Home / Browse projects / Mumbai Suburban, Maharashtra / ALAG MARINA

Registered No litigation declared Residential / Group Housing project

ALAG MARINA

By ALAG PROPERTY CONSTRUCTIONS PVT. LTD.

RG-MH-21026 · RERA P51800003162 · Last updated on MahaRERA portal: 1 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 66 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 66 months from the original
6 of 11Construction stages donefurthest along: Slabs of Super Structure, 95%
24 of 48Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

ALAG MARINA is a Residential / Group Housing project by ALAG PROPERTY CONSTRUCTIONS PVT. LTD. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003162 on 4 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 66 months from the original filing. 24 of the 48 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameALAG MARINA
  • TypeResidential / Group Housing
  • Location
    • Madan Mohal Malaviya Road
    • St. Pius Church Mulund West
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003162
  • ReraGenie IDRG-MH-21026

Builder

  • NameALAG PROPERTY CONSTRUCTIONS PVT. LTD.
  • Entity typeCompany
  • Other registrations4 more →
  • Completed2 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017First promiseJun 2021Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed56 files

Current status

50%24 of 48 units booked
94.3%Work done, per cost certificate

Figures as on 1 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ALAG MARINANA212148048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

ALAG MARINA: 97% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 1 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed118

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots118
Closed/Covered118

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,558 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Jul 2026

Approvals and building plan

Permissible FSI5046.49
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchG V SCHEME ROAD NO 2 MULUND EAST
Estimated costRs 19.00 cr
Cost incurredRs 17.91 cr
Work done94.28%
BuildingWingEstimatedIncurred
ALAG MARINANARs 19.00 crRs 17.91 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectR P ASUNDARIA
ArchitectFOURTH DIMENSION
EngineerBHAVIN C SHAH
EngineerBHAGWAN INGOLE
Chartered AccountantMasarani & co
Chartered AccountantVINOD DEVNANI
Chartered AccountantNEHALI DOSHI
PartnerRole in project
ALAG PROPERTY CONSTRUCTIONS PVT. LTD.-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800010514Jun 2021 → Jun 2022

Reason as filed by the promoterTHE PROJECT HAS BEEN DELAYED DUE TO UNAVAILABILITY OF MATERIAL, LABOUR DUE TO COVID-19 PANDEMIC INDUCED LOCKDOWN.

EA15072621762Jun 2021 → Dec 2026

Reason as filed by the promoterSubject: Submission of Technical Reasons for Delay in Completion of the Project name "ALAG MARINA" located at on land bearing CTS No. 551/5, Madan Mohan Malviya Road, Village Mulund, Taluka Kurla, Mumbai Suburban District, Maha RERA Reg. No. P51800003162, Respected Sir, We, Mr. Pratik Mukesh Somaiya, are the promoters of the real estate project known as "ALAG MARINA" located at on land bearing CTS No. 551/5, Madan Mohan Malviya Road, Village Mulund, Taluka Kurla, Mumbai Suburban District, Maha RERA Reg. No. P51800003162, Certain design modifications and compliance requirements necessitated rev

