Red flags

  • 16 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Staircases, 97%
16Complaints at MahaRERAon this registration
Jump to the 117 documents Report an error

KANAKIA SEVENS is a Residential / Group Housing project by KANAKIA SPACES REALTY PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000388 on 15 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. 16 complaints are on record with the regulator.

At a glance

Project

  • NameKANAKIA SEVENS
  • TypeResidential / Group Housing
  • Location
    • Andheri
    • Mumbai Suburban
    • 400059
  • Pincode400059
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000388
  • ReraGenie IDRG-MH-07985

Builder

  • NameKANAKIA SPACES REALTY PRIVATE LIMITED
  • Entity typeCompany
  • CINU70109MH2019PTC331509
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsRasesh Babubhai Kanakia, Himanshu Babubhai Kanakia
  • Other registrations10 more →
  • Completed11 of 11
  • Declared earlier projects15 →

Key dates

this monthRegisteredJul 2017PromisedDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Jul 2017
  • Promised completion30 Dec 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed117 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KANAKIA SEVENSNA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 97%.

KANAKIA SEVENS: 85% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.94%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.93%

Progress on shared amenities16

As on 1 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingYes20%
Community BuildingsYes90%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes63%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes73%
Open ParkingYes73%
OTHERSYes10%

Parking filed310

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots310
Closed/Covered309
Open Space1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,184 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NEW MONARCH BUILDERS & CONTRACTORSAndheriMumbai Suburban

Approvals and building plan

Permissible FSI40486.17
Proposed, not sanctioned34,142 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKALPATARU ESTATE BUILDING NO 1 JOGESHWARI VIKHROLI LINK ROAD ANDHERI EAST MUMBAI 400093

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr. Rushikesh Hadnoorkar
ArchitectMr. JITU PATEL
ArchitectMR. AMOD SHEVDE
EngineerMr. Nikhil Shanghvi
EngineerMR CHARUDATTA V SAMANT
PartnerRole in project
KANAKIA SPACES REALTY PRIVATE LIMITED-

Litigation declared24

CaseCourtStatus
581/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER PREMISES
578/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
577/2019Additional CollectorPENDING FOR HEARING PERTAINING TO CO PROMOTER
579/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
456/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
454/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
459/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
455/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
450/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
451/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
458/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
449/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
457/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
452/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
453/2019Additional CollectorCASE REJECTED PERTAINING TO CO PROMOTER
575/2019Additional CollectorPENDING FOR HEARING PERTAINING TO CO PROMOTER
571/2019Additional CollectorPENDING FOR HEARING PERTAINING TO CO PROMOTER
569/2019Additional CollectorPENDING FOR HEARING PERTAINING TO CO PROMOTER
570/2019Additional CollectorPENDING FOR HEARING PERTAINING TO CO PROMOTER
572/2019Additional CollectorPENDING FOR HEARING PERTAINING TO CO PROMOTER
573/2019Additional CollectorPENDING FOR HEARING PERTAINING TO CO PROMOTER
574/2019Additional CollectorPENDING FOR HEARING PERTAINING TO CO PROMOTER
576/2019Additional CollectorPENDING FOR HEARING PERTAINING TO CO PROMOTER
4417/2019CITY CIVIL COURTPENDING FOR HEARING PERTAINING TO CO PROMOTER

Complaints filed with MahaRERA16

Case no.ComplainantRespondentFiled
CC006000000000726Meenal Gupta & Anshul BaranwalKanakia Spaces Realty Private Limited15/01/2018
CC006000000078222Chandrakala Yadvendra BangeraRahul Dubey23/02/2019
CC006000000194985Vijay Kanekar and Kamini KanekarKanakia Spaces Realty Private Limited23/11/2020
CC006000000195713Delishea Clyde CardozNew Monarch Builders & Contractors & Kanakia Spaces Realty Private Limited21/01/2021
CC006000000195877DARSHNA RAMESH HINGU AND RAMESH MADHAVJI HINGUKANAKIA SPACES REALTY PVT LTD04/02/2021
CC006000000196585Kanakia Spaces Realty Private LimitedMr V. Radhakrinshna18/04/2021
CC006000000196586Kanakia Spaces Realty Private LimitedMrs. Parveen Shabnam Khan18/04/2021
CC006000000196587Kanakia Spaces Realty Private LimitedMr. Jawhar Prasad30/04/2021
CC006000000251483Mehul Ashok Kumar ShahKanakia Spaces Realty Private Limited & Ors.15/06/2022
CC006000000395819kanakiya seven CHs LtdKanakia Spaces Realty Pvt.Ltd16/05/2023
CC006000000591570kanakiya seven CHs LtdKanakia spaces Reality Pvt Ltd,16/08/2024
CC006000000397569Sangeeta Subodh KediaKANAKIA SPACES REALTY PRIVATE LIMITED23/09/2023
CC006000000591272AMIT KAMLAKAR ZALTEM/s. Kanakia Spaces Realty Pvt Ltd22/07/2024
CC12400694KANAKIA SPACES REALTY PRIVATE LIMITEDAnkita Jain Wife of Nikhil Sinha07/11/2024
CC12501794M G MohammadKANAKIA SPACES REALTY PRIVATE LIMITED30/05/2025
CC12503847Samprati MotghareKANAKIA SPACES REALTY PRIVATE LIMITED02/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Feb 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Feb 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Nov 2020

Documents filed117

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of ConveyanceFile: RERA LETTER SEVENS Compressed.pdf1 Jul 2024
Status of ConveyanceFile: mail asking docs for execution of sevens conveyance.pdf10 Feb 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Sevens Society Certificate.pdf3 Feb 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Sevens Society Certificate.pdf3 Feb 2022
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf3 Dec 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full Occupation Certificate - Sevens.pdf4 Nov 2020
OtherFile: Full Occupation Certificate - Sevens.pdf4 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Sevens.pdf8 Jul 2020
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf7 Mar 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate 19th Floor Wing ABCD.pdf28 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Sevens Quality Assurance Certificate.pdf19 Feb 2020
Certificates of CA (Form 5)File: sevens.pdf7 Sep 2019
Certificates of CA (Form 3)File: CA Cert Sevens 30062019.pdf22 Aug 2019
Details of encumbrancesFile: JM Finance 50 Crs Sevens.pdf21 Aug 2019
Certificates of CA (Form 3)File: Sevens RERA Certificate 28022019.pdf21 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sevens Arch Certificate 3062019.pdf8 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sevens Architect Certificate 310319.pdf8 Jul 2019
OtherFile: Sevens Part OC till 18th floor.pdf1 Feb 2019
Certificates of CA (Form 3)File: Kanakia Sevens 22 January 2019.pdf29 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Sevens 31-12-18.pdf15 Jan 2019
Details of encumbrancesFile: Sevens - Index II.pdf17 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: CC_30-10-2018_SEVENS.pdf20 Nov 2018
Certificates of CA (Form 3)File: Sevens 03 October 2018.pdf6 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Severns rera certificate date 30-9-2018 Scan0007.pdf23 Oct 2018
Certificates of CA (Form 5)File: Form 5 Sevens RERA Registration no P51800000388.pdf29 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SEVENS ARCHITECT CERTIFICATE.pdf22 Aug 2018
Certificates of CA (Form 3)File: Sevens CA Certificate.pdf22 Aug 2018
Commencement Certificates / NA Order for plotted developmentFile: SEVENS CC 21 03 2018.pdf25 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Sevens.pdf15 Jun 2018
Certificates of CA (Form 3)File: Sevens Cost Certificate.pdf11 May 2018
Building plan approvalFile: Layout AND Letter.pdf21 Feb 2018
Building plan approvalFile: Sheet No-2-3.pdf21 Feb 2018
Layout approvalFile: Layout AND Letter.pdf21 Feb 2018
Building plan approvalFile: Sheet No-4-5-6.pdf21 Feb 2018
Building plan approvalFile: Sheet No-7-8-9-10.pdf21 Feb 2018
Building plan approvalFile: Sheet No-11-12-13-14.pdf21 Feb 2018
Building plan approvalFile: Sheet No-15-16-17-18.pdf21 Feb 2018
Building plan approvalFile: Sheet No-19-20.pdf21 Feb 2018
Building plan approvalFile: Sheet No-23-24.pdf21 Feb 2018
Building plan approvalFile: Sheet No-25-26.pdf21 Feb 2018
Layout approvalFile: Sheet No - 2,3,4,5, 6.pdf21 Feb 2018
Building plan approvalFile: Sheet No - 7,8,9, 10.pdf21 Feb 2018
Building plan approvalFile: Sheet No - 11,12,13,14, 15.pdf21 Feb 2018
Building plan approvalFile: Sheet No - 16,17,18,19, 20.pdf21 Feb 2018
Building plan approvalFile: Sheet No - 16,17,18,19, 20.pdf21 Feb 2018
Building plan approvalFile: Sheet No - 16,17,18,19, 20.pdf21 Feb 2018
Building plan approvalFile: Sheet No - 21,22,23, 24.pdf21 Feb 2018
Building plan approvalFile: Sheet No - 25,26,27, 28.pdf21 Feb 2018
Building plan approvalFile: Sheet No - 29,30, 31.pdf21 Feb 2018
Details of encumbrancesFile: Sevens 25 Crores Index II.pdf21 Feb 2018
Copy of Layout Approval (in case of layout)File: Layout AND Letter.pdf21 Feb 2018
Copy of Layout Approval (in case of layout)File: Sheet No - 2,3,4,5, 6.pdf21 Feb 2018
Building Plan Approval (IOD)File: Layout AND Letter.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-2-3.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-4-5-6.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-7-8-9-10.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-11-12-13-14.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-15-16-17-18.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-19-20.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-23-24.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-25-26.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No - 7,8,9, 10.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No - 11,12,13,14, 15.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No - 16,17,18,19, 20.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No - 16,17,18,19, 20.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No - 16,17,18,19, 20.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No - 21,22,23, 24.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No - 25,26,27, 28.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No - 29,30, 31.pdf21 Feb 2018
Certificates of CA (Form 3)File: Sevens 31 December 2017.pdf21 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sevens Architect Certificate 31 12 2017.pdf20 Feb 2018
Details of encumbrancesFile: SEVENS INDEX II.pdf26 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: Sevens CC.pdf26 Oct 2017
Certificates of CA (Form 3)File: Sevens- CA Certificate.pdf24 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate kanakia sevens.pdf29 Sep 2017
Copy of the legal title reportFile: Title Kanakia Sevens.pdf7 Jul 2017
Layout approvalFile: Binder1.pdf6 Jul 2017
Building plan approvalFile: Binder3.pdf6 Jul 2017
Building plan approvalFile: Binder4.pdf6 Jul 2017
Building plan approvalFile: Binder5.pdf6 Jul 2017

Promoter's earlier projects12

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise8 delivered late
ProjectLocationFlatsStatusPromisedDelivered
KANAKIA MIAMIPlot No 766 Junction of Causeway Mori Road Mahim W Mumbai 40001647CompletedSep 2018Late, Nov 2019
WALL STREET WING BCHAKALA ANDHERI KURLA ROAD ANDHERI EAST MUMBAI 400093211CompletedDec 2017Mar 2017
KANAKIA AROHADATTAPADA ROAD DONGRI OFF VILLAGE KANHERI NEAR LOHANA MARRIAGE HALL BORIVALI EAST MUMBAI 400066183CompletedDec 2017Mar 2017
ZILLION PHASE 2LBS ROAD JUNCTION CST ROAD BKC ANNEXE MUMBAI 400070107CompletedDec 2016Late, Jan 2017
BOOMERANG PHASE 2MAIN CHANDIVALI FARM ROAD NEAR POWAI ANDHERI EAST MUMBAI 40007256CompletedJun 2015Late, May 2016
ZILLION PHASE 1LBS ROAD JUNCTION CST ROAD BKC ANNEXE MUMBAI 400070100CompletedDec 2014Aug 2014
ATRIUM IINEXT TO 215 ATRIUM BEHIND COURTYARD MARRIOT ANDHERI KURLA ROAD ANDHERI EAST MUMBAI 40009364CompletedDec 2014Late, Jan 2015
SAMARPAN EXCOTICAWESTERN EXPRESS HIGHWAY BORIVALI EAST MUMBAI 400066189CompletedApr 2014Late, Jun 2014
351 ICONWETSERN EXPRESS HIGHWAY ANDHERI EAST MUMBAI 4000699CompletedSep 2013Jul 2013
ANANTABEVERLY PARK MIRA ROAD EAST THANE 40110756CompletedJun 2012Late, Dec 2012
WESTERN EDGE IIWESTERN EXPRESS HIGHWAY BORIVALI EAST MUMBAI 400066152CompletedDec 2011Late, Jul 2012
BOOMERANG PHASE 1MAIN CHANDIVALI FARM ROAD NEAR POWAI ANDHERI EAST MUMBAI 400072159CompletedApr 2010Late, Aug 2010

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KANAKIA SEVENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri6,700+ in Mumbai Suburban

2 kmKANAKIA SEVENSCompleted 106Lapsed / revoked 56Other 66Dot size: filed unitsN

Filed coordinates, straight-line distance. 228 registered projects within 2 km.

Builder: KANAKIA SPACES REALTY PRIVATE LIMITED

KANAKIA SPACES REALTY PRIVATE LIMITED has 11 registrations on MahaRERA, including KANAKIA MIAMI and KANAKIA WALLSTREET WING A. Its filings disclose 15 earlier MahaRERA projects: declares 5 of 15 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if KANAKIA SEVENS is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KANAKIA SEVENS?

The registered promoter entity is KANAKIA SPACES REALTY PRIVATE LIMITED, a company as per the filing. Its CIN U70109MH2019PTC331509 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KANAKIA SEVENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KANAKIA SEVENS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KANAKIA SEVENS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KANAKIA SEVENS?

The professionals named in the filing: Architect: Mr. Rushikesh Hadnoorkar; Architect: Mr. JITU PATEL; Architect: MR. AMOD SHEVDE; Engineer: Mr. Nikhil Shanghvi; Engineer: MR CHARUDATTA V SAMANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KANAKIA SEVENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KANAKIA SEVENS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KANAKIA SEVENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.