AAI CHANDIKA HILLS

By SHIVAM BUILDERS & DEVELOPERS

RG-MH-36827 · RERA P99000045679 · Last updated on MahaRERA portal: 10 Aug 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
10 of 11Construction stages donefurthest along: Installation of Lifts, 99%
28 of 120Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

AAI CHANDIKA HILLS is a Others project by SHIVAM BUILDERS & DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000045679 on 6 Jun 2022. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 18 months from the original filing. 92 of the 120 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameAAI CHANDIKA HILLS
  • TypeOthers
  • Location
    • JUHUCHANDRA BAPANE ROAD
    • VASAI
    • Chandrapada
    • Palghar
    • 401208
  • Pincode401208
  • RERA no.P99000045679
  • ReraGenie IDRG-MH-36827

Builder

  • NameSHIVAM BUILDERS & DEVELOPERS
  • Entity typeOthers
  • Named personVILAS BHOIR

Key dates

1 months past promisethis monthRegisteredJun 2022First promiseMar 2025Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Jun 2022
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 31 Mar 2025)
  • Buildings1 building record
  • Documents filed85 files

Current status

77%92 of 120 units booked
100.0%Work done, per cost certificate

Figures as on 10 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AAI CHANDIKA HILLSNA221810218120

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 99%.

AAI CHANDIKA HILLS: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%

Progress on shared amenities15

As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed42

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots42
Closed/Covered42

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,370 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 Jul 2025

Approvals and building plan

Sanctioning authorityVASAI VIRAR MUNICIPAL CORPORATION
Permissible FSI6875.09
Proposed, not sanctioned6,875 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchChrist House,Shop No 2 TO 4 Near KBP Vidyalaya Juchandra Naigaon East Vasai Virar Maharashtra 401208
Estimated costRs 29.96 cr
Cost incurredRs 29.96 cr
Work done100.0%
BuildingWingEstimatedIncurred
AAI CHANDIKA HILLSNARs 26.96 crRs 26.96 cr
-NARs 3.00 crRs 3.00 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUMESH KEKRE
EngineerJAY SHREE KRISHNA
EngineerMUKESH KUMAR
Chartered AccountantNEHALI & CO
Chartered AccountantNEHALI DHAVAL DOSHI
PartnerRole in project
SHIVAM BUILDERS & DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000027731Mar 2025 → Mar 2026

Reason as filed by the promoterWith reference to above subject Sir/Madam, I Vilas Madhukar Bhoir having PAN No. AIQPB2198Cam the proprietor of Shivam Builders & developers and am the owner of above-mentioned land/plot, I applied for RERA number and allotted RERA number on dated 06.06.2022 Sir I just want to inform you that before this project started, I was sand supplier and this is practically and theoretically my first project. Sir I inform you at the starting of this project i appoint one contractor but he has not fulfilled his commitment of work and he has left the work in between period so my work got stopped and slow

EA07042620571Mar 2025 → Sep 2026

Reason as filed by the promoterRespected Sir, M/S. SHIVAM BUILDERS & DEVELOPERS through Proprietor Mr. Vilas Madhukar Bhoir, Promoter of the proposed project AAI CHANDIKA HILLS, duly authorized by the promoter of the proposed project bearing Maha RERA Registration No P99000045679. This is to inform that the construction work of the project has been completed in all respects, and the project is ready for occupation. However, there has been an unavoidable delay in obtaining the Occupation Certificate (OC). The delay is primarily due to administrative reasons, specifically the transfer of the concerned Commissioner, which has

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Q1 Architect Certificate.pdf10 Aug 2026
Withdrawal Update Form 2File: Q1 Engineer Certificate.pdf10 Aug 2026
Withdrawal Update Form 3File: Q1 CA Certificate.pdf10 Aug 2026
Withdrawal Update Form 1File: Signed Architect Certificate.pdf8 May 2026
Withdrawal Update Form 2File: Signed Engineer Certificate.pdf8 May 2026
Withdrawal Update Form 3File: Signed CA Certificate- aai chandika_m26.pdf8 May 2026
Withdrawal Update Form 1File: Q3 Architect Certificate.pdf28 Mar 2026
Withdrawal Update Form 1File: Q3 Architect Certificate.pdf28 Mar 2026
Withdrawal Update Form 2File: Q3 Engineer Certificate.pdf28 Mar 2026
Withdrawal Update Form 2File: Q3 Engineer Certificate.pdf28 Mar 2026
Withdrawal Update Form 3File: Resigned 26-03-26 CA.pdf28 Mar 2026
Withdrawal Update Form 3File: Resigned 26-03-26 CA.pdf28 Mar 2026
Withdrawal Update Form 1File: form 1.pdf13 Nov 2025
Withdrawal Update Form 2File: form 2.pdf13 Nov 2025
Withdrawal Update Form 3File: form 3.pdf13 Nov 2025
Withdrawal Update Form 1File: Q1 Architect Certificate 25.pdf23 Sep 2025
Withdrawal Update Form 2File: Q1 Engineering Certificate 25.pdf23 Sep 2025
Withdrawal Update Form 3File: Signed CA Certificate 25.pdf23 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Resigned_CA Certificate- aai chandika_dec 24.pdf5 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory .pdf5 Mar 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY .pdf4 Mar 2025
Declaration in FORM BFile: Affidavit Cum Declaration 500 rupees.pdf22 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Signed Form 5- 22-23 aai chandika_.pdf8 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Signed Form 5- 23-24 aai chandika_.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate- aai chandika_dec 24.pdf3 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate- aai chandika_dec 24.pdf3 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 april to june 24.pdf21 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 july to sep 24.pdf21 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1_June 24.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Sept 24.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Dec 24.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2Sept 23.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Dec 24.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Sept 24.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 June 24.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 March 24.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Dec 23.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2_June 23 Q1.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf22 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf22 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf22 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf22 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf22 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf22 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf22 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf22 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_March 23.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_June 23.pdf5 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 22 Q4.pdf27 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 23 Q1.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 22 Q4.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 23 Q1.pdf27 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Shivam Builders and Developer.pdf16 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf26 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Structural Engineer Certificate.pdf24 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accounts Certificate.pdf24 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM 3.pdf20 May 2022
CERSAI detailsFile: Cersai Declaration.pdf15 Apr 2022
Declaration about Commencement CertificateFile: format-d.pdf12 Feb 2022
Proforma of Allotment letterFile: Agreement for sale under RERA CHANDRAPADA.pdf12 Feb 2022
Proforma of Allotment letterFile: allotment letter-Vilas Bhoir.pdf12 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf7 Feb 2022
Layout approvalFile: PLAN 1.pdf5 Feb 2022
Layout approvalFile: PLAN 2.pdf5 Feb 2022
Building plan approvalFile: PLAN 1.pdf5 Feb 2022
Building plan approvalFile: PLAN 2.pdf5 Feb 2022
Layout approvalFile: PLAN 3.pdf5 Feb 2022
Layout approvalFile: PLAN 4.pdf5 Feb 2022
Building plan approvalFile: PLAN 3.pdf5 Feb 2022
Building plan approvalFile: PLAN 4.pdf5 Feb 2022
PAN CardFile: Pan Card.pdf5 Feb 2022
Copy of the legal title reportFile: FINAL TITLE REPORT.pdf5 Feb 2022
Details of encumbrancesFile: NO ENCUMBRANCE.pdf5 Feb 2022
Copy of Layout Approval (in case of layout)File: PLAN 1.pdf5 Feb 2022
Copy of Layout Approval (in case of layout)File: PLAN 2.pdf5 Feb 2022
Copy of Layout Approval (in case of layout)File: PLAN 3.pdf5 Feb 2022
Copy of Layout Approval (in case of layout)File: PLAN 4.pdf5 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PLAN 1.pdf5 Feb 2022

How this compares with Palghar

77%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 18 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AAI CHANDIKA HILLS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VASAI3,200+ in Palghar

Builder: SHIVAM BUILDERS & DEVELOPERS

SHIVAM BUILDERS & DEVELOPERS has 1 registration on MahaRERA, including AAI CHANDIKA HILLS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if AAI CHANDIKA HILLS is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AAI CHANDIKA HILLS?

The registered promoter entity is SHIVAM BUILDERS & DEVELOPERS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AAI CHANDIKA HILLS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AAI CHANDIKA HILLS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AAI CHANDIKA HILLS?

The professionals named in the filing: Architect: UMESH KEKRE; Engineer: JAY SHREE KRISHNA; Engineer: MUKESH KUMAR; Chartered Accountant: NEHALI & CO; Chartered Accountant: NEHALI DHAVAL DOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAI CHANDIKA HILLS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAI CHANDIKA HILLS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAI CHANDIKA HILLS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.