Home / Browse projects / Nashik, Maharashtra / HARI KUNJ MAYFLOWER
HARI KUNJ MAYFLOWER
RG-MH-63013 · RERA P51600020249 · Last updated on MahaRERA portal: 12 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 33 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HARI KUNJ MAYFLOWER is a Others project by KBC GLOBAL LIMITED in Nashik, Maharashtra, registered with MahaRERA as P51600020249 on 29 Mar 2019. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 33 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameHARI KUNJ MAYFLOWER
- TypeOthers
- Location
- NASHIK
- 422009
- Pincode422009
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600020249
- ReraGenie IDRG-MH-63013
Builder
- NameKBC GLOBAL LIMITED
- Entity typeCompany
- CINL45400MH2007PLC174194
- CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Managing DirectorNaresh Jagumal Karda
- Other registrations19 more →
- Completed6 of 20
- No longer live13 lapsed, de-registered or revoked
- Declared earlier projects12 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 Mar 2019
- Promised completion31 Dec 2023
- Revised completionRevised to 31 Dec 2023 (originally 31 Mar 2021)
- Buildings5 building records
- Documents filed90 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 7 | 0 | 0 | 0 | 0 |
| Building B | NA | 7 | 0 | 0 | 0 | 0 |
| Building C | NA | 7 | 0 | 0 | 0 | 0 |
| Building D | NA | 7 | 0 | 0 | 0 | 0 |
| Building E | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 12 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building ANot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Building BNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Building CNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Building DNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Building ENot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 12 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed54
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building A | 1 | 18 | 19 |
| Building B | 1 | 8 | 9 |
| Building C | 1 | 8 | 9 |
| Building D | 1 | 7 | 8 |
| Building E | 1 | 8 | 9 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Alka Suryavanshi | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sumit Kumath |
| Partner | Role in project |
|---|---|
| DHARAN INFRA-EPC LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTo change the completion date of project to December, 31, 2023. As per requirements of Real Estate (Regulation and Development) Act, 2016 we have taken consent from majority of allottees having booked their apartment in the project.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC001000000030271 | SWAPNIL SARODE AND OTHER 54 HARI KUNJ MAYFLOWER | M/s. KARDA CONSTRUCTION LTD. | 30/07/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Mar 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed90
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: HARI KUNJ MAYFLOWER MAR.pdf | 12 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: HARI KUNJ MAYFLOWER JUNE.pdf | 14 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: HARI KUNJ MAYFLOWER SEPT.pdf | 14 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: HARI KUNJ MAYFLOWER DEC.pdf | 14 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: HARI KUNJ MAYFLOWER.pdf | 29 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Kunj Mayflower.pdf | 26 Apr 2024 |
| Details of encumbrancesFile: Encumbrance certificate (1)_page-0001.pdf | 23 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance certificate finance_page-0001.pdf | 23 Feb 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance certificate finance_page-0001.pdf | 23 Feb 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank acc details_page-0001.pdf | 23 Feb 2024 |
| Deviation Report with respect to Allotment letterFile: Encumbrance certificate-model allotment letter_page-0001.pdf | 23 Feb 2024 |
