ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai City, Maharashtra / Aarush

Registration lapsed No litigation declared Others project

Aarush

By Konark Enterprises

RG-MH-71941 · RERA P51900033696 · Last updated on MahaRERA portal: 10 Mar 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 95%
23 of 35Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 124 documents Report an error

Aarush is a Others project by Konark Enterprises in Mumbai City, Maharashtra, registered with MahaRERA as P51900033696 on 2 Mar 2022. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 9 months from the original filing. 12 of the 35 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameAarush
  • TypeOthers
  • Location
    • Rambhau Bhogle Marg
    • Mazgaon
    • Mumbai City
    • 400033
  • Pincode400033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900033696
  • ReraGenie IDRG-MH-71941

Builder

  • NameKonark Enterprises
  • Entity typeOthers
  • ProprietorKiran Patkar Narendra Patkar
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

13 months past promisethis monthRegisteredMar 2022First promiseDec 2024Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Mar 2022
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed124 files

Current status

34%12 of 35 units booked
97.9%Work done, per cost certificate

Figures as on 10 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AarushNA212132335

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

Aarush: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 10 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered12

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area273 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Aug 2025

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI1252.44
Proposed, not sanctioned1,111 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKonkan Nagar CHS Ltd P N Kotnis Marg Opp Fire Brigade Mahim West Mumbai 400016
Estimated costRs 8.20 cr
Cost incurredRs 8.03 cr
Work done97.89%
BuildingWingEstimatedIncurred
AarushNARs 7.25 crRs 7.17 cr
-NARs 94.45 lakhRs 85.81 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAakar Architects
EngineerSanjay Ahire
Chartered AccountantShavarin K Nisar & Co
PartnerRole in project
Konark Enterprises-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900025255Dec 2024 → Sep 2025

Reason as filed by the promoterWe, hereby apply for extension of Project Registration u/s 6 of the Real Estate (Regulation & Develop-ment) Act, 2016 for the registered project bearing vide no P51900033696 until date 30/09/2025. As certified by the Architect in Form-1 for last quarter, submitted as part of Quarterly Progress Reports, majority of the construction work of the project is completed and balance finishing work is in progress. We are hopeful that the balance work will get completed in couple of months and few months thereafter are required for obtaining various NOCS as well as Occupation Certificate for the project

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12603841Rohan Ramesh BhingardeKonark Enterprises21/06/2026
CC12604061Hrishikesh Vilas GopaleKonark Enterprises30/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed124

