Valid until 30 Oct 2027 Mixed Development project

Swagat Twincity Highstreet & Swagat Kingsland

By SWAGAT DEVELOPERS

RG-GJ-93589 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/CAA05578/A2M/160725/301027 · Last updated on GujRERA portal: 26 Jun 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Oct 2027Possession promisedno revision filed
34 of 72Construction stages doneacross 8 buildings; furthest along: External plumbing and external plaster, 90%
390 of 626Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

Swagat Twincity Highstreet & Swagat Kingsland is a Mixed Development project by SWAGAT DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/CAA05578/A2M/160725/301027 on 19 Jun 2019. Possession is promised by 30 Oct 2027. 236 of the 626 units on this registration are recorded sold or booked, and 34 of 72 construction stages are filed complete.

At a glance

Project

  • NameSwagat Twincity Highstreet & Swagat Kingsland
  • TypeMixed Development
  • Location
    • SWAGAT TWINCITY HIGHSTREET
    • NR. ASHKA HOSPITAL
    • NR. SARGASAN CROSS ROAD
    • GANDHINAGAR.
    • Sargasan
    • Gandhinagar
    • 382016
  • Pincode382016
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/CAA05578/A2M/160725/301027
  • ReraGenie IDRG-GJ-93589

Builder

  • NameSWAGAT DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations3 more →
  • Past their filed date1

Key dates

this monthRegisteredJun 2019PromisedOct 2027

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2027
  • Registered on19 Jun 2019
  • Promised completion30 Oct 2027
  • Revised completionNone
  • Buildings8 building records
  • Documents filed42 files

Current status

38%236 of 626 units booked
78.4%Of the estimated cost spent so far

Figures as on 26 Jun 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---56056
BLOCK B---28028
BLOCK C---56056
BLOCK D---56056
BLOCK E---56056
BLOCK F---44044
BLOCK G---22022
BLOCK H---0308308

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 26 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

34 of 72 construction stages are filed complete across 8 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

BLOCK A71%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing25%
BLOCK B71%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing25%
BLOCK C52%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats40%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK D52%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats40%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK E52%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats40%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK F51%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK G51%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK H89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 26 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes70%
Water supplyYes58%
Sewerage (chamber, lines, septic tank, STP)Yes55%
Storm water drainsYes55%
Landscaping and tree plantingYes40%
Street lightingYes25%
Community buildingsYes65%
Treatment and disposal of sewage and sullage waterYes20%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes30%
Energy managementYes0%
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes55%
Fire fightingYes60%
Drinking water facilitiesYes35%
Emergency evacuationYes55%
Use of renewable energyNoNot applicable
SecurityYes35%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,584 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 173.49 cr
Cost incurredRs 136.00 cr
Spent of the estimate78.39%
BuildingWingEstimatedIncurred
BLOCK HNARs 72.62 crRs 72.62 cr
BLOCK FNARs 19.35 crRs 10.64 cr
BLOCK ANARs 15.67 crRs 12.53 cr
BLOCK CNARs 15.39 crRs 9.70 cr
BLOCK DNARs 15.39 crRs 8.36 cr
BLOCK ENARs 15.39 crRs 11.50 cr
BLOCK GNARs 11.12 crRs 6.12 cr
BLOCK BNARs 8.56 crRs 4.53 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAKESHKUMAR KANNAIYALAL PRAJAPATI
EngineerJIGARKUMAR GHANSHYAMBHAI SHAH
EngineerKANDARP PARESHKUMAR DESAI

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/CAA05578/A2M/160725/301027 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)26 Jun 2025
Architect's certificate (Form 1)24 Jun 2025
Engineer's certificate (Form 2)24 Jun 2025
Engineer's certificate annexure24 Jun 2025
RERA registration certificate19 Jun 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

38%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep Swagat Twincity Highstreet & Swagat Kingslan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Sargasan1,600+ in Gandhinagar

2 kmSwagat Twincity HighstreOther 252Dot size: filed unitsN

Filed coordinates, straight-line distance. 252 registered projects within 2 km.

Builder: SWAGAT DEVELOPERS

SWAGAT DEVELOPERS has 4 registrations on GujRERA, including SWAGAT HOLIDAYMALL and Swagat Twincity Highstreet & Swagat Kingsland. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if Swagat Twincity Highstreet & Swagat Kingsland is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Swagat Twincity Highstreet & Swagat Kingsland?

The registered promoter entity is SWAGAT DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Swagat Twincity Highstreet & Swagat Kingsland?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Swagat Twincity Highstreet & Swagat Kingsland?

The professionals named in the filing: Architect: RAKESHKUMAR KANNAIYALAL PRAJAPATI; Engineer: JIGARKUMAR GHANSHYAMBHAI SHAH; Engineer: KANDARP PARESHKUMAR DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Swagat Twincity Highstreet & Swagat Kingsland?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Swagat Twincity Highstreet & Swagat Kingsland. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Swagat Twincity Highstreet & Swagat Kingslan to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.