Housing project by ARK PREM CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100000855 on 23 Jul 2017. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 87 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameALFA PREMIO PHASE 1
  • TypeResidential / Group Housing
  • Location
    • KHALSA DAIRY
    • VIMAN NAGAR
    • VIMANNAGAR
    • Haveli
    • Pune
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000855
  • ReraGenie IDRG-MH-10027

Builder

  • NameARK PREM CONSTRUCTIONS
  • Entity typePartnership
  • PartnersAVINASH RAMESH KHATANHAR, NITIN PREM BELLARA, RITESH PREM BELLARA
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredJul 2017First promiseSep 2018Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Sep 2018)
  • Buildings1 building record
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PHASE 1NA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

PHASE 1: 96% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed63

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots63
Closed/Covered63

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,563 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Padmavati Prem Realtors LLPVIMANNAGARPune

Approvals and building plan

Permissible FSI4839.0
Proposed, not sanctioned2,563 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKALYANI NAGAR PUNE

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
ARK PREM CONSTRUCTIONS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019303Sep 2018 → Dec 2025

Reason as filed by the promoterWe wish to inform that all residential flats in the project have been successfully sold until the approved OC stages. Furthermore, all units have been offered possession and a significant majority of unit owners have taken possession of their respective flats, thus we wish to apply for an extension on the basis of the possession letter

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000137159ARK PREM CONSTRUCTION THROGH PARTNER AVINASH KHATANHAR -PRAVEENKUMAR PRADEEPKUMAR MENON31/05/2022
CC005000000147174ARK PREM CONSTRUCTION THROGH PARTNER AVINASH KHATANHAR -PREVEENKUMAR PRADEEPKUMAR MENON31/05/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Mar 2024

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Alfa Premio Phase 1 as on December 2024.pdf8 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Alfa Premio Phase 1 as on December 2024.pdf8 Jan 2025
Disclosure of sold/ booked inventoryFile: Circular 29 - Alfa Premio Phase 1 as on December 2024.pdf8 Jan 2025
Certificates of CA (Form 3)File: Form 3 - Alfa Premio Phase 1 as on June 2024.pdf7 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Alfa Premio Phase 1 as on June 2024.pdf30 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Alfa Premio Phase 1 as on June 2024.pdf24 Jul 2024
Building plan approvalFile: Page 1.pdf19 Jul 2024
Building plan approvalFile: Page 2.pdf19 Jul 2024
Building plan approvalFile: Page 3.pdf19 Jul 2024
Building plan approvalFile: Page 4.pdf19 Jul 2024
Building plan approvalFile: Page 5.pdf19 Jul 2024
Building Plan Approval (IOD)File: Page 1.pdf19 Jul 2024
Building Plan Approval (IOD)File: Page 2.pdf19 Jul 2024
Building Plan Approval (IOD)File: Page 3.pdf19 Jul 2024
Building Plan Approval (IOD)File: Page 4.pdf19 Jul 2024
Building Plan Approval (IOD)File: Page 5.pdf19 Jul 2024
Certificates of CA (Form 3)File: Form 3 - Alfa Premio Phase 1 as on June 2024 (1).pdf19 Jul 2024
Proforma of Agreement for saleFile: Alfa AFS.pdf21 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect certificate Alfa - Copy.pdf14 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Alfa Premio Phase I as on Dec 2023.pdf14 Mar 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf14 Mar 2024
Certificates of CA (Form 3)File: Form 3 Alfa Premio Phase I as on 31-12-2023 Final.pdf14 Mar 2024
Certificates of CA (Form 3)File: 2 Certificates of CA (Form 3) (1).pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 Alfa Premio Phase I 2017-18.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Alfa Premio Phase I 2018-19.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Alfa Premio Phase I 2019-20.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Alfa Premio Phase I 2020-21.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Alfa Premio Phase I 2021-22.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Alfa Premio Phase I 2022-23.pdf14 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part 1 Completion Certificate 21 Sep 2018.pdf14 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part 2 Completion Certificate.pdf14 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part 3 Completion Certificate 10 May 2021.pdf14 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect certificate Alfa.pdf13 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf13 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: 1 Building Plan Approval (IOD) (1).pdf12 Mar 2024
Declaration about Commencement CertificateFile: Format D.pdf12 Mar 2024
Declaration in FORM BFile: Form B Affidavit.pdf12 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - 2019-20.pdf12 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - 2020-21.pdf12 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 2021-22.pdf12 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 2022-23.pdf12 Mar 2024
CERSAI detailsFile: Cersai Declaration.pdf12 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf12 Mar 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4_Premio.pdf22 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC Premio1mb.pdf30 Dec 2019
Architect’s Certificate on Completion of Project (Form 4)File: CC Premio1mb.pdf30 Dec 2019
Declaration in FORM BFile: Form B Alfa Premo.pdf20 Jul 2017
Building plan approvalFile: cc_2016.pdf19 Jul 2017
Layout approvalFile: Plan_pdf.pdf19 Jul 2017
PAN CardFile: Pan Card.pdf19 Jul 2017
Copy of the legal title reportFile: Search Report.pdf19 Jul 2017
Details of encumbrancesFile: Self Decleration.pdf19 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan_pdf.pdf19 Jul 2017
Building Plan Approval (IOD)File: cc_2016.pdf19 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf19 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_compressed.pdf19 Jul 2017
Certificates of CA (Form 3)File: C A Certificate.pdf19 Jul 2017
Proforma of Allotment letterFile: Pemio Agrremant And Agtallot.pdf19 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 87 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ALFA PREMIO PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIMAN NAGAR13,700+ in Pune

2 kmALFA PREMIO PHASE 1Completed 32Lapsed / revoked 14Other 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 78 registered projects within 2 km.

Builder: ARK PREM CONSTRUCTIONS

ARK PREM CONSTRUCTIONS has 3 registrations on MahaRERA, including ALFA ELEGANCE and Viman Platinum. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ALFA PREMIO PHASE 1 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ALFA PREMIO PHASE 1?

The registered promoter entity is ARK PREM CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ALFA PREMIO PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ALFA PREMIO PHASE 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ALFA PREMIO PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in ALFA PREMIO PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ALFA PREMIO PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ALFA PREMIO PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.