WTC GIFT Tower A, B & D
By WTC Noida Development Company Pvt Ltd
RG-GJ-03442 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA00788/EX1/180923 · Last updated on GujRERA portal: 20 Apr 2024
Source: official GujRERA filing
Red flags
- Completion date moved by 28 months
- 2 extensions taken
Clear
- Separate project account declared
Saved.
WTC GIFT Tower A, B & D is a Commercial project by WTC Noida Development Company Pvt Ltd in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA00788/EX1/180923 on 21 Nov 2017. Possession is promised by 30 Oct 2025. The completion date has moved by 28 months from the original filing. 1,168 of the 1,188 units on this registration are recorded sold or booked, and 20 of 27 construction stages are filed complete.
At a glance
Project
- NameWTC GIFT Tower A, B & D
- TypeCommercial
- Location
- Block No 51
- Road 5E
- Zone 5
- GIFT CITY
- Ratanpur
- Gandhinagar
- 382355
- Pincode382355
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA00788/EX1/180923
- ReraGenie IDRG-GJ-03442
Builder
- NameWTC Noida Development Company Pvt Ltd
- Entity typeCOMPANY
- Other registrations1 more →
- Past their filed date2
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Oct 2025
- Registered on21 Nov 2017
- Promised completion30 Oct 2025
- Revised completionRevised to 30 Oct 2025 (originally 30 Jun 2023)
- Buildings3 building records
- Documents filed41 files
Current status
Figures as on 20 Apr 2024, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower A | - | - | - | 0 | 141 | 141 |
| Tower B | - | - | - | 0 | 911 | 911 |
| Tower D | - | - | - | 0 | 136 | 136 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building3
As on 20 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary fittings within the flats, at 60%.
Tower A89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Tower B65%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 50% |
| Sanitary fittings within the flats | 60% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 42% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 29% |
Tower D89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 20 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 28% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 90% |
| Storm water drains | Yes | 90% |
| Landscaping and tree planting | Yes | 28% |
| Street lighting | Yes | 28% |
| Community buildings | Yes | 28% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | 90% |
| Water conservation, rain water harvesting | Yes | 28% |
| Energy management | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | Yes | 28% |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | Yes | 28% |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 28% |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Tower B | NA | Rs 164.95 cr | Rs 95.19 cr |
| Tower A | NA | Rs 46.66 cr | Rs 29.53 cr |
| Tower D | NA | Rs 46.66 cr | Rs 28.31 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Nirman Consultants Pvt Ltd |
| Engineer | Ducon Consultants Pvt Ltd |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed41
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA00788/EX1/180923 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 20 Apr 2024 |
| Engineer's certificate (Form 2) | 19 Apr 2024 |
| Engineer's certificate annexure | 19 Apr 2024 |
| Architect's certificate (Form 1) | 29 Mar 2024 |
| Site photograph, Tower A | 16 Mar 2024 |
| Site photograph, Tower B | 16 Mar 2024 |
| Site photograph, Tower D | 16 Mar 2024 |
| RERA registration certificate | 21 Nov 2017 |
| Extension certificate | - |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Gandhinagar
Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.
Keep WTC GIFT Tower A, B & D on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ratanpur1,600+ in Gandhinagar
Filed coordinates, straight-line distance. 30 registered projects within 2 km.
SIBAN
UNITED YOGI LLP
The Identity
RASHMII AND DOBARIYA INFRASPACE LLP
PRANA
Nila Urban Living Private Limited
SOBHA ELYSIA
SOBHA LIMITED
Regalia II
Nakshatra Infraspace
VIDA
Nila Spaces Limited
See every Gandhinagar project, with the district possession charts
Builder: WTC Noida Development Company Pvt Ltd
WTC Noida Development Company Pvt Ltd has 2 registrations on GujRERA, including WTC GIFT Tower A, B & D and WTC GIFT Tower C. Read the full track record. See more projects on the Gandhinagar district page.
Frequently asked questions
What are my rights if WTC GIFT Tower A, B & D is delayed beyond 30 Oct 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of WTC GIFT Tower A, B & D?
The registered promoter entity is WTC Noida Development Company Pvt Ltd, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in WTC GIFT Tower A, B & D?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at WTC GIFT Tower A, B & D?
The professionals named in the filing: Architect: Nirman Consultants Pvt Ltd; Engineer: Ducon Consultants Pvt Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in WTC GIFT Tower A, B & D?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.