ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / RADHE INFINITY

Valid until 30 Jun 2027 Mixed Development project

RADHE INFINITY

By ARPAN DEVELOPERS

RG-GJ-92581 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA06553/A1M/140820 · Last updated on GujRERA portal: 10 Feb 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jun 2027Possession promisedno revision filed
45 of 45Construction stages doneacross 5 buildings; every applicable stage filed complete
191 of 496Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

RADHE INFINITY is a Mixed Development project by ARPAN DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA06553/A1M/140820 on 2 Jan 2020. Possession is promised by 30 Jun 2027. 305 of the 496 units on this registration are recorded sold or booked, and 45 of 45 construction stages are filed complete.

At a glance

Project

  • NameRADHE INFINITY
  • TypeMixed Development
  • Location
    • RADHE INFINITY RAKSHASHAKTI CIRCLE
    • NR SWAMINARAYAN DHAM KUDASAN
    • Kudasan
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA06553/A1M/140820
  • ReraGenie IDRG-GJ-92581

Builder

  • NameARPAN DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2020PromisedJun 2027

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2027
  • Registered on2 Jan 2020
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings5 building records
  • Documents filed45 files

Current status

61%305 of 496 units booked
100.0%Of the estimated cost spent so far

Figures as on 10 Feb 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK-A---56056
BLOCK-B---56056
BLOCK-C---56056
BLOCK-D---56056
BLOCK-E---0272272

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 10 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

45 of 45 construction stages are filed complete across 5 buildings.

BLOCK-A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK-B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK-C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK-D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK-E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 10 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationYes100%
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,068 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 108.29 cr
Cost incurredRs 108.29 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
BLOCK-ENARs 51.39 crRs 51.39 cr
BLOCK-ANARs 14.36 crRs 14.36 cr
BLOCK-BNARs 14.36 crRs 14.36 cr
BLOCK-CNARs 14.09 crRs 14.09 cr
BLOCK-DNARs 14.09 crRs 14.09 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKRISHNA BHAVSAR
EngineerJIGER SHAH

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA06553/A1M/140820 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)10 Feb 2025
Architect's certificate (Form 1)8 Feb 2025
Site photograph, BLOCK-A7 Feb 2025
Site photograph, BLOCK-B7 Feb 2025
Site photograph, BLOCK-C7 Feb 2025
Site photograph, BLOCK-D7 Feb 2025
Site photograph, BLOCK-E7 Feb 2025
Engineer's certificate (Form 2)8 Oct 2024
Engineer's certificate annexure8 Oct 2024
RERA registration certificate2 Jan 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

61%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep RADHE INFINITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kudasan1,600+ in Gandhinagar

2 kmRADHE INFINITYOther 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 151 registered projects within 2 km.

Builder: ARPAN DEVELOPERS

ARPAN DEVELOPERS has 1 registration on GujRERA, including RADHE INFINITY. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if RADHE INFINITY is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RADHE INFINITY?

The registered promoter entity is ARPAN DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RADHE INFINITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RADHE INFINITY?

The professionals named in the filing: Architect: KRISHNA BHAVSAR; Engineer: JIGER SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RADHE INFINITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RADHE INFINITY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RADHE INFINITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.