Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
18 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 90%
1Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

HARI BHAKTI is a Others project by KBC GLOBAL LIMITED in Nashik, Maharashtra, registered with MahaRERA as P51600000585 on 18 Jul 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 42 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameHARI BHAKTI
  • TypeOthers
  • Location
    • Datta Mandir road
    • Deolali (CB)
    • Nashik
    • 422101
  • Pincode422101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600000585
  • ReraGenie IDRG-MH-00714

Builder

  • NameKBC GLOBAL LIMITED
  • Entity typeCompany
  • CINL45400MH2007PLC174194
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Managing DirectorNaresh Jagumal Karda
  • Other registrations19 more →
  • Completed6 of 20
  • No longer live13 lapsed, de-registered or revoked
  • Declared earlier projects12 →

Key dates

22 months past promisethis monthRegisteredJul 2017First promiseJun 2021Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Jul 2017
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 30 Jun 2021)
  • Buildings3 building records
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA70000
BNA140000
CNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 28 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 90%.

A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B39%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 28 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes50%

Parking filed103

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots103
Closed/Covered51
Open Space52
BuildingClosed/CoveredOpen SpaceTotal
A152237
B161733
C201333

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,066 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
Giriraj DevelopersNashikNashik
Narendra Janardan GadekarNashikNashik
Anjali Janardhan GadekarMumbai CityMumbai City
Sangita Janardhan GadekarwanwadiPune
Sarlabai Janardhan GadekarNashikNashik
Suvarna Janardhan GadekarNashikNashik

Approvals and building plan

Permissible FSI8400.0
Proposed, not sanctioned5,408 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHINGADA TALAV NASHIK PUNE RD, NASHIK

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRasik Bothara
EngineerR G Birla
PartnerRole in project
DHARAN INFRA-EPC LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600013618Jun 2021 → Dec 2024

Reason as filed by the promoterWork is being delayed due to unavoidable reasons

EXT51600009686Jun 2021 → Jun 2022

Reason as filed by the promoterDue to strict precautionary norms of government during this pandemic the constitution is getting delayed .hence extension is requested

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC001000000020256SATISH LAXMAN NANGUDEKARDA CONSTRUCTIONS LIMITED23/04/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: HARI BHAKTI JUNE.pdf28 Feb 2025
Disclosure of sold/ booked inventoryFile: HARI BHAKTI SEPT.pdf28 Feb 2025
Disclosure of sold/ booked inventoryFile: HARI BHAKTI DEC.pdf28 Feb 2025
Disclosure of sold/ booked inventoryFile: HARI BHAKTI.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Bhakti.pdf26 Apr 2024
Details of encumbrancesFile: Encumbrance certificate (1)_page-0001_page-0001.pdf23 Feb 2024
Details of encumbrances concerned to FinanceFile: Encumbrance certificate finance_page-0001_page-0001.pdf23 Feb 2024
Details of encumbrances concerned to LegalFile: Encumbrance certificate finance_page-0001_page-0001.pdf23 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank acc details (4)_page-0001.pdf23 Feb 2024
Deviation Report with respect to Allotment letterFile: Encumbrance certificate-model allotment letter_page-0001_page-0001.pdf23 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Encumbrance certificate-model agreement_page-0001_page-0001.pdf23 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Bhakti.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Bhakti.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Bhakti.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Bhakti.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Bhakti.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: hari bhakti.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Bhakti.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Bhakti.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Bhakti.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Bhakti.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Bhakti.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Bhakti.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Bhakti.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Bhakti.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Reco covering letter - 30062022 (1).pdf23 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 3009BHAKTI.pdf23 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 3112BHAKTI.pdf23 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20) (1).pdf23 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20) (1).pdf23 Jan 2023
Disclosure of sold/ booked inventoryFile: HARI BHAKTI.pdf29 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Hari bhakti 2a.pdf25 Apr 2022
Disclosure of sold/ booked inventoryFile: Hari Bhakti.pdf12 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: HARI BHAKTI.pdf22 Jan 2022
Disclosure of sold/ booked inventoryFile: HARI BHAKTI.pdf15 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Bhakti.pdf14 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: BHAKTI.pdf14 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Bhakti.pdf13 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Bhakti.pdf13 Oct 2021
Disclosure of sold/ booked inventoryFile: HARI BHAKTI (1).pdf12 Oct 2021
Disclosure of sold/ booked inventoryFile: Hari Bhakti.pdf8 Oct 2021
Disclosure of sold/ booked inventoryFile: Hari Bhakti.pdf7 Oct 2021
Declaration about Commencement CertificateFile: BHAKTI-DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf19 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Bhakti 19-20.pdf19 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Bhakti 20-21.pdf19 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - Hari Bhakti-18-19.pdf1 Oct 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Hari Bhakti_compressed.pdf30 Sep 2020
Certificates of CA (Form 5)File: Form 5 - Hari Bhakti_compressed.pdf30 Sep 2019
Certificates of CA (Form 5)File: Form 5 - Hari Bhakti-ilovepdf-compressed.pdf30 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf21 Apr 2018
Certificates of CA (Form 3)File: 9_Bhakti -ca certificate.pdf14 Jul 2017
Layout approvalFile: 4_LayoutApproval.pdf12 Jul 2017
Building plan approvalFile: 4_LayoutApproval.pdf12 Jul 2017
Copy of the legal title reportFile: 2_Supplementary Search report - Hari bhakti.pdf12 Jul 2017
Details of encumbrancesFile: 3_Encumbrances Hari Bhakti-min.pdf12 Jul 2017
Copy of Layout Approval (in case of layout)File: 4_LayoutApproval.pdf12 Jul 2017
Building Plan Approval (IOD)File: 4_LayoutApproval.pdf12 Jul 2017
Declaration in FORM BFile: 6_Form B Promoter.pdf12 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7_Bhakti Certificate-min.pdf12 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11_Eng Cert-Hari Bhakti.pdf12 Jul 2017
Proforma of Allotment letterFile: 5_AllotmentAgreement-ilovepdf-compressed.pdf12 Jul 2017

