Home / Browse projects / Pune, Maharashtra / ACE ATMOSPHERE PHASE I

Registered No litigation declared Residential / Group Housing project

ACE ATMOSPHERE PHASE I

By JHAMTANI REALTY PRIVATE LIMITED

RG-MH-34842 · RERA P52100051778 · Last updated on MahaRERA portal: 22 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 80.00 crore secured on the land, in favour of TATA CAPITAL HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2028Possession promisedmoved 12 months from the original
12 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 36%
34 of 340Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 215 documents Report an error

ACE ATMOSPHERE PHASE I is a Residential / Group Housing project by JHAMTANI REALTY PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100051778 on 3 Jul 2023. Possession is promised by 29 Sep 2028. The completion date has moved by 12 months from the original filing. 306 of the 340 units on this registration are recorded sold or booked, and 12 of 33 construction stages are filed complete.

At a glance

Project

  • NameACE ATMOSPHERE PHASE I
  • TypeResidential / Group Housing
  • Location
    • 60/1
    • 60/3 to 60/6
    • 60/8 to 60/12
    • 60/13
    • 60/15 to 60/19
    • 61/2/1(P)
    • Ravet
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051778
  • ReraGenie IDRG-MH-34842

Builder

  • NameJHAMTANI REALTY PRIVATE LIMITED
  • Entity typeCompany
  • CINU70200PN2018PTC176558
  • GSTIN27AAECJ2550P1Z7
  • DirectorsANUP PARMANAND JHAMTANI, PARMANAND MELHUMAL JHAMTANI, ANUP PARMANAND JHAMTANI, DAYAL SHYAMLAL JESWANI, ANUP PARMANAND JHAMTANI, DAYAL SHYAMLAL JESWANI, ANUP PARMANAND JHAMTANI, DAYAL SHYAMLAL JESWANI, ANUP PARMANAND JHAMTANI, DAYAL SHYAMLAL JESWANI, ANUP PARMANAND JHAMTANI, DAYAL SHYAMLAL JESWANI
  • DirectorDAYAL SHYAMLAL JESWANI
  • Other registrations12 more →
  • Completed5 of 13
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2023First promiseSep 2027Revised toSep 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jul 2023
  • Promised completion29 Sep 2028
  • Revised completionRevised to 29 Sep 2028 (originally 30 Sep 2027)
  • Buildings3 building records
  • Documents filed215 files

Current status

90%306 of 340 units booked
40.8%Work done, per cost certificate

Figures as on 22 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA33271220122
Building BNA332798098
Building CNA33271191120

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 22 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 36%.

Building A42%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure36%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises1%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.12%
Building B42%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure33%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises1%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks14%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.12%
Building C42%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure33%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks14%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.12%

Progress on shared amenities15

As on 22 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed918

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots918
Closed/Covered918
BuildingClosed/CoveredTotal
Building A314314
Building B314314
Building C290290

Land and ownership4

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area6,801 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared present
Charge in favour ofTATA CAPITAL HOUSING FINANCE LIMITED
Secured amountRs 80.00 crore
CERSAI search filedYes
Declared on16 Jul 2025
LandownerVillageDistrict
ANUP PARMANAND JHAMTANIPimpri Chinchawad (M Corp.)Pune
Aashee DevelopersPimpri Chinchawad (M Corp.)Pune
Pandharinath Vitthal JambhalkarPimpri Chinchawad (M Corp.)Pune
Gauribai Devaramji ChaudhariPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI55378.57
Proposed, not sanctioned12,931 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSurvey No 207/2/1/4A/1, Kaspate Wasti, Fortune Business Center, Pune, Maharashtra 411057
Estimated costRs 194.93 cr
Cost incurredRs 79.55 cr
Work done40.81%
BuildingWingEstimatedIncurred
Building ANARs 177.46 crRs 71.05 cr
-NARs 17.47 crRs 8.49 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVKa Architecture
EngineerBhausaheb Jangle
EngineerPRANAV SHANTARAM PATIL
Chartered AccountantRavi Talreja and Associates
PartnerRole in project
JHAMTANI REALTY PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017784Sep 2027 → Sep 2028

Reason as filed by the promoterAddition of new land, i.e., Survey No. 60/13, accordingly changes in the layout plan, sanction and addition of units.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 29 Sep 2028

