Home / Browse projects / Mumbai Suburban, Maharashtra / KANAKIA ZENWORLD PHASE I

Completed No litigation declared Residential / Group Housing project

KANAKIA ZENWORLD PHASE I

By KANAKIA SPACES REALTY PRIVATE LIMITED

RG-MH-25700 · RERA P51800008343 · Last updated on MahaRERA portal: 31 Mar 2023

Source: official MahaRERA filing

Red flags

  • 12 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2023Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 10%
12Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

KANAKIA ZENWORLD PHASE I is a Residential / Group Housing project by KANAKIA SPACES REALTY PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008343 on 18 Aug 2017. The registration is recorded completed; possession was promised by 30 Mar 2023. 12 complaints are on record with the regulator.

At a glance

Project

  • NameKANAKIA ZENWORLD PHASE I
  • TypeResidential / Group Housing
  • Location
    • KANJURMARG
    • Kurla
    • Mumbai Suburban
    • 400042
  • Pincode400042
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008343
  • ReraGenie IDRG-MH-25700

Builder

  • NameKANAKIA SPACES REALTY PRIVATE LIMITED
  • Entity typeCompany
  • CINU70109MH2019PTC331509
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsRasesh Babubhai Kanakia, Himanshu Babubhai Kanakia
  • Other registrations10 more →
  • Completed11 of 11
  • Declared earlier projects15 →

Key dates

this monthRegisteredAug 2017PromisedMar 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Aug 2017
  • Promised completion30 Mar 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed101 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KANAKIA ZENWORLD PHASE INA250000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 10%.

KANAKIA ZENWORLD PHASE I: 83% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 31 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes14%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes44%
Open ParkingYes44%
OTHERSYes0%

Parking filed438

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots438
Closed/Covered350
Open Space88

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,905 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI25554.14
Proposed, not sanctioned25,554 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch349 BUSINESS POINT BLDG ANDHERI EAST MUMBAI 400069

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Ajay Sawant
ArchitectMr.ManojKumar Dubal
ArchitectMr. Harsh Pote
EngineerMr. Charudatta V. Samant
EngineerMr. Watve
PartnerRole in project
KANAKIA SPACES REALTY PRIVATE LIMITED-

Litigation declared1

CaseCourtStatus
474/2017SUPERINTENDENT OF LAND RECORDSMATTER DISPOSED OFF

Complaints filed with MahaRERA12

Case no.ComplainantRespondentFiled
CC006000000079462Mr. Swatantrakumar GuptaKanakia Space Realty Private Limited27/05/2019
CC006000000171512Prasad WaingankarKapil Advani21/11/2019
CC006000000195363PRADEEP GAIKWADKanakia Spaces Realty Private Limted24/12/2020
CC006000000210424Prakash Dattaram KorgaonkarKanakia Spaces Realty Pvt. Ltd.28/03/2022
CC006000000375272KANAKIA SPACES REALTY PVT LTDDEVEN BHARAT BHATT12/05/2023
CC006000000396459Kanakia Spaces Realty Private LimitedMr. Jameel Dawood Parkar And another28/06/2023
CC006000000396460Kanakia Spaces Realty Private LimitedMr. Vilas B. Kale28/06/2023
CC006000000396660Kanakia Spaces Realty Private LimitedAshok Narendra Rach17/07/2023
CC006000000396720Kanakia Spaces Realty Private LimitedAshok Narendra Rach17/07/2023
CC006000000396721Kanakia Spaces Realty Private LimitedSachita and Vishad Keer17/07/2023
CC12400695KANAKIA SPACES REALTY PRIVATE LIMITEDASHOK NARENDRA RACH07/11/2024
CC12600171KANAKIA SPACES REALTY PRIVATE LIMITEDMR DEVEN BHARAT BHATT10/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Feb 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Nov 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Feb 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Mar 2023

