Home / Browse projects / Nashik, Maharashtra / Hari Sanskruti Phase I
Hari Sanskruti Phase I
RG-MH-00907 · RERA P51600001194 · Last updated on MahaRERA portal: 18 Dec 2024
Source: official MahaRERA filing
Red flags
- Completion date moved by 66 months
- 5 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Hari Sanskruti Phase I is a Residential / Group Housing project by KBC GLOBAL LIMITED in Nashik, Maharashtra, registered with MahaRERA as P51600001194 on 27 Jul 2017. The registration is recorded completed; possession was promised by 31 Mar 2026. The completion date has moved by 66 months from the original filing.
At a glance
Project
- NameHari Sanskruti Phase I
- TypeResidential / Group Housing
- Location
- Deolali
- Deolaligaon
- Nashik
- 422101
- Pincode422101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600001194
- ReraGenie IDRG-MH-00907
Builder
- NameKBC GLOBAL LIMITED
- Entity typeCompany
- CINL45400MH2007PLC174194
- CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Managing DirectorNaresh Jagumal Karda
- Other registrations19 more →
- Completed6 of 20
- No longer live13 lapsed, de-registered or revoked
- Declared earlier projects12 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on27 Jul 2017
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 30 Sep 2020)
- Buildings2 building records
- Documents filed95 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING E | NA | 13 | 0 | 0 | 0 | 0 |
| BUILDING D | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 18 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 80%.
BUILDING E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING D69%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 50% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 18 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 50% |
| Podium slab | Yes | 25% |
Parking filed182
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BUILDING E | 48 | 69 | 117 |
| BUILDING D | 21 | 44 | 65 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prashant Themaskar |
| Partner | Role in project |
|---|---|
| DHARAN INFRA-EPC LIMITED | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter, Naresh Karda, Managing Director of Promoter Karda Constructions Limited, hereby confirm and declare that the construction of the project Hari Sanskruti Phase I [MAHARERA Registration Number: P51600001194] the Plot bearing Survey No.248/1 to 6/1+2+3+4 (Part) demarcated by its boundaries Adj. S. No. 249 to the North, Approved Layout No. 3/12 to the South, Approved Layout No. C-3/21 & 12M Wide Colony Road to the East, Adj. S. No. 247 & Proposed 60M D. P. Road to the West of Division Nashik, Village Deolali, Taluka Nashik, District Nashik PIN 422 101 admeasuring 6873.28 sq.mts. is in progress. A
Reason as filed by the promoterdue to some unavoidable reasons the construction of building D is not completed within the stipulated time, hence the extension is requested. There are no bookings taken in the D building.
Reason as filed by the promoterThe above project has 2 buildings i.e. Building D and Building E. Building E of the project is granted Part Occupancy Certificate. Building D is at nearing completion stage, the halt in construction activities due to labour migration and limited supply of raw materials has put forward several challenges.
Reason as filed by the promoterThe construction activity is being delayed due to unavoidable reason such as non availability of raw material.
