Home / Browse projects / Gandhinagar, Gujarat / JOY

Valid until 31 Dec 2026 Residential/Group Housing project

JOY

By SHRINIVAS ORGANISORS PRIVATE LIMITED

RG-GJ-57049 · RERA PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA09873/280222 · Last updated on GujRERA portal: 15 Dec 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2026Possession promisedno revision filed
50 of 90Construction stages doneacross 10 buildings; furthest along: Internal walls, 96%
292 of 808Units unsoldnot recorded sold or booked
Jump to the 51 documents Report an error

JOY is a Residential/Group Housing project by SHRINIVAS ORGANISORS PRIVATE LIMITED in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA09873/280222 on 28 Feb 2022. Possession is promised by 31 Dec 2026. 516 of the 808 units on this registration are recorded sold or booked, and 50 of 90 construction stages are filed complete.

At a glance

Project

  • NameJOY
  • TypeResidential/Group Housing
  • Location
    • SUPERCITY JOY
    • BHADAJ DENTAL COLLEGE ROAD NR SCIENCE CITY
    • Kalol
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA09873/280222
  • ReraGenie IDRG-GJ-57049

Builder

  • NameSHRINIVAS ORGANISORS PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations13 more →
  • Past their filed date8

Key dates

this monthRegisteredFeb 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on28 Feb 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings10 building records
  • Documents filed51 files

Current status

64%516 of 808 units booked
95.1%Of the estimated cost spent so far

Figures as on 15 Dec 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---56056
BLOCK B---56056
BLOCK C---56056
BLOCK D---56056
BLOCK E---1120112
BLOCK F---1080108
BLOCK G---1400140
BLOCK H---1120112
BLOCK I---56056
BLOCK J---56056

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building10

As on 15 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

50 of 90 construction stages are filed complete across 10 buildings. The stage furthest along is Internal walls, at 96%.

BLOCK A77%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing45%
BLOCK B76%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing35%
BLOCK C81%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats88%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing78%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
BLOCK D80%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats88%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing77%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing55%
BLOCK E82%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats96%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing88%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
BLOCK F84%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats96%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing96%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing65%
BLOCK G78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing40%
BLOCK H78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing45%
BLOCK I76%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats78%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing35%
BLOCK J73%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing25%

Progress on shared amenities19

As on 15 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes40%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes50%
Storm water drainsYes50%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes50%
Treatment and disposal of sewage and sullage waterYes50%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes60%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes50%
Fire fightingYes55%
Drinking water facilitiesYes40%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,913 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 106.96 cr
Cost incurredRs 101.73 cr
Spent of the estimate95.11%
BuildingWingEstimatedIncurred
BLOCK GNARs 15.68 crRs 15.13 cr
BLOCK ENARs 12.54 crRs 12.04 cr
BLOCK HNARs 12.54 crRs 12.12 cr
BLOCK FNARs 12.10 crRs 11.53 cr
BLOCK ANARs 9.02 crRs 8.48 cr
BLOCK BNARs 9.02 crRs 8.51 cr
BLOCK CNARs 9.02 crRs 8.54 cr
BLOCK DNARs 9.02 crRs 8.53 cr
BLOCK INARs 9.02 crRs 8.46 cr
BLOCK JNARs 9.02 crRs 8.40 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKAMLESH DINKERROY MEHTA
EngineerVIJAY DASHRATHBHAI SHAH

Documents filed51

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA09873/280222 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)15 Dec 2025
Engineer's certificate (Form 2)15 Dec 2025
Engineer's certificate annexure15 Dec 2025
Accountant's certificate (Form 3)15 Dec 2025
Site photograph, BLOCK A15 Dec 2025
Site photograph, BLOCK B15 Dec 2025
Site photograph, BLOCK C15 Dec 2025
Site photograph, BLOCK D15 Dec 2025
Site photograph, BLOCK D15 Dec 2025
Site photograph, BLOCK E15 Dec 2025
Site photograph, BLOCK F15 Dec 2025
Site photograph, BLOCK G15 Dec 2025
Site photograph, BLOCK H15 Dec 2025
Site photograph, BLOCK I15 Dec 2025
Site photograph, BLOCK J15 Dec 2025
RERA registration certificate28 Feb 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

64%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep JOY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmJOYOther 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: SHRINIVAS ORGANISORS PRIVATE LIMITED

SHRINIVAS ORGANISORS PRIVATE LIMITED has 14 registrations on GujRERA, including SUPER CITY PHASE 1 and SUPER CITY PHASE 2 DREAM. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if JOY is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of JOY?

The registered promoter entity is SHRINIVAS ORGANISORS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in JOY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JOY?

The professionals named in the filing: Architect: KAMLESH DINKERROY MEHTA; Engineer: VIJAY DASHRATHBHAI SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JOY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JOY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JOY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.