Home / Browse projects / Pune, Maharashtra / 24Life Altaa
24Life Altaa
By KSHITEJ REALTORS THROUGH ITS PROPRIETOR KAUSTUBH S TALEKAR
RG-MH-23660 · RERA P52100078972 · Last updated on MahaRERA portal: 1 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 4 months
- 1 extension taken
- Rs 10.00 crore secured on the land, in favour of HERO FINCORP LIMITED
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
24Life Altaa is a Others project by KSHITEJ REALTORS THROUGH ITS PROPRIETOR KAUSTUBH S TALEKAR in Pune, Maharashtra, registered with MahaRERA as P52100078972 on 24 Jan 2025. Possession is promised by 28 Feb 2029. The completion date has moved by 4 months from the original filing. 10 of the 47 units on this registration are recorded sold or booked, and 3 of 10 construction stages are filed complete.
At a glance
Project
- Name24Life Altaa
- TypeOthers
- Location
- -
- Punawale
- Mulshi
- Pune
- 411033
- Pincode411033
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100078972
- ReraGenie IDRG-MH-23660
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Jan 2025
- Promised completion28 Feb 2029
- Revised completionRevised to 28 Feb 2029 (originally 31 Oct 2028)
- Buildings1 building record
- Documents filed85 files
Current status
Figures as on 1 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 24Life Altaa | NA | 15 | 13 | 36 | 11 | 47 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 1 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 10 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.
24Life Altaa: 48% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 1 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed133
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Deepali Dhanajay Kapre | Hadapsar | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| 24Life Altaa | NA | Rs 11.52 cr | Rs 10.40 cr |
| - | NA | Rs 1.90 cr | Rs 60.00 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Arcon Associates |
| Engineer | Mahadeo Shelar |
| Chartered Accountant | Snehal G Patil and Co |
| Chartered Accountant | Avishkar Phanse |
| Chartered Accountant | VSAP & Company |
| Partner | Role in project |
|---|---|
| KSHITEJ REALTORS THROUGH ITS PROPRIETOR KAUSTUBH S TALEKAR | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNA
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Dec 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 May 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 28 Feb 2029
Documents filed85
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Form 2A - FY 24-25 Altaa.pdf | 1 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A - FY 25-26 Altaa.pdf | 1 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Q1 24Life Altaa.pdf | 26 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Q1 24Life Altaa.pdf | 26 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Q1 24Life Altaa.pdf | 26 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Q4 24Life Altaa.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Q4 24Life Altaa.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 24Life Altaa.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Q3 Altaa.pdf | 15 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Q3 Altaa.pdf | 15 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 Q3 24Life Altaa.pdf | 15 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Q3 Altaa.pdf | 28 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Q3 Altaa.pdf | 28 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 Q3 Altaa.pdf | 28 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 Altaa Q2.pdf | 10 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 Altaa Q2.pdf | 10 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 Altaa Q2 QPR.pdf | 10 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 Altaa Q2.pdf | 5 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 Altaa Q2.pdf | 5 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 Altaa Q2.pdf | 5 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 Altaa Q1.pdf | 1 Aug 2025 |
| Withdrawal Update Form 2File: Form 2 Altaa Q1.pdf | 1 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 Altaa Q1.pdf | 1 Aug 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Annual Report - 24Life Altaa FY 2024-25.pdf | 27 Jul 2025 |
| Withdrawal Update Form 1File: Form 1 Q4.pdf | 23 Jul 2025 |
| Withdrawal Update Form 2File: Form 2 Q4.pdf | 23 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 Q4 FY 24-25.pdf | 23 Jul 2025 |
| Form 1File: Form 1 FY24-25 Q4 Altaa.pdf | 17 Jun 2025 |
| Form 2File: Form 2 FY24-25 Q4 Altaa.pdf | 17 Jun 2025 |
| Form 3File: Form 3 FY24-25 Q4 Altaa.pdf | 17 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Promoter Disclosure FY24-25 Q4 Altaa.pdf | 17 Jun 2025 |
| Building plan approvalFile: 4.pdf | 17 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY24-25 Q4 Altaa.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY24-25 Q4 Altaa.pdf | 27 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 (Altaa) Q4 FY 24-25.pdf | 27 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Promotor disclosure Q4 Altaa.pdf | 27 Apr 2025 |
| Building plan approvalFile: 1.pdf | 19 Apr 2025 |
| Building plan approvalFile: 2.pdf | 19 Apr 2025 |
| Building plan approvalFile: 3.pdf | 19 Apr 2025 |
| Building plan approvalFile: 5.pdf | 19 Apr 2025 |
| Building plan approvalFile: 4.pdf | 19 Apr 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Altaa 2nd CC.pdf | 19 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 1.pdf | 19 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 19 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 19 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 19 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 19 Apr 2025 |
| Declaration about Commencement CertificateFile: Revised Declaration of CC.pdf | 19 Apr 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: new_Format B Bank Account Details (2).pdf | 16 Jan 2025 |
| Deviation Report with respect to Allotment letterFile: DEVIATION REPORT - ALLOTMENT LETTER - PAYMENT SCHEDULE DEVIATION.pdf | 15 Jan 2025 |
| Other - FinanceFile: Declaration of Pancard.pdf | 15 Jan 2025 |
| Proforma of Agreement for saleFile: DRAFT AGREEMENT - 24 LIFE ALTAA.pdf | 15 Jan 2025 |
| Other - TechnicalFile: ALtaa CC PCMC.pdf | 10 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 28 Dec 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Landowner Declaration Bank account.pdf | 28 Dec 2024 |
| Other - TechnicalFile: Annexure A - Altaa.pdf | 20 Dec 2024 |
| PAN CardFile: Pan card KT.pdf | 19 Dec 2024 |
| Proforma of Allotment letterFile: Allotment Letter Altaa.pdf | 19 Dec 2024 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION With Respect To Agreement.pdf | 19 Dec 2024 |
| Copy of the legal title reportFile: ALtaa TSR.pdf | 18 Dec 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Declaration about RERA Designated Bank Accounts for real estate projects.pdf | 16 Dec 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured and unsecured finance availed.pdf | 14 Dec 2024 |
| Building plan approvalFile: 6.pdf | 12 Dec 2024 |
| Building plan approvalFile: 5.pdf | 12 Dec 2024 |
| Building plan approvalFile: 4.pdf | 12 Dec 2024 |
| Building plan approvalFile: 3.pdf | 12 Dec 2024 |
| Building plan approvalFile: 2.pdf | 12 Dec 2024 |
| Layout approvalFile: 1.pdf | 12 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Letter - Finance.pdf | 12 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Letter - Legal.pdf | 12 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 12 Dec 2024 |
| Declaration in FORM BFile: Form B Promoter.pdf | 12 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 12 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 12 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Altaa CC.pdf | 12 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 12 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 12 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 12 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 12 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 12 Dec 2024 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| 24Life BlissP52100054878 | DUDULGAON, Pune | 154 | Feb 2024 | Ongoing | Jul 2027 | Not due yet |
| 24Life ExoticaP52100049643 | Dudulgaon, Pune | 242 | Feb 2023 | Ongoing | Dec 2026 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 85 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep 24Life Altaa on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near -13,700+ in Pune
Filed coordinates, straight-line distance. 232 registered projects within 2 km.
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: KSHITEJ REALTORS THROUGH ITS PROPRIETOR KAUSTUBH S TALEKAR
KSHITEJ REALTORS THROUGH ITS PROPRIETOR KAUSTUBH S TALEKAR has 2 registrations on MahaRERA, including 24Life Blooms and 24Life Altaa. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if 24Life Altaa is delayed beyond 28 Feb 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of 24Life Altaa?
The registered promoter entity is KSHITEJ REALTORS THROUGH ITS PROPRIETOR KAUSTUBH S TALEKAR, an individual as per the filing. Its GSTIN 27AEYPT6234K1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in 24Life Altaa?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for 24Life Altaa?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at 24Life Altaa?
The professionals named in the filing: Architect: Arcon Associates; Engineer: Mahadeo Shelar; Chartered Accountant: Snehal G Patil and Co; Chartered Accountant: Avishkar Phanse; Chartered Accountant: VSAP & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in 24Life Altaa?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback