Home / Browse projects / Pune, Maharashtra / 1 Hallmark Avenue Phase I

Completed No litigation declared Residential / Group Housing project

1 Hallmark Avenue Phase I

By RajHeramb Properties

RG-MH-11605 · RERA P52100002760 · Last updated on MahaRERA portal: 21 Jun 2021

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2019Possession promisedregistration recorded completed
79 of 88Construction stages doneacross 8 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

1 Hallmark Avenue Phase I is a Residential / Group Housing project by RajHeramb Properties in Pune, Maharashtra, registered with MahaRERA as P52100002760 on 4 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2019. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • Name1 Hallmark Avenue Phase I
  • TypeResidential / Group Housing
  • Location
    • BRT Road
    • Ravet
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002760
  • ReraGenie IDRG-MH-11605

Builder

  • NameRajHeramb Properties
  • Entity typeOthers
  • Named personPravin Vishwanath Patil
  • Other registrations5 more →
  • Completed4 of 6
  • Declared earlier projects6 →

Key dates

this monthRegisteredAug 2017First promiseJun 2018Revised toJun 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Aug 2017
  • Promised completion30 Jun 2019
  • Revised completionRevised to 30 Jun 2019 (originally 30 Jun 2018)
  • Buildings8 building records
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BNA140000
CNA140000
DNA140000
ENA140000
FNA140000
GNA140000
HNA140000
INA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 21 Jun 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

79 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Podiums (if any), at 0%.

B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
I82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Jun 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes40%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes40%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed321

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots321
Closed/Covered127
Open Space194
BuildingClosed/CoveredOpen SpaceTotal
B163147
C163147
D163147
E163147
F163147
G161430
H161329
I151227

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,286 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI15445.11
Proposed, not sanctioned15,445 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNDA Road Bavdhan Pune

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGem Associate Mr Girish Gupte
EngineerSpectrum Consultants Mr Parag Chopda
PartnerRole in project
RajHeramb Properties-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100000449Jun 2018 → Jun 2019

Reason as filed by the promoterAs our Project 1 Hallmark Avenue Phase I registered with MAHARERA . We have initially given the completion Date as 30/06/2018. As on today work on the site is 100% complete for 7 Building out of Total 8 Buildings. we have obtained all NOC's from Pimpri Chinchwad Municipal Corporation and have Completed the formalities for obtaining Completion Certificate from Pimpri Chinchwad Municipal Corporation. There is delay in getting Completion Certificate from Pimpri Chinchwad Municipal Corporation Hence,request you to kindly extend our date of completion

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Feb 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Feb 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: ABC805.pdf21 Jun 2021
Certificates of CA (Form 5)File: RERA ARCHIECT FORM 4 CERTIFICATE RAVET PHASE I.pdf27 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 200122041513_0001.pdf22 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 200122041513_0001.pdf22 Jan 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: RERA ENGINEER 2A CERTIFICATE RAVET PHASE I.pdf22 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: RERA ARCHIECT FORM 4 CERTIFICATE PHASE I.pdf22 Jan 2020
Details of encumbrancesFile: ECL Ravet TL Index II.pdf21 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certifcate Ravet.pdf21 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Cert.pdf21 May 2019
Certificates of CA (Form 3)File: CA Certifcate Ravet B to I Wing.pdf21 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase I Ravet.pdf20 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Phase I Ravet.pdf20 Feb 2019
Certificates of CA (Form 3)File: CA RAVET.pdf20 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Ravet'.pdf3 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 181203080350_0001.pdf3 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engi Certificate Ravet.pdf3 Dec 2018
OtherFile: 181203081210_0001.pdf3 Dec 2018
Certificates of CA (Form 5)File: CA Certifecate Ravet.pdf15 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ravet Architect Certificate.pdf7 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ravet Phase 1 Engineers Certificate.pdf7 Aug 2018
Certificates of CA (Form 3)File: CA Certificate Ravet.pdf7 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Architect Certificate Ravet.pdf18 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Ravet.pdf18 May 2018
Certificates of CA (Form 3)File: CA Certificates Ravet.pdf18 May 2018
Layout approvalFile: new plan 1mb format layout ravet.pdf27 Feb 2018
Copy of Layout Approval (in case of layout)File: new plan 1mb format layout ravet.pdf27 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: Ravet CC.pdf27 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Ravet.pdf27 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate Ravet.pdf27 Feb 2018
Certificates of CA (Form 3)File: 180227065918_0001.pdf27 Feb 2018
Details of encumbrancesFile: Anand rathi Index 2.pdf15 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ravet Architect Certificate.pdf4 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ravet Engineer Certificate.pdf4 Nov 2017
Certificates of CA (Form 3)File: Ravet CA Certificate.pdf4 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ravet Architect Certificate.pdf27 Jul 2017
Layout approvalFile: Ravet Layout.pdf26 Jul 2017
Building plan approvalFile: Ravet IOD Layout.pdf26 Jul 2017
PAN CardFile: Pravin Sir PAN.pdf26 Jul 2017
Copy of the legal title reportFile: Ravet Title.pdf26 Jul 2017
Details of encumbrancesFile: Ravet Title.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Ravet Layout.pdf26 Jul 2017
Building Plan Approval (IOD)File: Ravet IOD Layout.pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Ravet Commencement Certificate.pdf26 Jul 2017
Declaration in FORM BFile: FORM B Ravet.pdf26 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ravet Engineer Certificate.pdf26 Jul 2017
Certificates of CA (Form 3)File: Ravet CA Certificate.pdf26 Jul 2017
Proforma of Allotment letterFile: Ravet.PDF26 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Venkatesh ImperiaSurvey No 14 part 4 Punawale Tal Mulshi Dist.Pune128CompletedDec 2015Late, Jun 2016
Regalia ResidencyPlot No 1 14 15 16 out of survey no 276 277 278 275 Bavdhan BK Tal Mulshi Dist Pune119CompletedAug 2014Late, Jun 2015

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 1 Hallmark Avenue Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ravet13,700+ in Pune

2 km1 Hallmark Avenue Phase Completed 114Lapsed / revoked 50Other 115Dot size: filed unitsN

Filed coordinates, straight-line distance. 279 registered projects within 2 km.

Builder: RajHeramb Properties

RajHeramb Properties has 6 registrations on MahaRERA, including Regalia Residency and Venkatesh Imperia Phase I. Its filings disclose 6 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if 1 Hallmark Avenue Phase I is delayed beyond 30 Jun 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 1 Hallmark Avenue Phase I?

The registered promoter entity is RajHeramb Properties, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 1 Hallmark Avenue Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for 1 Hallmark Avenue Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 1 Hallmark Avenue Phase I?

The professionals named in the filing: Architect: Gem Associate Mr Girish Gupte; Engineer: Spectrum Consultants Mr Parag Chopda. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 1 Hallmark Avenue Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 1 Hallmark Avenue Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 1 Hallmark Avenue Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.