Documents filed215

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 215 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Ace Atmosphere Form-1.pdf22 Apr 2026
Withdrawal Update Form 2File: Ace Atmosphere Phase-1 Form-2.pdf22 Apr 2026
Withdrawal Update Form 3File: Ace Atmosphere Form-3 Q4 25-26.pdf22 Apr 2026
Withdrawal Update Form 1File: Ace Atmosphere Form 1 Q3 25-26.pdf20 Jan 2026
Withdrawal Update Form 2File: Ace Atmosphere Form 2 Q3 25-26.pdf20 Jan 2026
Withdrawal Update Form 3File: ACE ATMOSPHERE FORM 3 Q3.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: ACE ATMOSPHERE FORM5 2024-25.pdf19 Jan 2026
Withdrawal Update Form 1File: form 1 ace atmosphere..pdf20 Oct 2025
Withdrawal Update Form 2File: Ace Atmosphere.pdf20 Oct 2025
Withdrawal Update Form 3File: ACE ATMOSPHERE FORM 3 Q2.pdf20 Oct 2025
Withdrawal Update Form 1File: Ace Atmosphere Form 1.pdf22 Jul 2025
Withdrawal Update Form 2File: Ace Atmosphere Phase I.pdf22 Jul 2025
Withdrawal Update Form 3File: Ace Atmosphere Phase 1 Form 3.pdf22 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ace Atmsophere.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ace Atmosphere Phase 1 Form 3 New.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ace Atmosphere Phase I.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: 6) ACE ATMOSPHERE PHASE I.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ACE ATMOSPHERE PHASE 1 FORM 3 Q3 2425 FINAL.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ace Atmosphere I.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ace Atmosphere I.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Ace Atmosphere Phase I.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ACE ATMOSPHERE PHASE I.pdf17 Jan 2025
Building plan approvalFile: 1.pdf14 Jan 2025
Building plan approvalFile: 2.pdf14 Jan 2025
Building plan approvalFile: 3.pdf14 Jan 2025
Building plan approvalFile: 4.pdf14 Jan 2025
Building plan approvalFile: 5.pdf14 Jan 2025
Building plan approvalFile: 6.pdf14 Jan 2025
Building plan approvalFile: 7.pdf14 Jan 2025
Building plan approvalFile: 8.pdf14 Jan 2025
Building plan approvalFile: 9.pdf14 Jan 2025
Building plan approvalFile: 10.pdf14 Jan 2025
Building plan approvalFile: 11.pdf14 Jan 2025
Building plan approvalFile: 12.pdf14 Jan 2025
Building plan approvalFile: 13.pdf14 Jan 2025
Building plan approvalFile: 14.pdf14 Jan 2025
Building plan approvalFile: 15.pdf14 Jan 2025
Building plan approvalFile: 16.pdf14 Jan 2025
Building plan approvalFile: 17.pdf14 Jan 2025
Building plan approvalFile: 18.pdf14 Jan 2025
Building plan approvalFile: 19.pdf14 Jan 2025
Building plan approvalFile: 20.pdf14 Jan 2025
Building plan approvalFile: 21.pdf14 Jan 2025
Building plan approvalFile: 22.pdf14 Jan 2025
Building plan approvalFile: 23.pdf14 Jan 2025
Building plan approvalFile: 24.pdf14 Jan 2025
Building plan approvalFile: 25.pdf14 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 14.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 10.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 15.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 16.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 17.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 18.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 19.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 20.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 21.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 22.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 23.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 24.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 25.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 13.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 12.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 11.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 9.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 8.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 7.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 6.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 5.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf14 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf14 Jan 2025
Layout approvalFile: 01.pdf13 Jan 2025
Layout approvalFile: Revised 1.pdf13 Jan 2025
Copy of Layout Approval (in case of layout)File: Revised 1.pdf13 Jan 2025
Copy of Layout Approval (in case of layout)File: 01.pdf13 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ACE ATMOSPHERE FORM 5 2023-24.pdf3 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ACE ATMOSPHERE FORM 5 2023-24.pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ACE ATMOSPHERE PHASE I WING- A B C (2).pdf17 Oct 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
ACE AURUM III TOWER 01SURVEY NO 45 HISSA NO 1 OF 1 RAVET28CompletedDec 2024Apr 2024

How this compares with Pune

90%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ACE ATMOSPHERE PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ravet13,700+ in Pune

2 kmACE ATMOSPHERE PHASE ICompleted 96Lapsed / revoked 51Other 123Dot size: filed unitsN

Filed coordinates, straight-line distance. 270 registered projects within 2 km.

Builder: JHAMTANI REALTY PRIVATE LIMITED

JHAMTANI REALTY PRIVATE LIMITED has 13 registrations on MahaRERA, including ACE AURUM III TOWER 04 and ACE AURUM III TOWER 05. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ACE ATMOSPHERE PHASE I is delayed beyond 29 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ACE ATMOSPHERE PHASE I?

The registered promoter entity is JHAMTANI REALTY PRIVATE LIMITED, a company as per the filing. Its CIN U70200PN2018PTC176558 and GSTIN 27AAECJ2550P1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ACE ATMOSPHERE PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ACE ATMOSPHERE PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ACE ATMOSPHERE PHASE I?

The professionals named in the filing: Architect: VKa Architecture; Engineer: Bhausaheb Jangle; Engineer: PRANAV SHANTARAM PATIL; Chartered Accountant: Ravi Talreja and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ACE ATMOSPHERE PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ACE ATMOSPHERE PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ACE ATMOSPHERE PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.