ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / HARI VRUDDHI

Registration lapsed No litigation declared Commercial project

HARI VRUDDHI

By KBC GLOBAL LIMITED

RG-MH-78073 · RERA P51600018377 · Last updated on MahaRERA portal: 21 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
0 of 11Construction stages donefurthest along: Stilt Floor, 50%
1Complaints at MahaRERAon this registration
Jump to the 83 documents Report an error

HARI VRUDDHI is a Commercial project by KBC GLOBAL LIMITED in Nashik, Maharashtra, registered with MahaRERA as P51600018377 on 26 Oct 2018. Possession was promised by 28 Dec 2025 and is now 10 months past that date. The completion date has moved by 48 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameHARI VRUDDHI
  • TypeCommercial
  • Location
    • Nashik road
    • Deolaligaon
    • Nashik
    • 422101
  • Pincode422101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600018377
  • ReraGenie IDRG-MH-78073

Builder

  • NameKBC GLOBAL LIMITED
  • Entity typeCompany
  • CINL45400MH2007PLC174194
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Managing DirectorNaresh Jagumal Karda
  • Other registrations19 more →
  • Completed6 of 20
  • No longer live13 lapsed, de-registered or revoked
  • Declared earlier projects12 →

Key dates

10 months past promisethis monthRegisteredOct 2018First promiseDec 2021Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Oct 2018
  • Promised completion28 Dec 2025
  • Revised completionRevised to 28 Dec 2025 (originally 30 Dec 2021)
  • Buildings1 building record
  • Documents filed83 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HARI VRUDDHINA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 50%.

HARI VRUDDHI: 18% average across the applicable activities

ActivityProgress
Excavation30%
Basement (if any)30%
Podiums (if any)0%
Plinth30%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,480 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3591.17
Proposed, not sanctioned3,591 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 10-18, SAI PLAZA, NASHIK ROAD-422101

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSumit Kumath
PartnerRole in project
DHARAN INFRA-EPC LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600011255Dec 2021 → Dec 2022

Reason as filed by the promoterThere has been delay in constructions activities due to unavoidable reasons.

EXT51600016551Dec 2021 → Dec 2025

Reason as filed by the promoterWork has been delayed due to unavoidable reasons

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC001000000090415Banu Ahmed BootwalaMr Naresh Karda of KBC Global limited03/12/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed83

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 311224.pdf21 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 310325.pdf21 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 311224.pdf21 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 310325.pdf21 May 2025
Disclosure of sold/ booked inventoryFile: HARI VRUDDHI DEC.pdf28 Mar 2025
Certificates of CA (Form 3)File: FORM 3 VRUDDHI-CORRECTION.pdf30 Dec 2024
Certificates of CA (Form 3)File: hari vrudhi 300924.pdf30 Dec 2024
Certificates of CA (Form 3)File: hari vrudhi 300624.pdf30 Dec 2024
Certificates of CA (Form 3)File: VRUDHI310324.pdf30 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 300924.pdf10 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 300624.pdf10 Dec 2024
Certificates of CA (Form 3)File: HARI VRUDDHI 300924.pdf10 Dec 2024
Certificates of CA (Form 3)File: HARI VRUDDHI 300624.pdf10 Dec 2024
Certificates of CA (Form 3)File: HARI VRUDDHI 310324.pdf10 Dec 2024
Certificates of CA (Form 3)File: VRUDDHI310323.pdf10 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Hari Vrudhi - Form 5 FY 22-23.pdf10 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5-vruddhi-23-24.pdf10 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: vruddhi 30624FORM 2.pdf6 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: vruddhi 30924-Form 2.pdf6 Dec 2024
Disclosure of sold/ booked inventoryFile: Vruddhisoldunsold300624.pdf6 Dec 2024
Disclosure of sold/ booked inventoryFile: vruddhisoldunsold300924.pdf6 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: vruddhi 30624-2A.pdf6 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: vruddhi 30924-Form 2A.pdf6 Dec 2024
Disclosure of sold/ booked inventoryFile: HARI VRUDDHI.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Vruddhi.pdf26 Apr 2024
Details of encumbrancesFile: Encumbrance certificate (1) (1)_page-0001_page-0001.pdf23 Feb 2024
Details of encumbrances concerned to FinanceFile: Encumbrance certificate finance (1)_page-0001_page-0001.pdf23 Feb 2024
Details of encumbrancesFile: Encumbrance certificate (1)_page-0001_page-0001.pdf23 Feb 2024
Details of encumbrances concerned to FinanceFile: Encumbrance certificate finance_page-0001_page-0001.pdf23 Feb 2024
Details of encumbrances concerned to LegalFile: Encumbrance certificate finance (1)_page-0001_page-0001.pdf23 Feb 2024
Details of encumbrances concerned to LegalFile: Encumbrance certificate finance_page-0001_page-0001.pdf23 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank acc details_page-0001_page-0001.pdf23 Feb 2024
Deviation Report with respect to Allotment letterFile: Encumbrance certificate-model allotment letter_page-0001_page-0001.pdf23 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Encumbrance certificate-model agreement_page-0001_page-0001.pdf23 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vruddhi.pdf17 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Hari Vruddhi.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Vruddhi.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Vruddhi.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Vruddhi.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Vruddhi.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Vruddhi.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Vruddhi.pdf17 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5-20-21.pdf22 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual report on Statement of Accounts-21-22.pdf22 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Hari Vruddhi.pdf17 Apr 2023
Disclosure of sold/ booked inventoryFile: Hari Vruddhi.pdf6 Apr 2023
Disclosure of sold/ booked inventoryFile: Hari Vruddhi.pdf6 Apr 2023
Disclosure of sold/ booked inventoryFile: Hari Vruddhi.pdf5 Apr 2023
Disclosure of sold/ booked inventoryFile: Hari Vruddhi.pdf5 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Hari Vruddhi.pdf20 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Hari Vruddhi.pdf20 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: H Vruddhi.pdf16 Mar 2023
Disclosure of sold/ booked inventoryFile: HARI VRUDDHI.pdf29 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Hari Vruddhi.pdf5 Apr 2022
Disclosure of sold/ booked inventoryFile: Hari Vruddhi.pdf12 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: hari vruddhi.pdf5 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: VRUDDHI.pdf13 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: VRUDDHI.pdf13 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: VRUDDHI.pdf13 Oct 2021
Disclosure of sold/ booked inventoryFile: Hari vruddhi.pdf9 Oct 2021
Disclosure of sold/ booked inventoryFile: Hari vruddhi.pdf9 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Hari Vruddhi.pdf8 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Hari Vruddhi.pdf8 Oct 2021
Disclosure of sold/ booked inventoryFile: Hari Vruddhi.pdf7 Oct 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE-Vruddhi.pdf15 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - Hari Vruddhi-18-19.pdf1 Oct 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Hari Vruddhi_compressed.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5)File: Form 5 - Hari Vruddhi_compressed.pdf30 Sep 2019
Proforma of Allotment letterFile: Vruddhi-Agreement.pdf20 Feb 2019
Building plan approvalFile: Vruddhi-Plan.pdf19 Oct 2018
Layout approvalFile: Vruddhi-Layout Plan.pdf19 Oct 2018
Layout approvalFile: Vruddhi-Layout.pdf19 Oct 2018
PAN CardFile: KCL PAN.pdf19 Oct 2018
Copy of the legal title reportFile: Vruddhi-Title Report (5).pdf19 Oct 2018
Details of encumbrancesFile: Vruddhi-Encumbrance Certificate.pdf19 Oct 2018
Copy of Layout Approval (in case of layout)File: Vruddhi-Layout Plan.pdf19 Oct 2018
Copy of Layout Approval (in case of layout)File: Vruddhi-Layout.pdf19 Oct 2018
Building Plan Approval (IOD)File: Vruddhi-Plan.pdf19 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Vruddhi-Commencement Certificate.pdf19 Oct 2018
Declaration in FORM BFile: Vruddhi-Promoter Form B.pdf19 Oct 2018