Reason as filed by the promoterDue to unavoidable reasons
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 26 Mar 2021
Documents filed95
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: SANSKRUTI3006.pdf | 18 Dec 2024 |
| Certificates of CA (Form 3)File: Sanskruti3009.pdf | 18 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: sanskrutiform2-300924.pdf | 18 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: SANSKRUTI3006.pdf | 18 Dec 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: SANSKRUTI3006.pdf | 18 Dec 2024 |
| Declaration in FORM BFile: ACE Scanner_2024_12_12(2)_compressed.pdf | 12 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SANSKRUTI I-1-3006.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SANSKRUTI I-11-3009.pdf | 11 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SAN20-21.pdf | 11 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: soldunsold3006.pdf | 11 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: soldunsold3009.pdf | 11 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SAN21-22.pdf | 11 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SAN22-23.pdf | 11 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SAN23-24.pdf | 11 Dec 2024 |
| Certificates of CA (Form 3)File: HARI SANSKRUTI PHASE I FORM 3 30062024.pdf | 10 Dec 2024 |
| Certificates of CA (Form 3)File: HARI SANSKRUTI PHASE I FORM 3 30092024.pdf | 10 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sanskruti 2 300624.pdf | 10 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Sanskruti2a30624.pdf | 10 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2ASanskruti30924.pdf | 10 Dec 2024 |
| Declaration in FORM BFile: Hari Sanskruti-I.pdf | 2 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: HARI SANSKRUTI PHASE I.pdf | 29 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Sanskruti I.pdf | 26 Apr 2024 |
| Details of encumbrancesFile: Encumbrance certificate (1).pdf | 22 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance certificate finance.pdf | 22 Feb 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance certificate finance.pdf | 22 Feb 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank acc details.pdf | 22 Feb 2024 |
| Deviation Report with respect to Allotment letterFile: Encumbrance certificate-model allotment letter.pdf | 22 Feb 2024 |
| Deviation Report with respect to model copy of AgreementFile: Encumbrance certificate-model agreement.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Hari Sanskruti I.pdf | 17 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Hari Sanskruti I.pdf | 17 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sanskruti I.pdf | 17 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Hari Sanskruti I.pdf | 17 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sanskruti I.pdf | 17 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sanskruti I.pdf | 17 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sanskruti I.pdf | 17 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: H Sanskruti I.pdf | 20 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sanskruti I.pdf | 20 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sanskruti I.pdf | 20 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Sanskruti I.pdf | 20 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sanskruti I.pdf | 20 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sanskruti I.pdf | 20 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Sanskruti Phase I.pdf | 20 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: HARI SANSKRUTI PHASE I (1)_page-0001.pdf | 9 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: HARI SANSRUTI I.pdf | 29 Apr 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200231160163_For_Asset_Based_Search_25_02_2022_17_30_28_434.pdf | 25 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD SANSKRUTI PHASE I.pdf | 19 Feb 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sanskruti I.pdf | 22 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: HARI SANSKRUTI PHASE I.pdf | 15 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sanskruti I.pdf | 14 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sanskruti I.pdf | 14 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Sanskruti I 19-20.pdf | 13 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sanskruti I 20-21.pdf | 13 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sanskruti I.pdf | 13 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sanskruti I.pdf | 13 Oct 2021 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE-Sanskruti I.pdf | 12 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Hari sanskruti phase 1.pdf | 9 Oct 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion ,27-7-2020 (1).pdf | 26 Mar 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: Upasana RERA (1).pdf | 26 Mar 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - Hari Sanskruti I-18-19.pdf | 1 Oct 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Hari Sanskruti I_compressed.pdf | 30 Sep 2020 |
| Certificates of CA (Form 5)File: Form 5 - Hari Sanskruti Phase I_compressed.pdf | 30 Sep 2019 |
| Certificates of CA (Form 5)File: Form 5 - Hari Sanskurti Phase I-ilovepdf-compressed.pdf | 30 Sep 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sanskruti-Engineers certificate.pdf | 24 Jul 2017 |
| Layout approvalFile: SANKRUTI 1 (1).pdf | 18 Jul 2017 |
| Building plan approvalFile: SANKRUTI 1 (1).pdf | 18 Jul 2017 |
| Building plan approvalFile: SANSKRUTI 2 (1).pdf | 18 Jul 2017 |
| Building plan approvalFile: SANKRUTI 3.pdf | 18 Jul 2017 |
| Building plan approvalFile: SANKRUTI 4 (1).pdf | 18 Jul 2017 |
| Building plan approvalFile: SANSKRUTI5.pdf | 18 Jul 2017 |
| Building plan approvalFile: SANSKRUTI6.pdf | 18 Jul 2017 |
| Building plan approvalFile: SANSKRUIT7.pdf | 18 Jul 2017 |
| Building plan approvalFile: SANSKRUTI 8.pdf | 18 Jul 2017 |
| Building plan approvalFile: SANSKRUTI 9.pdf | 18 Jul 2017 |
| Building plan approvalFile: SANKRUTI 10.pdf | 18 Jul 2017 |
| Building plan approvalFile: SANSKRUTI11.pdf | 18 Jul 2017 |
| PAN CardFile: KCL.pdf | 18 Jul 2017 |
| Copy of the legal title reportFile: Sanskruti - Title report.pdf | 18 Jul 2017 |
| Details of encumbrancesFile: Sanskruti - Encumbrance Certificate.pdf | 18 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: SANKRUTI 1 (1).pdf | 18 Jul 2017 |
| Building Plan Approval (IOD)File: SANKRUTI 1 (1).pdf | 18 Jul 2017 |
Promoter's earlier projects12
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Hari Shrushti | Opp IT Park Wadala Road indira Nagar Nashik 422214 | 50 | Completed | Jul 2015 | Late, Aug 2015 |
| Hari Sneh Phase II | Behind Ashoka Universal School near IT park Nashik 422011 | 50 | Completed | May 2015 | Late, Jun 2015 |
| Hari Amrut | Lokhande Mala Old Saikheda road Jail road Nashik 422214 | 69 | Completed | Jul 2014 | Late, Jul 2014 |
| Hari Sparsh | Barnes School Deolali camp Nashik-422502 | 76 | Completed | May 2014 | Apr 2014 |
| Hari OmPhase I | Near Guru Givind Singh polytechnic college Indira Nagar Nashik 422009 | 216 | Completed | Oct 2013 | Late, Nov 2013 |
| Hari Aangan Phase I | Jachak Mala Jai Bhavani Road Deolali | 24 | Completed | Apr 2013 | Late, May 2013 |
| Hari Sneh I | Behind Ashoka universal School near IT park Nashik422011 | 50 | Completed | Dec 2012 | Sep 2012 |
| Hari Sankalp | Near Serene Meadows Gangapur Road 422013 | 37 | Completed | Oct 2012 | Late, Nov 2012 |
| Hari Kunj | Jai Bhavani Road Nashik Road | 36 | Completed | Sep 2012 | Late, Oct 2012 |
| Hari Vandan Phase II | Near Aarambh Maha Vidyalaya Sane Guruji nagar Jail Road Nashik 422101 | 28 | Completed | Aug 2012 | Late, Oct 2012 |
| Hari Sankul Phase I | Near Ashoka Universal School behind Fame Multiplex Ashoka Marg Nashik 422006 | 93 | Completed | Dec 2011 | Late, May 2012 |
| Hari Niwas | Behind Muktidham near hotel Orange Tree Datta Mandir Nashik Road Nashik 422101 | 93 | Completed | Jul 2011 | Late, Sep 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 19 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 95 filed documents as one ZIP, foldered, with a manifest
Keep Hari Sanskruti Phase I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Deolali4,100+ in Nashik
The Exchange
Viraj Estates Pvt. Ltd. & Others
HARI SANSKRUTI PHASE II
KBC GLOBAL LIMITED
ARRPAN HOUSING
A C JAIN BUILDERS AND DEVELOPERS LLP
Shilpa Madhuvan
Shilpa Estate
STAR PLUS B
DEEPAK KALYANJI CHANDE
SKY ONE
OM SAI OM BUILDERS
See every Nashik project, with the district possession charts
Builder: KBC GLOBAL LIMITED
KBC GLOBAL LIMITED has 20 registrations on MahaRERA, including HARI SPARSH II and HARI VATIKA. Its filings disclose 12 earlier MahaRERA projects: declares 2 of 12 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Hari Sanskruti Phase I is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Hari Sanskruti Phase I?
The registered promoter entity is KBC GLOBAL LIMITED, a company as per the filing. Its CIN L45400MH2007PLC174194 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Hari Sanskruti Phase I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Hari Sanskruti Phase I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Hari Sanskruti Phase I?
The professionals named in the filing: Architect: Prashant Themaskar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Hari Sanskruti Phase I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.