New projects and RERA data in Gandhinagar district, Gujarat
1660 projects are registered in Gandhinagar district: 205,777 units across them, 145 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 1660 covered registrations, 267 have revised their promised completion date. The median project here is 53% booked as of the current data. Every figure comes from the projects' own GujRERA filings.
How far Gandhinagar possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 267 of 1,660 projects (16%) have moved at least once; the median move is 12 months and the longest is 72 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Where in Gandhinagar: projects by taluka
1,660 of the 1,660 registrations on this page name their taluka.
| Taluka | Projects | Share |
|---|---|---|
| Gandhinagar | 1,429 | 86% |
| Kalol | 109 | 7% |
| 5 other talukas | 122 | 7% |
Projects in Gandhinagar
Showing 1 to 60 of 1,660 projects.
Largest first, by the unit count in the filing.
| Project | Developer | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| SIBANPirojpur Gandhinagar, 382355 | UNITED YOGI LLP | 1668 | 52% | 31 Dec 2024 | Valid until 30 Apr 2031 |
| AMBA TOWNSHIP SECTOR 4 Part A - Phase 1Adalaj, 382422 | AMBA TOWNSHIP PRIVATE LIMITED | 1364 | 0% | 18 Dec 2017 | Valid until 19 Jun 2018 |
| TPS 09 FP 175 EWS II | GANDHINAGAR URBAN DEVELOPMENT AUTHORITY | 1352 | 100% | 28 Aug 2023 | Valid until 31 Jul 2028 |
| TPS 07 FP 186 EWS II | GANDHINAGAR URBAN DEVELOPMENT AUTHORITY | 1208 | 99% | 17 Mar 2021 | Valid until 31 Jan 2025 |
| WTC GIFT Tower A, B & DRatanpur, 382355 | WTC Noida Development Company Pvt Ltd | 1188 | 98% | 21 Nov 2017 | Valid until 30 Oct 2025 |
| ZUNDAL FP 123 TP 72 | AHMEDABAD URBAN DEVELOPMENT AUTHORITY | 1132 | 91% | 17 Jun 2021 | Valid until 14 Feb 2025 |
| The IdentityRATANPUR, 382355 | RASHMII AND DOBARIYA INFRASPACE LLP | 1030 | 46% | 12 Dec 2024 | Valid until 30 Apr 2031 |
| Trogon Twin TowersKhoraj | RADHERTH VENTURE LLP | 928 | 28% | 31 Aug 2023 | Valid until 31 Jul 2027 |
| PRAMUKH ANAND ORBIT MALL | PRAMUKHANAND CORPORATION LLP | 812 | 23% | 10 Oct 2019 | Valid until 30 Jun 2025 |
| JOY | SHRINIVAS ORGANISORS PRIVATE LIMITED | 808 | 64% | 28 Feb 2022 | Valid until 31 Dec 2026 |
| AMBA TOWSHIP SECTOR 4 - PART BAdalaj, 382422 | AMBA TOWNSHIP PRIVATE LIMITED | 728 | 93% | 18 Dec 2017 | Valid until 30 Jun 2022 |
| PRANAPirojpur, 382355 | Nila Urban Living Private Limited | 703 | 26% | 10 Jul 2025 | Valid until 30 Apr 2031 |
| SHILP NORTH SKY | SHILP INFRAPROJECTS PRIVATE LIMITED | 668 | 93% | 6 Apr 2023 | Valid until 31 Jul 2028 |
| Swagat Twincity Highstreet & Swagat KingslandSargasan, 382016 | SWAGAT DEVELOPERS | 626 | 38% | 19 Jun 2019 | Valid until 30 Oct 2027 |
| TPS 09 FP 149 EWS II | GANDHINAGAR URBAN DEVELOPMENT AUTHORITY | 624 | 100% | 24 Aug 2023 | Valid until 31 Jul 2028 |
