Home / Browse projects / Gandhinagar, Gujarat / VIDA

Valid until 30 Oct 2028 Residential/Group Housing project

VIDA

By Nila Spaces Limited

RG-GJ-44966 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/GIFT Urban Development Authority/RN209AA10109/011022 · Last updated on GujRERA portal: 30 Sep 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Oct 2028Possession promisedno revision filed
3 of 9Construction stages donefurthest along: Internal walls, 99%
93 of 496Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

VIDA is a Residential/Group Housing project by Nila Spaces Limited in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/GIFT Urban Development Authority/RN209AA10109/011022 on 1 Oct 2022. Possession is promised by 30 Oct 2028. 403 of the 496 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameVIDA
  • TypeResidential/Group Housing
  • Location
    • VIDA
    • Plot no. 46 J
    • Block No. 46
    • Opp. Petrol Pump
    • Gujarat International Finance Tec City
    • Gandhinagar
    • Pirojpur
    • Gandhinagar
    • 382355
  • Pincode382355
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/GIFT Urban Development Authority/RN209AA10109/011022
  • ReraGenie IDRG-GJ-44966

Builder

  • NameNila Spaces Limited
  • Entity typeCOMPANY

Key dates

this monthRegisteredOct 2022PromisedOct 2028

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2028
  • Registered on1 Oct 2022
  • Promised completion30 Oct 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Current status

81%403 of 496 units booked
95.9%Of the estimated cost spent so far

Figures as on 30 Sep 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B---4960496

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 30 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.

A+B: 83% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats99%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%

Progress on shared amenities19

As on 30 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes60%
Water supplyYes98%
Sewerage (chamber, lines, septic tank, STP)Yes99%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes30%
Street lightingYes5%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes65%
Energy managementYes25%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes98%
Fire fightingYes95%
Drinking water facilitiesYes65%
Emergency evacuationYes45%
Use of renewable energyYes10%
SecurityYes60%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,128 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 222.01 cr
Cost incurredRs 212.90 cr
Spent of the estimate95.9%
BuildingWingEstimatedIncurred
A+BNARs 222.01 crRs 212.90 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHartmut Johannes Wurster
EngineerUTSAV DEVENDRA SHAH

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/GIFT Urban Development Authority/RN209AA10109/011022 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)30 Sep 2026
Engineer's certificate (Form 2)28 Sep 2026
Engineer's certificate annexure28 Sep 2026
Architect's certificate (Form 1)25 Sep 2026
Site photograph, A+B16 Sep 2026
RERA registration certificate1 Oct 2022
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

81%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep VIDA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Pirojpur1,600+ in Gandhinagar

2 kmVIDAOther 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 29 registered projects within 2 km.

Builder: Nila Spaces Limited

Nila Spaces Limited has 1 registration on GujRERA, including VIDA. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if VIDA is delayed beyond 30 Oct 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VIDA?

The registered promoter entity is Nila Spaces Limited, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VIDA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VIDA?

The professionals named in the filing: Architect: Hartmut Johannes Wurster; Engineer: UTSAV DEVENDRA SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIDA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIDA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIDA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.