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 124 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Aarush Form-1 Sept 2025.pdf10 Mar 2026
Withdrawal Update Form 2File: Aarush Form-2 Sept 2025.pdf10 Mar 2026
Withdrawal Update Form 3File: Aarush Form-3 Sept 2025.pdf10 Mar 2026
Withdrawal Update Form 1File: KA Form 1 202506.pdf9 Feb 2026
Withdrawal Update Form 2File: KA Form 2 202506.pdf9 Feb 2026
Withdrawal Update Form 3File: KA Form 3 202506.pdf9 Feb 2026
Form 1File: Konark Arch Form 1 202306.pdf17 Nov 2025
Form 2File: Konark Engr Form 2 202306.pdf17 Nov 2025
Form 3File: Konark CA Form 3 202306.pdf17 Nov 2025
Disclosure of Sold and Booked InventoryFile: Konark Disclosure of Sold 202306.pdf17 Nov 2025
Form 1File: Konark Arc Form 1 202303.pdf17 Nov 2025
Form 2File: Konark Engr Form 2 202303.pdf17 Nov 2025
Form 3File: Konark CA Form 3 202303.pdf17 Nov 2025
Disclosure of Sold and Booked InventoryFile: Konark Disclosure- March 2023.pdf17 Nov 2025
Form 1File: Konark Arc Form 202212.pdf17 Nov 2025
Form 2File: Konark Engr Form 2 202212.pdf17 Nov 2025
Form 3File: Konark CA Form 3 202212.pdf17 Nov 2025
Disclosure of Sold and Booked InventoryFile: Konark Sold Unsold Disclosure 202212.pdf17 Nov 2025
Form 1File: 202403_Ar.pdf6 Oct 2025
Form 2File: 202403_Er.pdf6 Oct 2025
Form 3File: 202403_CA.pdf6 Oct 2025
Disclosure of Sold and Booked InventoryFile: 202403_Sold.pdf6 Oct 2025
Form 1File: 202406_Ar.pdf6 Oct 2025
Form 2File: 202406_Er.pdf6 Oct 2025
Form 3File: 202406_CA.pdf6 Oct 2025
Disclosure of Sold and Booked InventoryFile: 202406_Sold.pdf6 Oct 2025
Form 1File: KE_A_2409-1_Form-1.pdf6 Oct 2025
Form 2File: KE_A_2409-2_Form-2.pdf6 Oct 2025
Form 3File: KE_A_2409-4_Form-3.pdf6 Oct 2025
Disclosure of Sold and Booked InventoryFile: KE_A_2409-3_Sold.pdf6 Oct 2025
Form 1File: Konark Form 1_Arct.pdf6 Oct 2025
Form 2File: Konark Form 2_Enr.pdf6 Oct 2025
Form 3File: Konark Form 3_CA.pdf6 Oct 2025
Disclosure of Sold and Booked InventoryFile: Konark Disclouser sold unsold inv Dec 24.pdf6 Oct 2025
Form 1File: Konark Form 1 202503.pdf6 Oct 2025
Form 2File: Konark Engg Certificate as on March 2025 Compres2.pdf6 Oct 2025
Form 3File: Konark Form-3 202503 (1).pdf6 Oct 2025
Disclosure of Sold and Booked InventoryFile: Konark - Disclosure SoldUnsold units 202503.pdf6 Oct 2025
Form 1File: 202309_Konark Architect.pdf6 Oct 2025
Form 2File: 202309_Konark Engineer Cer.pdf6 Oct 2025
Form 3File: 202309_CA.pdf6 Oct 2025
Disclosure of Sold and Booked InventoryFile: Konark Disclosure of Sold 202309.pdf6 Oct 2025
Commencement Certificates / NA Order for plotted developmentFile: KE_CC_20floor.pdf11 Mar 2025
Declaration about Commencement CertificateFile: Declaration of CC11032025 2.pdf11 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24_compressed.pdf5 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 RERA Konark Enterprises_FY 23-24_04 03 2025ZA.pdf4 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Konark Arct Certi as on 31122024.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Konark CA Cert as on 31122024.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Konark sold unsold inv 31122024.pdf24 Jan 2025
Declaration in FORM BFile: REvised Form-B.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202406_Ar.pdf25 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KE_A_2409-1_Form-1.pdf25 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202406_CA.pdf25 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KE_A_2409-4_Form-3.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202406_Er.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KE_A_2409-2_Form-2.pdf25 Nov 2024
Disclosure of sold/ booked inventoryFile: 202406_Sold.pdf25 Nov 2024
Disclosure of sold/ booked inventoryFile: KE_A_2409-3_Sold.pdf25 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2022-23_Konark Form 2A.pdf25 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Konark Form 5-March 2023.pdf25 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202309_Konark Architect.pdf30 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202403_Ar.pdf30 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202309_Konark Engineer Cer.pdf30 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202403_CA.pdf30 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202403_Er.pdf30 May 2024
Disclosure of sold/ booked inventoryFile: 202306_Sold.pdf30 May 2024
Disclosure of sold/ booked inventoryFile: 202309_Sold.pdf30 May 2024
Disclosure of sold/ booked inventoryFile: 202403_Sold.pdf30 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202309_CA.pdf30 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202403_CA.pdf30 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202306_Ar.pdf25 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202306_Er.pdf25 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202303_CA.pdf25 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202306_CA.pdf25 Sep 2023
Declaration about Commencement CertificateFile: 20230714_CC Declaration.pdf14 Jul 2023
Building plan approvalFile: 20230425_IoD Plan.pdf13 Jul 2023
Building plan approvalFile: 20230425_IoD.pdf13 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: 20230425_IoD Plan.pdf13 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: 20230425_IoD.pdf13 Jul 2023

How this compares with Mumbai City

34%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 9 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aarush on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mazgaon780+ in Mumbai City

2 kmAarushCompleted 9Lapsed / revoked 15Other 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 69 registered projects within 2 km.

Builder: Konark Enterprises

KONARK ENTERPRISES has 2 registrations on MahaRERA, including KRUPANIDHI and Aarush. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that Aarush shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Aarush is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aarush?

The registered promoter entity is Konark Enterprises, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aarush?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Aarush?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Aarush?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aarush?

The professionals named in the filing: Architect: Aakar Architects; Engineer: Sanjay Ahire; Chartered Accountant: Shavarin K Nisar & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aarush?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aarush. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aarush to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.