Promoter's earlier projects12

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise10 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Hari ShrushtiOpp IT Park Wadala Road indira Nagar Nashik 42221450CompletedJul 2015Late, Aug 2015
Hari Sneh Phase IIBehind Ashoka Universal School near IT park Nashik 42201150CompletedMay 2015Late, Jun 2015
Hari AmrutLokhande Mala Old Saikheda road Jail road Nashik 42221469CompletedJul 2014Late, Jul 2014
Hari SparshBarnes School Deolali camp Nashik-42250276CompletedMay 2014Apr 2014
Hari OmPhase INear Guru Givind Singh polytechnic college Indira Nagar Nashik 422009216CompletedOct 2013Late, Nov 2013
Hari Aangan Phase IJachak Mala Jai Bhavani Road Deolali24CompletedApr 2013Late, May 2013
Hari Sneh IBehind Ashoka universal School near IT park Nashik42201150CompletedDec 2012Sep 2012
Hari SankalpNear Serene Meadows Gangapur Road 42201337CompletedOct 2012Late, Nov 2012
Hari KunjJai Bhavani Road Nashik Road36CompletedSep 2012Late, Oct 2012
Hari Vandan Phase IINear Aarambh Maha Vidyalaya Sane Guruji nagar Jail Road Nashik 42210128CompletedAug 2012Late, Oct 2012
Hari Sankul Phase INear Ashoka Universal School behind Fame Multiplex Ashoka Marg Nashik 42200693CompletedDec 2011Late, May 2012
Hari NiwasBehind Muktidham near hotel Orange Tree Datta Mandir Nashik Road Nashik 42210193CompletedJul 2011Late, Sep 2011

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 48 months
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HARI VRUDDHI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nashik road4,100+ in Nashik

2 kmHARI VRUDDHICompleted 32Lapsed / revoked 7Other 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 72 registered projects within 2 km.

Builder: KBC GLOBAL LIMITED

KBC GLOBAL LIMITED has 20 registrations on MahaRERA, including HARI SPARSH II and HARI VATIKA. Its filings disclose 12 earlier MahaRERA projects: declares 2 of 12 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that HARI VRUDDHI shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if HARI VRUDDHI is delayed beyond 28 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HARI VRUDDHI?

The registered promoter entity is KBC GLOBAL LIMITED, a company as per the filing. Its CIN L45400MH2007PLC174194 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HARI VRUDDHI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HARI VRUDDHI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for HARI VRUDDHI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HARI VRUDDHI?

The professionals named in the filing: Architect: Sumit Kumath. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HARI VRUDDHI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HARI VRUDDHI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HARI VRUDDHI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.