Registration lapsed No litigation declared Residential / Group Housing project

Yogayog Bhavan

By Omkar Orbit

RG-MH-72466 · RERA P51700048443 · Last updated on MahaRERA portal: 26 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
6 of 30Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 80 documents Report an error

Yogayog Bhavan is a Residential / Group Housing project by Omkar Orbit in Thane, Maharashtra, registered with MahaRERA as P51700048443 on 3 Jan 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 24 of the 30 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameYogayog Bhavan
  • TypeResidential / Group Housing
  • Location
    • Shastri Nagar
    • Dombivli west
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421202
  • Pincode421202
  • RERA no.P51700048443
  • ReraGenie IDRG-MH-72466

Builder

  • NameOmkar Orbit
  • Entity typePartnership
  • PartnersVinay Ramchandra Deshmukh, Samir Dasharath Deshmukh, Mehul Sunil Gambhirrao

Key dates

10 months past promisethis monthRegisteredJan 2023PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Jan 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed80 files

Current status

80%24 of 30 units booked

Figures as on 26 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Yogayog BhavanNA8828230

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Yogayog Bhavan: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 26 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Closed/Covered39

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area484 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Sep 2024
LandownerVillageDistrict
Mohan Vasant PatilDOMBIVLIThane
Sharad Vasant PatilDOMBIVLIThane
Dilip Vasant PatilDOMBIVLIThane
Rahul Nandkumar PatilDOMBIVLIThane
Sonali Nitin BholeDOMBIVLIThane
Shubhangi Nandkumar PatilDOMBIVLIThane

Approvals and building plan

Sanctioning authorityKALYAN DOMBIVLI MUNICIPAL CORPORATION
Permissible FSI1747.6
Proposed, not sanctioned1,748 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDombivli west thane 421202

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRachana Shilp
EngineerRajesh Thakare and Associates
EngineerRAJESH THAKARE & ASSOCIATED
EngineerTejas Deshmukh
Chartered AccountantKapure and Kapure
Chartered AccountantKAPURE & KAPURE CHARTERED ACCOUNTANT
Chartered AccountantNAVAL KARNIK & CO.,
PartnerRole in project
Omkar Orbit-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Dec 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Feb 2025

Documents filed80

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A - Yogayog Bhavan.pdf26 Feb 2026
Form 5 (FY 2024-2025)File: Omkar Orbit - Form 5 - 24-25.pdf11 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Omkar Orbit - March 25.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 - Omkar Orbit - March 25_compressed.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure - Omkar Orbit -March 25.pdf20 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: omkar orbit CC.pdf24 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Omkar Orbit - Form 1.pdf19 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Omkar Orbit_compressed.pdf19 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Omkar Orbit - Form 2.pdf19 Jan 2025
Disclosure of sold/ booked inventoryFile: Omkar Orbit - Disclosure.pdf19 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Omkar orbit.pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Omkar Orbit - Arch Sep - 2024.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Omkar Orbit - Form 3_compressed.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Omkar Orbit - Engg Sep - 2024.pdf20 Oct 2024
Disclosure of sold/ booked inventoryFile: Omkar Orbit - Disclosure Sept 2024.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure June 24 - Omkar Orbit.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Omkar Orbit.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assuarance - Omkar Orbit - 2024.pdf14 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Omkar Orbit.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Omkar Orbit.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure Mar-24 - Omkar Orbit.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Omkar Orbit - Signed form 3.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Omkar Orbit Engg Cert Dec 2023.pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: Omkar Orbit Flat Inventory.pdf17 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Omkar Orbit - Form 3_compressed.pdf17 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Omkar Orbit Dec Arch Cert.pdf14 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Omkar Orbit - Quality Assuarance.pdf23 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Omkar Orbit - Architect.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Omkar Orbit - Engg.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Omkar orbit_compressed.pdf18 Oct 2023
Layout approvalFile: Plan 1.pdf16 Oct 2023
Layout approvalFile: Plan 2.pdf16 Oct 2023
Building plan approvalFile: Plan 1.pdf16 Oct 2023
Building plan approvalFile: Plan 2.pdf16 Oct 2023
Copy of Layout Approval (in case of layout)File: Plan 1.pdf16 Oct 2023
Copy of Layout Approval (in case of layout)File: Plan 2.pdf16 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 1.pdf16 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 2.pdf16 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf16 Oct 2023
Declaration about Commencement CertificateFile: Omkar Orbit - CC Declaration.pdf16 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Omkat Orbit Form 5.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar - Omkar Orbit - March.pdf21 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar - Omkar Orbit - June.pdf21 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Omkar Orbit - March.pdf21 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Omkar Orbit - June.pdf21 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 Omkar orbit- March 23_compressed.pdf21 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2023_compressed.pdf21 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Yogayog_261222_compressed.pdf26 Dec 2022
Proforma of Agreement for saleFile: Agreement for Sale-YOGAYOG-RERA-revised_191222.pdf19 Dec 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report -AFS Yogayog bhavan_compressed.pdf19 Dec 2022
Other - LegalFile: Self declaration - for mismatch owner.pdf19 Dec 2022
Other - LegalFile: ORDER_Collector Thane_compressed.pdf19 Dec 2022
Other - TechnicalFile: Self declaration - for mismatch owner.pdf19 Dec 2022
Other - TechnicalFile: ORDER_Collector Thane_compressed.pdf19 Dec 2022
CERSAI detailsFile: CERSAI.pdf2 Dec 2022
Proforma of Allotment letterFile: Allotment Letter.pdf2 Dec 2022
Deviation Report with respect to Allotment letterFile: Deviation Allotment letter-1.pdf2 Dec 2022
Layout approvalFile: PLAN SHEET 1.pdf1 Dec 2022
Layout approvalFile: PLAN SHEET 2.pdf1 Dec 2022
Building plan approvalFile: PLAN SHEET 1.pdf1 Dec 2022
Building plan approvalFile: PLAN SHEET 2.pdf1 Dec 2022
PAN CardFile: Pan card Omkar orbit.pdf1 Dec 2022
Copy of the legal title reportFile: Title report.pdf1 Dec 2022
Details of encumbrances concerned to FinanceFile: Declaration for encumbrance concerned to legal.pdf1 Dec 2022
Details of encumbrances concerned to FinanceFile: Declaration finance.pdf1 Dec 2022
Details of encumbrances concerned to LegalFile: Declaration for encumbrance concerned to legal.pdf1 Dec 2022
Details of encumbrances concerned to LegalFile: Declaration finance.pdf1 Dec 2022
Copy of Layout Approval (in case of layout)File: PLAN SHEET 1.pdf1 Dec 2022
Copy of Layout Approval (in case of layout)File: PLAN SHEET 2.pdf1 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: PLAN SHEET 1.pdf1 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: PLAN SHEET 2.pdf1 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: CC Omakr Orbit.pdf1 Dec 2022
Declaration about Commencement CertificateFile: Decalaration for CC.pdf1 Dec 2022
Declaration in FORM BFile: Form B Milind.pdf1 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Yogabhavan.pdf1 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Yogayog Bhavan.pdf1 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for seprate bank account.pdf1 Dec 2022

How this compares with Thane

80%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Yogayog Bhavan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dombivli west7,600+ in Thane

Builder: Omkar Orbit

Omkar Orbit has 1 registration on MahaRERA, including Yogayog Bhavan. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Yogayog Bhavan shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Yogayog Bhavan is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Yogayog Bhavan?

The registered promoter entity is Omkar Orbit, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Yogayog Bhavan?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Yogayog Bhavan?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Yogayog Bhavan?

The professionals named in the filing: Architect: Rachana Shilp; Engineer: Rajesh Thakare and Associates; Engineer: RAJESH THAKARE & ASSOCIATED; Engineer: Tejas Deshmukh; Chartered Accountant: Kapure and Kapure; Chartered Accountant: KAPURE & KAPURE CHARTERED ACCOUNTANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Yogayog Bhavan?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Yogayog Bhavan. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Yogayog Bhavan to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.