Home / Developers / City Corporation Limited
City Corporation Limited: RERA track record
CIN U45202PN2003PLC018435 · Company · attribution by exact filing name, entity resolution in progress
City Corporation Limited has 13 registrations on MahaRERA, including Amanora Gateway Towers 98 and 99 and Amanora Gateway Tower 100. Its filings disclose 8 earlier MahaRERA projects: declares 8 of 8 past projects completed on time.
Projects by this developer
Showing all 13 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Amanora Arbano Towers 73,74,75 and 76P52100052019 | Amanora Park Town, Pune, 411028 | 843 | 98% | 19 Jul 2023 | Registered |
| Amanora Gateway Towers 2 - Towers 102 and 103P52100079477 | Amanora Park Town, Pune, 411028 | 340 | 61% | 7 Mar 2025 | Registered |
| Amanora Arbano Towers 71 and 72P52100052614 | Amanora Park Town, Pune, 411028 | 229 | 98% | 11 Sep 2023 | Registered |
| Amanora Elevate Tower 47P52100032079 | Amanora Park Town, Pune, 411028 | 225 | 100% | 3 Dec 2021 | Completed |
| Amanora Gateway Towers 2 - Tower 101PR1261012500749 | Amanora Park Town, Pune, 411028 | 170 | 34% | 10 Sep 2025 | Registered |
| Amanora Ascent AvenueP52100047453 | Hadapsar, Pune, 411028 | 131 | 69% | 31 Oct 2022 | Completed |
| Amanora Sweet Water Villa PlotsP52100004890 | Amanora Park Town, Pune, 411028 | 88 | 82% | 9 Aug 2017 | Completed |
| Amanora Adreno TowersP52100001822 | Amanora Park Town, Pune, 411028 | - | - | 29 Jul 2017 | Completed |
| Amanora Ascent Towers 48 and 49P52100030032 | Amanora Park Town, Pune, 411028 | - | - | 26 Jul 2021 | Completed |
| Amanora Gateway Tower 100P52100000380 | Amanora Park Town, Pune, 411028 | - | - | 15 Jul 2017 | Completed |
| Amanora Gateway Towers 98 and 99P52100000321 | Amanora Park Town, Pune, 411028 | - | - | 15 Jul 2017 | Completed |
| Amanora Gold Towers 42 and 43P52100017612 | Amanora Park Town, Pune, 411028 | - | - | 29 Aug 2018 | Completed |
| Amanora Gold Towers 44, 45 and 46P52100017962 | Amanora Park Town, Pune, 411028 | - | - | 1 Oct 2018 | Completed |
What this promoter declares as its own experience
City Corporation Limited declares experience on 8 earlier projects. 6 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
6 of these declarations can be compared with the dates those projects' own registrations hold. On 1, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on 1 of the 6 completions recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Amanora Aspire Towers, Sector R3 | 15 Nov 2016 | 15 Oct 2016 | On time |
| Amanora Future Tower, Sector R11 | 15 Mar 2017 | 9 Feb 2017 | On time |
| Amanora Gateway Towers 98 and 99 P52100000321 | 31 Dec 2018 | 31 Dec 2018 | On time |
| Amanora Adreno Towers P52100001822 | 30 Mar 2022 | 5 Jan 2022 | On time |
| Amanora Gateway Tower 100 P52100000380 | 29 Apr 2022 | 29 Apr 2022 | On time |
| Amanora Gold Towers 42 and 43 P52100017612 | 30 Dec 2023 | 7 Jun 2023 | On time |
| Amanora Gold Towers 44, 45 and 46 P52100017962 | 30 May 2024 | 21 May 2024 | On time |
| Amanora Ascent Towers 48 and 49 P52100030032 | 30 Sep 2025 | 21 Oct 2024 | On time |
Frequently asked questions
How do I verify City Corporation Limited as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45202PN2003PLC018435 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with City Corporation Limited?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.