Promoter's earlier projects12

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise10 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Hari ShrushtiOpp IT Park Wadala Road indira Nagar Nashik 42221450CompletedJul 2015Late, Aug 2015
Hari Sneh Phase IIBehind Ashoka Universal School near IT park Nashik 42201150CompletedMay 2015Late, Jun 2015
Hari AmrutLokhande Mala Old Saikheda road Jail road Nashik 42221469CompletedJul 2014Late, Jul 2014
Hari SparshBarnes School Deolali camp Nashik-42250276CompletedMay 2014Apr 2014
Hari OmPhase INear Guru Givind Singh polytechnic college Indira Nagar Nashik 422009216CompletedOct 2013Late, Nov 2013
Hari Aangan Phase IJachak Mala Jai Bhavani Road Deolali24CompletedApr 2013Late, May 2013
Hari Sneh IBehind Ashoka universal School near IT park Nashik42201150CompletedDec 2012Sep 2012
Hari SankalpNear Serene Meadows Gangapur Road 42201337CompletedOct 2012Late, Nov 2012
Hari KunjJai Bhavani Road Nashik Road36CompletedSep 2012Late, Oct 2012
Hari Vandan Phase IINear Aarambh Maha Vidyalaya Sane Guruji nagar Jail Road Nashik 42210128CompletedAug 2012Late, Oct 2012
Hari Sankul Phase INear Ashoka Universal School behind Fame Multiplex Ashoka Marg Nashik 42200693CompletedDec 2011Late, May 2012
Hari NiwasBehind Muktidham near hotel Orange Tree Datta Mandir Nashik Road Nashik 42210193CompletedJul 2011Late, Sep 2011

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 42 months
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HARI BHAKTI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Datta Mandir road4,100+ in Nashik

2 kmHARI BHAKTICompleted 33Lapsed / revoked 7Other 31Dot size: filed unitsN

Filed coordinates, straight-line distance. 71 registered projects within 2 km.

Builder: KBC GLOBAL LIMITED

KBC GLOBAL LIMITED has 20 registrations on MahaRERA, including HARI SPARSH II and HARI VATIKA. Its filings disclose 12 earlier MahaRERA projects: declares 2 of 12 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that HARI BHAKTI shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if HARI BHAKTI is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HARI BHAKTI?

The registered promoter entity is KBC GLOBAL LIMITED, a company as per the filing. Its CIN L45400MH2007PLC174194 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HARI BHAKTI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HARI BHAKTI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for HARI BHAKTI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HARI BHAKTI?

The professionals named in the filing: Architect: Rasik Bothara; Engineer: R G Birla. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HARI BHAKTI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HARI BHAKTI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HARI BHAKTI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.