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: Kanakia Zenworld Form 5.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Kanakia Zenworld Form 5.pdf2 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf2 Mar 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Kanakia Zenworld Phase I.pdf2 Mar 2023
Disclosure of sold/ booked inventoryFile: Kanakia Zenworld A to E wing.pdf5 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Zenworld Phase I.pdf9 Mar 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate.pdf10 Nov 2020
OtherFile: Occupation Certificate.pdf10 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Zenworld.pdf8 Jul 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Zen I Quality Assurance Certificate.pdf19 Feb 2020
Certificates of CA (Form 5)File: zenworld phase I.pdf7 Sep 2019
Certificates of CA (Form 3)File: CA Cert Zenworld 30062019.pdf26 Aug 2019
Certificates of CA (Form 3)File: Zenworld RERA Cert 28022019.pdf22 Aug 2019
Certificates of CA (Form 3)File: Zenworld RERA Cert 31122018.pdf21 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Zenworld Arch Certificate 3062019.pdf8 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Zenworld Arch Certificate 3062019.pdf8 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Zenworld Architecture Certifcate.pdf8 Jul 2019
Details of encumbrancesFile: 01-Zenworld -Index-II.pdf6 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Zenworld 31-12-18.pdf15 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Zenworld A to E.pdf19 Nov 2018
Certificates of CA (Form 5)File: Form 5 Zenworld RERA Registration no P51800008343.pdf29 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: ZENWORLD Further CC 21 08 2018.pdf11 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ZENWORLD AC 30 06 2018.pdf4 Sep 2018
Certificates of CA (Form 3)File: ZenWorld CA Certificate.pdf22 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_ZEN.pdf23 Jul 2018
Certificates of CA (Form 3)File: Zenworld Cost Certificate.pdf11 May 2018
Building plan approvalFile: Layout AND Letter.pdf21 Feb 2018
Building plan approvalFile: Sheet No-2-3.pdf21 Feb 2018
Building plan approvalFile: Sheet No-4-5-6.pdf21 Feb 2018
Building plan approvalFile: Sheet No-7-8-9-10.pdf21 Feb 2018
Building plan approvalFile: Sheet No-7-8-9-10.pdf21 Feb 2018
Building plan approvalFile: Sheet No-11-12-13-14.pdf21 Feb 2018
Building plan approvalFile: Sheet No-15-16-17-18.pdf21 Feb 2018
Building plan approvalFile: Sheet No-19-20.pdf21 Feb 2018
Building plan approvalFile: Sheet No-23-24.pdf21 Feb 2018
Building plan approvalFile: Sheet No-25-26.pdf21 Feb 2018
Copy of the legal title reportFile: Sheet No-4-5-6.pdf21 Feb 2018
Building Plan Approval (IOD)File: Layout AND Letter.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-2-3.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-4-5-6.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-7-8-9-10.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-7-8-9-10.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-11-12-13-14.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-15-16-17-18.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-19-20.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-23-24.pdf21 Feb 2018
Building Plan Approval (IOD)File: Sheet No-25-26.pdf21 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: ZENWORLD CC 03 02 2018.pdf21 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Zen wolrd Architect Certificate 31 12 2017.pdf20 Feb 2018
Certificates of CA (Form 3)File: Kanakia Zenworld 31 Dece 2017.pdf20 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: ZEN CC 30 NOV 2017.pdf30 Nov 2017
Layout approvalFile: Layout and Letter.pdf15 Nov 2017
Building plan approvalFile: Sheet No 2 and 3.pdf15 Nov 2017
Building plan approvalFile: Sheet No 4 and 5.pdf15 Nov 2017
Building plan approvalFile: Sheet No 6 and 7.pdf15 Nov 2017
Building plan approvalFile: Sheet No 8 and 9.pdf15 Nov 2017
Building plan approvalFile: Sheet No 10 and 11.pdf15 Nov 2017
Building plan approvalFile: Sheet No 12 and 13.pdf15 Nov 2017
Building plan approvalFile: Sheet No 14 and 15.pdf15 Nov 2017
Building plan approvalFile: Sheet No 16.pdf15 Nov 2017
Building plan approvalFile: Sheet No 17 and 18 and 19.pdf15 Nov 2017
Building plan approvalFile: Sheet No 20.pdf15 Nov 2017
Building plan approvalFile: Sheet No 21 and 22 and 23.pdf15 Nov 2017
Copy of Layout Approval (in case of layout)File: Layout and Letter.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 2 and 3.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 4 and 5.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 6 and 7.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 8 and 9.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 10 and 11.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 12 and 13.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 14 and 15.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 16.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 17 and 18 and 19.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 20.pdf15 Nov 2017
Building Plan Approval (IOD)File: Sheet No 21 and 22 and 23.pdf15 Nov 2017
Commencement Certificates / NA Order for plotted developmentFile: Kanjur CC.pdf26 Oct 2017
Certificates of CA (Form 3)File: Zenworld Phase I - CA CertificatE.pdf24 Oct 2017
Copy of the legal title reportFile: Kanjurmarg Title Report.pdf29 Jul 2017
Declaration in FORM BFile: FORM B ZEN WORLD PART 2.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE ZEN WORLD.pdf29 Jul 2017

Promoter's earlier projects12

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise8 delivered late
ProjectLocationFlatsStatusPromisedDelivered
KANAKIA MIAMIPlot No 766 Junction of Causeway Mori Road Mahim W Mumbai 40001647CompletedSep 2018Late, Nov 2019
WALL STREET WING BCHAKALA ANDHERI KURLA ROAD ANDHERI EAST MUMBAI 400093211CompletedDec 2017Mar 2017
KANAKIA AROHADATTAPADA ROAD DONGRI OFF VILLAGE KANHERI NEAR LOHANA MARRIAGE HALL BORIVALI EAST MUMBAI 400066183CompletedDec 2017Mar 2017
ZILLION PHASE 2LBS ROAD JUNCTION CST ROAD BKC ANNEXE MUMBAI 400070107CompletedDec 2016Late, Jan 2017
BOOMERANG PHASE 2MAIN CHANDIVALI FARM ROAD NEAR POWAI ANDHERI EAST MUMBAI 40007256CompletedJun 2015Late, May 2016
ZILLION PHASE 1LBS ROAD JUNCTION CST ROAD BKC ANNEXE MUMBAI 400070100CompletedDec 2014Aug 2014
ATRIUM IINEXT TO 215 ATRIUM BEHIND COURTYARD MARRIOT ANDHERI KURLA ROAD ANDHERI EAST MUMBAI 40009364CompletedDec 2014Late, Jan 2015
SAMARPAN EXCOTICAWESTERN EXPRESS HIGHWAY BORIVALI EAST MUMBAI 400066189CompletedApr 2014Late, Jun 2014
351 ICONWETSERN EXPRESS HIGHWAY ANDHERI EAST MUMBAI 4000699CompletedSep 2013Jul 2013
ANANTABEVERLY PARK MIRA ROAD EAST THANE 40110756CompletedJun 2012Late, Dec 2012
WESTERN EDGE IIWESTERN EXPRESS HIGHWAY BORIVALI EAST MUMBAI 400066152CompletedDec 2011Late, Jul 2012
BOOMERANG PHASE 1MAIN CHANDIVALI FARM ROAD NEAR POWAI ANDHERI EAST MUMBAI 400072159CompletedApr 2010Late, Aug 2010

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KANAKIA ZENWORLD PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANJURMARG6,700+ in Mumbai Suburban

2 kmKANAKIA ZENWORLD PHASE ICompleted 38Lapsed / revoked 33Other 113Dot size: filed unitsN

Filed coordinates, straight-line distance. 184 registered projects within 2 km.

Builder: KANAKIA SPACES REALTY PRIVATE LIMITED

KANAKIA SPACES REALTY PRIVATE LIMITED has 11 registrations on MahaRERA, including KANAKIA MIAMI and KANAKIA WALLSTREET WING A. Its filings disclose 15 earlier MahaRERA projects: declares 5 of 15 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if KANAKIA ZENWORLD PHASE I is delayed beyond 30 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KANAKIA ZENWORLD PHASE I?

The registered promoter entity is KANAKIA SPACES REALTY PRIVATE LIMITED, a company as per the filing. Its CIN U70109MH2019PTC331509 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KANAKIA ZENWORLD PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KANAKIA ZENWORLD PHASE I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KANAKIA ZENWORLD PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KANAKIA ZENWORLD PHASE I?

The professionals named in the filing: Architect: Mr Ajay Sawant; Architect: Mr.ManojKumar Dubal; Architect: Mr. Harsh Pote; Engineer: Mr. Charudatta V. Samant; Engineer: Mr. Watve. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KANAKIA ZENWORLD PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KANAKIA ZENWORLD PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KANAKIA ZENWORLD PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.