Home / Browse projects / Ratnagiri, Maharashtra / ZAID ENCLAVE

Completed No litigation declared Residential / Group Housing project

ZAID ENCLAVE

By Mohammad Karim Fakir

RG-MH-30127 · RERA P52800029783 · Last updated on MahaRERA portal: 19 Aug 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Internal walls, 85%
7 of 15Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

ZAID ENCLAVE is a Residential / Group Housing project by Mohammad Karim Fakir in Ratnagiri, Maharashtra, registered with MahaRERA as P52800029783 on 29 Jun 2021. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 24 months from the original filing. 8 of the 15 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameZAID ENCLAVE
  • TypeResidential / Group Housing
  • Location
    • Kanse Wadi Road
    • Mirjoli
    • Chiplun
    • Ratnagiri
    • 415605
  • Pincode415605
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800029783
  • ReraGenie IDRG-MH-30127

Builder

  • NameMohammad Karim Fakir
  • Entity typeIndividual

Key dates

this monthRegisteredJun 2021First promiseDec 2023Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Jun 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed42 files

Current status

53%8 of 15 units booked

Figures as on 19 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ZAID ENCLAVENA5315015

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

ZAID ENCLAVE: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 19 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered4

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area550 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityChiplun Municipal Council
Permissible FSI598.53
Proposed, not sanctioned599 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR HOTEL ATITHI MUMBAI GOA HIGHWAY CHIPLUN 415605

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbhay Ravindra Kaanekar
EngineerRvindra M Patil
Chartered AccountantSantosh Jadhav & Associates
Chartered AccountantOmkar A Sardesai
PartnerRole in project
Mohammad Karim Fakir-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52800019383Dec 2023 → Dec 2025

Reason as filed by the promoterIssues with material availability, procurement delays, or supply chain disruptions, such as transportation bottlenecks or shortages, can lead to project delays.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12501720KISHOR DILIP MALIMohammad Karim Fakir26/05/2025
CC12501723MOHAN SHETIBA DHOTAREMohammad Karim Fakir26/05/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Full Occupancy Certificate.pdf19 Aug 2026
Form 2File: Full Occupancy Certificate.pdf19 Aug 2026
Form 3File: Full Occupancy Certificate.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: Full Occupancy Certificate.pdf19 Aug 2026
Form 1File: Full Occupancy Certificate.pdf19 Aug 2026
Form 2File: Full Occupancy Certificate.pdf19 Aug 2026
Form 3File: Full Occupancy Certificate.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: Full Occupancy Certificate.pdf19 Aug 2026
Form 1File: Full Occupancy Certificate.pdf19 Aug 2026
Form 2File: Full Occupancy Certificate.pdf19 Aug 2026
Form 3File: Full Occupancy Certificate.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: Full Occupancy Certificate.pdf19 Aug 2026
Form 2A (FY 2025-2026)File: Full Occupancy Certificate.pdf19 Aug 2026
Form 5 (FY 2024-2025)File: Full Occupancy Certificate.pdf19 Aug 2026
Occupational CertificateFile: Full Occupancy Certificate.pdf19 Aug 2026
Occupational CertificateFile: OC Confirmation Mail.pdf19 Aug 2026
Declaration about Commencement CertificateFile: Format D.pdf22 Mar 2024
Declaration in FORM BFile: M Fakir Form B.pdf22 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf22 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf22 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 1.pdf22 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf22 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf22 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22.pdf22 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf22 Mar 2024
Declaration about Commencement CertificateFile: document(47).pdf22 Jun 2021
Proforma of Allotment letterFile: Proformar Agreement For Sale.pdf22 Jun 2021
Layout approvalFile: Blueprint.pdf17 Jun 2021
Building plan approvalFile: Blueprint.pdf17 Jun 2021
PAN CardFile: PAN Card.pdf17 Jun 2021
Copy of the legal title reportFile: Search Report.pdf17 Jun 2021
Details of encumbrancesFile: Encumbrance Certificate.pdf17 Jun 2021
Copy of Layout Approval (in case of layout)File: Blueprint.pdf17 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: Blueprint.pdf17 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf17 Jun 2021
Declaration in FORM BFile: Form B (Promotor).pdf17 Jun 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf17 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf17 Jun 2021
OtherFile: Kharedi Khat-1-7.pdf17 Jun 2021
OtherFile: Kharedi Khat-8-14.pdf17 Jun 2021
OtherFile: Kharedi Khat-15-21.pdf17 Jun 2021

How this compares with Ratnagiri

53%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one moved by 24 months
30%of Ratnagiri registrations have lapsed or been cancelledthis one is completed

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep ZAID ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mirjoli1,100+ in Ratnagiri

2 kmZAID ENCLAVECompleted 40Lapsed / revoked 29Other 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 82 registered projects within 2 km.

Builder: Mohammad Karim Fakir

Mohammad Karim Fakir has 1 registration on MahaRERA, including ZAID ENCLAVE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if ZAID ENCLAVE is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ZAID ENCLAVE?

The registered promoter entity is Mohammad Karim Fakir, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ZAID ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ZAID ENCLAVE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ZAID ENCLAVE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ZAID ENCLAVE?

The professionals named in the filing: Architect: Abhay Ravindra Kaanekar; Engineer: Rvindra M Patil; Chartered Accountant: Santosh Jadhav & Associates; Chartered Accountant: Omkar A Sardesai. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ZAID ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ZAID ENCLAVE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ZAID ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.