| Deviation Report with respect to model copy of AgreementFile: Encumbrance certificate-model agreement_page-0001.pdf | 23 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Hari Kunj mayflower.pdf | 24 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: hari KunjMay Flower.pdf | 20 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Kunj Mayflower.pdf | 16 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Kunj Mayflower.pdf | 11 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: H Kunj Mayflower.pdf | 15 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Mayflower.pdf | 15 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Hari Kunj Mayflower.pdf | 17 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Kunj Mayflower.pdf | 6 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Kunj Mayflower.pdf | 6 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Kunj Mayflower.pdf | 5 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Hari Kunj Mayflower.pdf | 5 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Hari Kunj Mayflower.pdf | 24 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Hari Kunj Mayflower.pdf | 24 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: HARI KUNJ MAYFLOWER.pdf | 29 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Hari Kunj Mayflower.pdf | 21 Apr 2022 |
| Building plan approvalFile: scan0347 (2).pdf | 28 Mar 2022 |
| Building plan approvalFile: scan0348_(2).pdf | 28 Mar 2022 |
| Building plan approvalFile: scan0349_(2).pdf | 28 Mar 2022 |
| Building plan approvalFile: scan0350_(2).pdf | 28 Mar 2022 |
| Building plan approvalFile: scan0351_(2).pdf | 28 Mar 2022 |
| Building plan approvalFile: scan0353_(2).pdf | 28 Mar 2022 |
| Building Plan Approval (IOD)File: scan0347 (2).pdf | 28 Mar 2022 |
| Building Plan Approval (IOD)File: scan0348_(2).pdf | 28 Mar 2022 |
| Building Plan Approval (IOD)File: scan0349_(2).pdf | 28 Mar 2022 |
| Building Plan Approval (IOD)File: scan0350_(2).pdf | 28 Mar 2022 |
| Building Plan Approval (IOD)File: scan0351_(2).pdf | 28 Mar 2022 |
| Building Plan Approval (IOD)File: scan0353_(2).pdf | 28 Mar 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: mayflower 2A.pdf | 12 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: Hari Kunj Mayflower.pdf | 12 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: MAYFLOWER.pdf | 15 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Mayflower.pdf | 14 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Mayflower.pdf | 14 Oct 2021 |
| Form 2AFile: Mayflower.pdf | 13 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Mayflower.pdf | 13 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Mayflower.pdf | 13 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: maflowe.pdf | 9 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: hari kunj- may flower.pdf | 8 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Kunj Mayf;lower.pdf | 8 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Mayflower (4).pdf | 7 Oct 2021 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE-KUNJ.pdf | 15 Aug 2021 |
| Building plan approvalFile: KUNJ-1.pdf | 15 Apr 2021 |
| Building plan approvalFile: KUNJ-2.pdf | 15 Apr 2021 |
| Building plan approvalFile: KUNJ-3.pdf | 15 Apr 2021 |
| Building plan approvalFile: KUNJ-4.pdf | 15 Apr 2021 |
| Building Plan Approval (IOD)File: KUNJ-1.pdf | 15 Apr 2021 |
| Building Plan Approval (IOD)File: KUNJ-2.pdf | 15 Apr 2021 |
| Building Plan Approval (IOD)File: KUNJ-3.pdf | 15 Apr 2021 |
| Building Plan Approval (IOD)File: KUNJ-4.pdf | 15 Apr 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement 26-3-2021.pdf | 15 Apr 2021 |
| Building plan approvalFile: New Revised Plan (1)-2_compressed.pdf | 15 Dec 2020 |
| Building plan approvalFile: New Revised Plan (1)-1.pdf | 15 Dec 2020 |
| Building Plan Approval (IOD)File: New Revised Plan (1)-1.pdf | 15 Dec 2020 |
| Building Plan Approval (IOD)File: New Revised Plan (1)-2_compressed.pdf | 15 Dec 2020 |
| Building plan approvalFile: Plans -1.pdf | 19 Oct 2020 |
| Building plan approvalFile: Plans -2.pdf | 19 Oct 2020 |
| Building plan approvalFile: Plans -3.pdf | 19 Oct 2020 |
| Building Plan Approval (IOD)File: Plans -1.pdf | 19 Oct 2020 |
