ALAG PROPERTY CONSTRUCTIONS PVT. LTD. has 5 registrations in this build, including ALAG MARINA and ALAG BELLA. Its filings disclose 4 earlier MahaRERA projects: 3 of 4 past projects completed on time.

5Registrations in this build
4Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
ALAG MARINAMumbai Suburban, Maharashtra4850%Registration lapsed
ALAG BELLAMumbai Suburban, Maharashtra--Completed
ALAG STELLAMumbai Suburban, Maharashtra--Completed
ALAG CAPITALMumbai Suburban, Maharashtra--Registered
ALAG ENDEAVOURMumbai Suburban, Maharashtra--Registration lapsed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
ALAG AURA
3 Jan 20153 Jan 2015On time
ALAG AIR MEGHANA
11 Apr 201711 Apr 2017On time
ALAG BELLA
P51800006661
30 Jun 201830 May 2018On time
ALAG STELLA
P51800018925
30 Jun 202225 Jul 2022+1 months

Frequently asked questions

How do I verify ALAG PROPERTY CONSTRUCTIONS PVT. LTD. as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with ALAG PROPERTY CONSTRUCTIONS PVT. LTD.?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.