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf1 Aug 2026
Withdrawal Update Form 1File: Declaration letter.pdf1 Aug 2026
Withdrawal Update Form 2File: Form 2.pdf1 Aug 2026
Withdrawal Update Form 2File: Declaration letter.pdf1 Aug 2026
Withdrawal Update Form 3File: Form 3.pdf1 Aug 2026
Withdrawal Update Form 3File: Declaration letter.pdf1 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf1 Aug 2026
Withdrawal Update Form 1File: Form 1.pdf31 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf31 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf31 Jul 2026
Withdrawal Update Form 1File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 1File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 1File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 1File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 2File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 2File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 2File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 2File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 3File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 3File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 3File: Declaration letter.pdf30 Jul 2026
Withdrawal Update Form 3File: Declaration letter.pdf30 Jul 2026
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory-31032021.pdf20 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_Marina_19-20.pdf19 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: Full CC_signed.pdf17 Jul 2021
Declaration about Commencement CertificateFile: Form D for Registered Project Declaration - Marina.pdf17 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (Architect) 31-03-2020 Marina.pdf10 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (Architect) 31-03-2021 Marina_compressed.pdf10 Jul 2021
Certificates of CA (Form 3)File: 5-31032020 Form 3_compressed_compressed.pdf10 Jul 2021
Certificates of CA (Form 3)File: FORM 3 SIGNED.pdf10 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Alag Marina - 2018-19 Form 5.pdf6 Mar 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A (Engineer)-300919.pdf27 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A (Engineer)-311219.pdf27 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4-30092019.pdf18 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf14 Dec 2019
Certificates of CA (Form 3)File: Form 3.pdf12 Dec 2019
Annual Audit Report of Statutory CA (Form 5)File: Alag Marina Form 5.pdf14 Sep 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society registration_reduce.pdf15 Jul 2019
Status of ConveyanceFile: Conveyance Deed 1.pdf24 Jun 2019
Status of ConveyanceFile: Conveyance Deed 2.pdf24 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3_Form 2_10042019_Less than 1 mb.pdf20 Jun 2019
Certificates of CA (Form 3)File: 3_Form 3_29042019_Less than 1 mb.pdf20 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4-Form 1_10042019.pdf19 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineers Certificate.pdf28 Jul 2017
Certificates of CA (Form 3)File: Form 3 - Chartered Accountant Certificate.pdf28 Jul 2017
Proforma of Allotment letterFile: SALE AGREEMENT AND ALLOTMENT LETTER.pdf28 Jul 2017
Details of encumbrancesFile: Non Encumbrance Certificate.pdf27 Jul 2017
Declaration in FORM BFile: Form B.pdf27 Jul 2017
Building plan approvalFile: IOD Conditions_compressed.pdf25 Jul 2017
Layout approvalFile: MARINA-SHEET-1.pdf25 Jul 2017
PAN CardFile: APCPL_Pan Card_Color.pdf25 Jul 2017
Copy of the legal title reportFile: Title Clearance Certificate_compressed.pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: MARINA-SHEET-1.pdf25 Jul 2017
Building Plan Approval (IOD)File: IOD Conditions_compressed.pdf25 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Plinth CC.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf25 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise1 delivered late
ProjectLocationRegisteredStatusPromisedDelivered
ALAG STELLAP51800018925MULUND EAST, Mumbai SuburbanDec 2018CompletedJun 2022Registered original: Jun 2021Late, Jul 2022
ALAG BELLAP51800006661Kurla, Mumbai SuburbanAug 2017CompletedJun 2018Registered original: Dec 2017May 2018
ALAG AIR MEGHANADEVIDAYAL NAGAR, MULUND WEST, MUMBAI 400080-CompletedApr 2017Apr 2017
ALAG AURAB.P.CROSS ROAD, MULUND WEST, MUMBAI 400080-CompletedJan 2015Jan 2015

How this compares with Mumbai Suburban

50%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 66 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ALAG MARINA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near St. Pius Church Mulund West6,700+ in Mumbai Suburban

2 kmALAG MARINACompleted 125Lapsed / revoked 100Other 160Dot size: filed unitsN

Filed coordinates, straight-line distance. 385 registered projects within 2 km.

Builder: ALAG PROPERTY CONSTRUCTIONS PVT. LTD.

ALAG PROPERTY CONSTRUCTIONS PVT. LTD. has 5 registrations on MahaRERA, including ALAG MARINA and ALAG BELLA. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if ALAG MARINA is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ALAG MARINA?

The registered promoter entity is ALAG PROPERTY CONSTRUCTIONS PVT. LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ALAG MARINA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ALAG MARINA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ALAG MARINA?

The professionals named in the filing: Architect: R P ASUNDARIA; Architect: FOURTH DIMENSION; Engineer: BHAVIN C SHAH; Engineer: BHAGWAN INGOLE; Chartered Accountant: Masarani & co; Chartered Accountant: VINOD DEVNANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ALAG MARINA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ALAG MARINA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ALAG MARINA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.