ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / VINAYAK COURTYARD

Valid until 31 Aug 2026 Mixed Development project

VINAYAK COURTYARD

By WHITESWAN BUILDCON LLP

RG-GJ-31846 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07612/A2M/EX1/020725/310826 · Last updated on GujRERA portal: 16 Dec 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Aug 2026Possession promisedmoved 12 months from the original
65 of 72Construction stages doneacross 8 buildings; furthest along: Sanitary fittings within the flats, 90%
117 of 382Units unsoldnot recorded sold or booked
Jump to the 49 documents Report an error

VINAYAK COURTYARD is a Mixed Development project by WHITESWAN BUILDCON LLP in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07612/A2M/EX1/020725/310826 on 29 Oct 2020. Possession is promised by 31 Aug 2026. The completion date has moved by 12 months from the original filing. 265 of the 382 units on this registration are recorded sold or booked, and 65 of 72 construction stages are filed complete.

At a glance

Project

  • NameVINAYAK COURTYARD
  • TypeMixed Development
  • Location
    • FP NO 90+95
    • TP NO. 18
    • RAYSAN
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07612/A2M/EX1/020725/310826
  • ReraGenie IDRG-GJ-31846

Builder

  • NameWHITESWAN BUILDCON LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations1 more →
  • Past their filed date2

Key dates

this monthRegisteredOct 2020First promiseAug 2025Revised toAug 2026

Key facts

Registration and timeline

  • StatusValid until 31 Aug 2026
  • Registered on29 Oct 2020
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 31 Aug 2025)
  • Buildings8 building records
  • Documents filed49 files

Current status

69%265 of 382 units booked
100.0%Of the estimated cost spent so far

Figures as on 16 Dec 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---42042
BLOCK C---42042
BLOCK B---42042
BLOCK E---42042
BLOCK D---42042
BLOCK H---42042
BLOCK G---42042
BLOCK I---08688

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 16 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

65 of 72 construction stages are filed complete across 8 buildings. The stage furthest along is Sanitary fittings within the flats, at 90%.

BLOCK A99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK C99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK B99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK E99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK D99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK H99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK G99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK I100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 16 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes80%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsYes100%
Landscaping and tree plantingYes80%
Street lightingYes50%
Community buildingsYes50%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes80%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes80%
Fire fightingYes80%
Drinking water facilitiesYes80%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes50%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area17,117 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 137.25 cr
Cost incurredRs 137.25 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
BLOCK ENARs 23.55 crRs 23.55 cr
BLOCK ANARs 18.80 crRs 18.80 cr
BLOCK BNARs 18.80 crRs 18.80 cr
BLOCK CNARs 18.80 crRs 18.80 cr
BLOCK DNARs 18.80 crRs 18.80 cr
BLOCK GNARs 13.00 crRs 13.00 cr
BLOCK HNARs 13.00 crRs 13.00 cr
BLOCK INARs 12.50 crRs 12.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTHE GRID ARCHITECTS
EngineerJAYESH PANDYA

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07612/A2M/EX1/020725/310826Applied May 2025; approved Jul 2025

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07612/A2M/EX1/020725/310826 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)16 Dec 2025
Engineer's certificate (Form 2)15 Dec 2025
Engineer's certificate annexure15 Dec 2025
Architect's certificate (Form 1)13 Dec 2025
Site photograph, BLOCK A12 Dec 2025
Site photograph, BLOCK C12 Dec 2025
Site photograph, BLOCK B12 Dec 2025
Site photograph, BLOCK E12 Dec 2025
Site photograph, BLOCK D12 Dec 2025
Site photograph, BLOCK H12 Dec 2025
Site photograph, BLOCK G12 Dec 2025
Site photograph, BLOCK I12 Dec 2025
RERA registration certificate29 Oct 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

69%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 12 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep VINAYAK COURTYARD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmVINAYAK COURTYARDOther 148Dot size: filed unitsN

Filed coordinates, straight-line distance. 148 registered projects within 2 km.

Builder: WHITESWAN BUILDCON LLP

WHITESWAN BUILDCON LLP has 2 registrations on GujRERA, including VINAYAK GARDENS and VINAYAK COURTYARD. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if VINAYAK COURTYARD is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VINAYAK COURTYARD?

The registered promoter entity is WHITESWAN BUILDCON LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VINAYAK COURTYARD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VINAYAK COURTYARD?

The professionals named in the filing: Architect: THE GRID ARCHITECTS; Engineer: JAYESH PANDYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VINAYAK COURTYARD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VINAYAK COURTYARD. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VINAYAK COURTYARD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.