Home / Developers / KBC GLOBAL LIMITED
KBC GLOBAL LIMITED: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
KBC GLOBAL LIMITED has 20 registrations in this build, including HARI SPARSH II and HARI VATIKA. Its filings disclose 12 earlier MahaRERA projects: 2 of 12 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| HARI SPARSH II | Nashik, Maharashtra | - | - | Completed |
| HARI VATIKA | Nashik, Maharashtra | - | - | Completed |
| HARI NAMAN | Nashik, Maharashtra | - | - | Completed |
| HARI SPARSH PHASE III | Nashik, Maharashtra | - | - | Completed |
| HARI OM PHASE II | Nashik, Maharashtra | - | - | Registration lapsed |
| HARI SANSKRUTI PHASE II | Nashik, Maharashtra | 418 | 58% | Registration lapsed |
| HARI BHAKTI | Nashik, Maharashtra | - | - | Registration lapsed |
| Hari Sanskruti Phase I | Nashik, Maharashtra | - | - | Completed |
| HARI VISHWA D BUILDING | Nashik, Maharashtra | 100 | 97% | Registration lapsed |
| HARI ANAND | Nashik, Maharashtra | - | - | Completed |
| HARI SAMARTH | Nashik, Maharashtra | - | - | Registration lapsed |
| HARI LAXMI PHASE I | Nashik, Maharashtra | 31 | 39% | Registration lapsed |
| HARI LAXMI PHASE II | Nashik, Maharashtra | 56 | 98% | Registration lapsed |
| HARI LAXMI PHASE III | Nashik, Maharashtra | - | - | Registration lapsed |
| HARI NISARG | Nashik, Maharashtra | 38 | 45% | Registration lapsed |
| HARI AAKRUTI PHASE II | Nashik, Maharashtra | 49 | 100% | Registration lapsed |
| HARI VRUDDHI | Nashik, Maharashtra | - | - | Registration lapsed |
| HARI KUNJ MAYFLOWER | Nashik, Maharashtra | - | - | Registration lapsed |
| HARI KRISHNA PHASE IV | Nashik, Maharashtra | 69 | 100% | Registration lapsed |
| Hari Aangan- Residential, High Streets Shopping Mall -Commercial | Nashik, Maharashtra | - | - | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Hari Niwas | 11 Jul 2011 | 6 Sep 2011 | +2 months |
| Hari Sankul Phase I | 25 Dec 2011 | 29 May 2012 | +5 months |
| Hari Vandan Phase II | 16 Aug 2012 | 31 Oct 2012 | +2 months |
| Hari Kunj | 30 Sep 2012 | 31 Oct 2012 | +1 months |
| Hari Sankalp | 20 Oct 2012 | 5 Nov 2012 | +1 months |
| Hari Sneh I | 8 Dec 2012 | 4 Sep 2012 | On time |
| Hari Aangan Phase I | 2 Apr 2013 | 7 May 2013 | +1 months |
| Hari OmPhase I | 1 Oct 2013 | 16 Nov 2013 | +2 months |
| Hari Sparsh | 1 May 2014 | 28 Apr 2014 | On time |
| Hari Amrut | 5 Jul 2014 | 21 Jul 2014 | +1 months |
| Hari Sneh Phase II | 5 May 2015 | 1 Jun 2015 | +1 months |
| Hari Shrushti | 31 Jul 2015 | 15 Aug 2015 | On time |
Frequently asked questions
How do I verify KBC GLOBAL LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with KBC GLOBAL LIMITED?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.