| GreencityKalol, 382721 | GREEN CITY INFRASTRUCTURE | 607 | 84% | 1 Dec 2018 | Valid until 31 Dec 2020 |
| SWAGAT GLASSGLOWSARGASAN, 382421 | SWAGAT DEVELOPERS | 592 | 55% | 21 Mar 2024 | Valid until 30 Apr 2032 |
| Dharohar | SHEETAL HOUSING DEVELOPMENT LLP | 588 | 11% | 31 Aug 2023 | Valid until 30 Apr 2028 |
| SUBH LABH AAVAS YOJNAAdalaj, 382421 | GANDHINAGAR URBAN DEVELOPMENT AUTHORITY | 582 | 0% | 17 Jan 2019 | Valid until 31 Mar 2019 |
| SOBHA ELYSIAPIROJPUR, 382355 | SOBHA LIMITED | 572 | 21% | 30 Mar 2024 | Valid until 30 Apr 2031 |
| North EnclaveGandhinagar, 382421 | PACIFICA INDIA PROJECTS PRIVATE LIMITED | 560 | 95% | 12 Dec 2018 | Valid until 31 Dec 2024 |
| ANAVYA PARMESHWAR | PARMESHWAR BUILDCON | 552 | 75% | 1 Feb 2021 | Valid until 31 Dec 2026 |
| EkamKudasan, 382421 | AMI DEVELOPERS | 537 | 0% | 11 Feb 2025 | Valid until 30 Apr 2030 |
| SHALIGRAM LAKEVIEWKhoraj, 382421 | SHRIMATE INFRASTRUCTURE LLP | 523 | 0% | 10 Nov 2017 | Valid until 31 Dec 2018 |
| Regalia IIRatanpur, Shahpur, 382355 | Nakshatra Infraspace | 508 | 39% | 28 Oct 2024 | Valid until 30 Apr 2031 |
| K B Royal LuminousZundal, 382421 | KGB INFRASTRUCTURE LLP | 506 | 0% | 19 Feb 2026 | Valid until 30 Apr 2031 |
| TPS 13 FP 319 EWS II | GANDHINAGAR URBAN DEVELOPMENT AUTHORITY | 504 | 94% | 17 Mar 2021 | Valid until 31 Jan 2024 |
| RADHE INFINITYKudasan | ARPAN DEVELOPERS | 496 | 61% | 2 Jan 2020 | Valid until 30 Jun 2027 |
| VIDAPirojpur, 382355 | Nila Spaces Limited | 496 | 81% | 1 Oct 2022 | Valid until 30 Oct 2028 |
| SHILP CENTRICA | SHILP INFRAPROJECTS PRIVATE LIMITED | 492 | 66% | 8 Nov 2023 | Valid until 30 Apr 2030 |
| REVARatanpur, 382355 | KAAVYARATNA INFRA LLP | 486 | 90% | 30 Jul 2022 | Valid until 30 Apr 2028 |
| REVANTA LAKEVIEWKOBA, 382421 | RADHE DEVELOPERS | 486 | 0% | 6 Apr 2026 | Valid until 31 Dec 2030 |
| MIG KUDASANKudasan, 382421 | GANDHINAGAR URBAN DEVELOPMENT AUTHORITY | 480 | 100% | 7 Jan 2019 | Valid until 31 Mar 2020 |
| Sobha Dream HeightsPhirozpur, 382355 | SOBHA LIMITED | 474 | 100% | 28 Mar 2019 | Valid until 29 Sep 2025 |
| ReflectionsKhoraj, 380060 | Pacifica Developers Private Limited | 468 | 0% | 9 Oct 2017 | Valid until 31 Dec 2018 |
| SANSKRUTIRandesan | KR DEVELOPERS | 468 | 88% | 21 Jun 2020 | Valid until 28 Feb 2025 |
| Construction of 504 L.I.G Houses including Shops and Infrastructure At: Adalaj Ta: Gandhinagar Dist: GandhinagarAdalaj, 382421 | GUJARAT RURAL HOUSING BOARD GNR | 464 | 96% | 17 Dec 2018 | Valid until 30 Dec 2022 |
| GRACESantej -Rakanpur, 382721 | SHRINIVAS ORGANISORS PRIVATE LIMITED | 462 | 0% | 17 Oct 2026 | Valid until 30 Jun 2031 |
| Shivalik WaveKhoraj, 382735 | SHIVALIK DEVELOPERS PRIVATE LIMITED | 459 | 29% | 19 Dec 2024 | Valid until 30 Apr 2030 |
| Shivalik CurvPirojpur | SHIVALIK DEVELOPERS PRIVATE LIMITED | 453 | 81% | 21 Oct 2023 | Valid until 30 Apr 2030 |
| KAILASH One51CHILODA (NARODA), 382330 | KAILASH SUDARSHAN REALTY LLP | 443 | 9% | 3 Feb 2024 | Valid until 30 Apr 2030 |
| Onyx LuxuriaAdalaj, 382421 | MARUTI BUILDCON | 443 | 13% | 8 Jul 2024 | Valid until 31 Jul 2029 |
| THE PARK BY PARMESHWARZUNDAL, 382421 | Pancham Infra | 439 | 45% | 28 Jul 2025 | Valid until 30 Apr 2030 |
| EMBRACE THE WINDSARGASAN, 382421 | SRIPRAD SHASHWAT | 428 | 10% | 31 Jan 2025 | Valid until 30 Apr 2031 |
| Satyamev Royal 5 | SHREE GAYATRI SATYAMEV REALTY PRIVATE LIMITED | 424 | 26% | 21 Oct 2022 | Valid until 31 Jul 2027 |
| STAVYA SKY | STAVYA BUILDCON LLP | 420 | 67% | 21 Jun 2023 | Valid until 31 Jul 2027 |
| STELLA | BAKERI RESIDENCES LLP | 419 | 58% | 17 Aug 2023 | Valid until 30 Jul 2028 |
| LUXURIA 2 | SHRINIVAS ORGANISORS PRIVATE LIMITED | 408 | 51% | 7 Sep 2021 | Valid until 30 Jun 2027 |
| SUPER CITY PHASE 1Santej, 382721 | SHRINIVAS ORGANISORS PRIVATE LIMITED | 406 | 0% | 29 Aug 2017 | Valid until 31 May 2019 |
| SHIVALAY SHARNAMKudasan, 382421 | Shiv Infrastructure | 404 | 89% | 28 Mar 2019 | Valid until 1 Feb 2023 |
| MAITRI LAKE VIEWZundal, 382421 | GAYATRI INFRASTRUCTURE LIMITED | 402 | 69% | 10 Jan 2018 | Valid until 26 Jan 2026 |
| VED BUNGALOWS/VED GREEN PHASE-1 | VED INFRA | 400 | 72% | 4 Oct 2018 | Valid until 25 Jun 2025 |
| THE OFFICES BY HARI GROUPSARAGASAN | HN HARI INFRASTRUCTURE LLP | 397 | 25% | 30 May 2023 | Valid until 30 Apr 2027 |
| LIG - II RaysanRAYSAN, 382355 | GANDHINAGAR URBAN DEVELOPMENT AUTHORITY | 393 | 89% | 31 May 2019 | Valid until 30 Dec 2021 |
| THE ADDRESS | GOPINATH DEVELOPER | 393 | 20% | 28 Jun 2023 | Valid until 26 Oct 2027 |
| EWS - 2Sargasan, 382016 | GANDHINAGAR URBAN DEVELOPMENT AUTHORITY | 392 | 95% | 31 Dec 2018 | Valid until 30 Jun 2023 |
| SECTOR 6A PHASE-1 | VITRAG ENTERPRISE LLP | 392 | 93% | 11 Oct 2021 | Valid until 31 Mar 2026 |
| VINAYAK COURTYARD | WHITESWAN BUILDCON LLP | 382 | 69% | 29 Oct 2020 | Valid until 31 Aug 2026 |
| ELARAKOBA, 382010 | RA IRA DEVELOPERS LLP | 375 | 1% | 28 Apr 2025 | Valid until 30 Jul 2031 |
| Pramukh MastanaKudasan, 382421 | PRAMUKH MASTANA ASSOCIATES | 373 | 63% | 19 Jan 2019 | Valid until 31 Oct 2021 |
Developers active in Gandhinagar
GANDHINAGAR URBAN DEVELOPMENT AUTHORITY (14), SHRINIVAS ORGANISORS PRIVATE LIMITED (14), RADHE DEVELOPERS (9), SHIV DEVELOPERS (9), AMBA TOWNSHIP PRIVATE LIMITED (8), ADANI ESTATE MANAGEMENT PRIVATE LIMITED (7). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Gandhinagar projects listed above?
Compare each project against its neighbours, not against the brochure. The median project on this page is 53% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Gandhinagar project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What if a Gandhinagar project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.