| Building Plan Approval (IOD)File: Plans -2.pdf | 19 Oct 2020 |
| Building Plan Approval (IOD)File: Plans -3.pdf | 19 Oct 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Hari Kunj MayFlower_compressed.pdf | 30 Sep 2020 |
| Form 2AFile: Form 2A mayflower.pdf | 24 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5)File: Form 5 - Hari Kunj Mayflower_compressed.pdf | 30 Sep 2019 |
| Form 2AFile: Kunj mayflower-FORM 2A.pdf | 15 May 2019 |
| Declaration in FORM BFile: Form B PROMOTER.pdf | 26 Mar 2019 |
| Layout approvalFile: Layout.pdf | 14 Mar 2019 |
| Building plan approvalFile: Building Plan-1-2.pdf | 14 Mar 2019 |
| Building plan approvalFile: Building Plan-3-4-1.pdf | 14 Mar 2019 |
| Building plan approvalFile: Building Plan-3-4-2.pdf | 14 Mar 2019 |
Promoter's earlier projects12
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Hari Shrushti | Opp IT Park Wadala Road indira Nagar Nashik 422214 | 50 | Completed | Jul 2015 | Late, Aug 2015 |
| Hari Sneh Phase II | Behind Ashoka Universal School near IT park Nashik 422011 | 50 | Completed | May 2015 | Late, Jun 2015 |
| Hari Amrut | Lokhande Mala Old Saikheda road Jail road Nashik 422214 | 69 | Completed | Jul 2014 | Late, Jul 2014 |
| Hari Sparsh | Barnes School Deolali camp Nashik-422502 | 76 | Completed | May 2014 | Apr 2014 |
| Hari OmPhase I | Near Guru Givind Singh polytechnic college Indira Nagar Nashik 422009 | 216 | Completed | Oct 2013 | Late, Nov 2013 |
| Hari Aangan Phase I | Jachak Mala Jai Bhavani Road Deolali | 24 | Completed | Apr 2013 | Late, May 2013 |
| Hari Sneh I | Behind Ashoka universal School near IT park Nashik422011 | 50 | Completed | Dec 2012 | Sep 2012 |
| Hari Sankalp | Near Serene Meadows Gangapur Road 422013 | 37 | Completed | Oct 2012 | Late, Nov 2012 |
| Hari Kunj | Jai Bhavani Road Nashik Road | 36 | Completed | Sep 2012 | Late, Oct 2012 |
| Hari Vandan Phase II | Near Aarambh Maha Vidyalaya Sane Guruji nagar Jail Road Nashik 422101 | 28 | Completed | Aug 2012 | Late, Oct 2012 |
| Hari Sankul Phase I | Near Ashoka Universal School behind Fame Multiplex Ashoka Marg Nashik 422006 | 93 | Completed | Dec 2011 | Late, May 2012 |
| Hari Niwas | Behind Muktidham near hotel Orange Tree Datta Mandir Nashik Road Nashik 422101 | 93 | Completed | Jul 2011 | Late, Sep 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 19 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 90 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep HARI KUNJ MAYFLOWER on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NASHIK4,100+ in Nashik
Filed coordinates, straight-line distance. 286 registered projects within 2 km.
STAR WORLD
DEEPAK KALYANJI CHANDE
VRAJ CENTRAL VISTA
DHAIRYA DEVELOPERS
ROONGTA TECHONE APARTMENT
SHREE TIRUMALA BUILDCON
VRAJ CAPITAL
KAPILAVASTU CREATORS
MAA BHAGWATI RESIDENCY APARTMENT
ROONGTA LANDMARKS LLP
THREE LEAVES PHASE ONE
DEEPAK INFRA AND HOMES PRIVATE LIMITED
See every Nashik project, with the district possession charts
Builder: KBC GLOBAL LIMITED
KBC GLOBAL LIMITED has 20 registrations on MahaRERA, including HARI SPARSH II and HARI VATIKA. Its filings disclose 12 earlier MahaRERA projects: declares 2 of 12 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What does it mean that HARI KUNJ MAYFLOWER shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if HARI KUNJ MAYFLOWER is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HARI KUNJ MAYFLOWER?
The registered promoter entity is KBC GLOBAL LIMITED, a company as per the filing. Its CIN L45400MH2007PLC174194 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HARI KUNJ MAYFLOWER?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against HARI KUNJ MAYFLOWER?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for HARI KUNJ MAYFLOWER?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HARI KUNJ MAYFLOWER?
The professionals named in the filing: Architect: Sumit Kumath. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HARI KUNJ MAYFLOWER?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback