Home / Browse projects / Thane, Maharashtra / BHOIR JEWELS

Registered No litigation declared Residential / Group Housing project

BHOIR JEWELS

By SHANKAR NAMAJI BHOIR

RG-MH-24468 · RERA P51700003969 · Last updated on MahaRERA portal: 17 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 60 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 60 months from the original
12 of 33Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 80%
205 of 315Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 307 documents Report an error

BHOIR JEWELS is a Residential / Group Housing project by SHANKAR NAMAJI BHOIR in Thane, Maharashtra, registered with MahaRERA as P51700003969 on 7 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 60 months from the original filing. 110 of the 315 units on this registration are recorded sold or booked, and 12 of 33 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBHOIR JEWELS
  • TypeResidential / Group Housing
  • Location
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421202
  • Pincode421202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700003969
  • ReraGenie IDRG-MH-24468

Builder

  • NameSHANKAR NAMAJI BHOIR
  • Entity typeIndividual

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2022)
  • Buildings3 building records
  • Documents filed307 files

Current status

35%110 of 315 units booked
38.6%Work done, per cost certificate

Figures as on 17 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING - BNA14141258133
WING - ANA12121423145
WING - CNA9936137

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 17 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 80%.

WING - B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING - A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING - C39%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed46

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots46
Closed/Covered2
Open Space44
BuildingClosed/CoveredOpen SpaceTotal
WING - B12223
WING - A12223

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,693 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityKalyan Dombivli Municipal Corporation
Permissible FSI12784.0
Proposed, not sanctioned8,354 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMatunga East
Estimated costRs 75.11 cr
Cost incurredRs 29.00 cr
Work done38.61%
BuildingWingEstimatedIncurred
WING - ANARs 36.75 crRs 2.87 cr
WING - BNARs 16.08 crRs 17.63 cr
-NARs 13.61 crRs 5.22 cr
WING - CNARs 8.66 crRs 3.28 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectP S GOKHALE
EngineerMANOHAR PATIL
Chartered AccountantLaxmikant Kabra & Co LLP
Chartered AccountantNarendra Rajput
PartnerRole in project
SHANKAR NAMAJI BHOIR-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700012456Dec 2022 → Dec 2027

Reason as filed by the promoterDear Team, Explanation and Reasons for Project Delay Bhoir Jewels MahaRera No - P51700003963 1. Land Dispute- There was a land dispute between Shankar Namaji Bhoir proprietor of Kailash Construction company and one Mhatre family. The same land on which ‘A’wing of the project is to be constructed .The developers were in settlement talks with Mhatre family since 2016. The dispute finally got resolved on 26/12/2022 where the developer paid Rs. 10, 50,000/- in three cheques to the family & details of notary document are attached below in the Exhibit ‘A’. This was the reason what ‘A’ wing got delay

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000220753SHAMSUNDAR SHANKARRAO KATKARM/S. KAILASH CONSTRUCTION COMPANY, PROP. SHANKAR NAMAJI BHOIR11/04/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Apr 2022
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed307

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 307 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 January-2026 to March-2026.pdf17 Jun 2026
Withdrawal Update Form 2File: Form 2 Q4 FY 25-26.pdf17 Jun 2026
Withdrawal Update Form 3File: Form 3 Q4 FY 25-26.pdf17 Jun 2026
Withdrawal Update Form 1File: form 1 Oct to Dec - 2025.pdf11 Feb 2026
Withdrawal Update Form 2File: Form 2 Oct to Dec- 2026.pdf11 Feb 2026
Withdrawal Update Form 3File: Form 3 final.pdf11 Feb 2026
Withdrawal Update Form 1File: Form 1 - Jan To Mar 2023.pdf9 Feb 2026
Withdrawal Update Form 1File: Form 1 April to june 2025.pdf9 Feb 2026
Withdrawal Update Form 1File: Form 1 july to sep- 2025.pdf9 Feb 2026
Withdrawal Update Form 2File: OCT TO DEC 2022.pdf9 Feb 2026
Withdrawal Update Form 2File: Form 2 April to June - 2025.pdf9 Feb 2026
Withdrawal Update Form 2File: Form 2 july to September - 2025.pdf9 Feb 2026
Withdrawal Update Form 3File: Form 3 Q1 - Signed.pdf9 Feb 2026
Withdrawal Update Form 3File: Form 3 Q1 - Signed.pdf9 Feb 2026
Withdrawal Update Form 3File: Form 3 Q2 - Signed.pdf9 Feb 2026
Form 1File: Form 1 Q4 FY 22-23.pdf13 Jan 2026
Form 2File: Form 2 Q4 FY 22-23.pdf13 Jan 2026
Form 3File: Form 3 Q4 FY 22-23.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q4 Disclosure of sold and booked inventory com.pdf13 Jan 2026
Form 1File: Form 1 Q1 FY 23-24.pdf13 Jan 2026
Form 2File: Form 2 Q1 FY 23-24.pdf13 Jan 2026
Form 3File: Form 3 Q1 FY 23-24.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q1 Disclosure of sold and booked inventory Com.pdf13 Jan 2026
Form 1File: Form 1 Q2 FY 23-24.pdf13 Jan 2026
Form 2File: Form 2 Q2 FY 23-24.pdf13 Jan 2026
Form 3File: Form 3 Q2 FY 23-24.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q2 Disclosure of sold and booked inventory com.pdf13 Jan 2026
Form 1File: Form 1 Q3 FY 23-24.pdf13 Jan 2026
Form 2File: Form 2 Q3 FY 23-24.pdf13 Jan 2026
Form 3File: Form 3 Q3 FY 23-24.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q3 Disclosure of sold and booked inventory com.pdf13 Jan 2026
Form 1File: Form 1 Q4 FY 23-24.pdf13 Jan 2026
Form 2File: Form 2 Q4 FY 23-24.pdf13 Jan 2026
Form 3File: Form 3 Q4 FY 23-24.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q4 Disclosure of sold and booked inventory com.pdf13 Jan 2026
Form 1File: Form 1 Q1 FY 24-25.pdf13 Jan 2026
Form 2File: Form 2 Q1 FY 24-25.pdf13 Jan 2026
Form 3File: Form 3 Q1 FY 24-25.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q1 Disclosure of sold and booked inventory com.pdf13 Jan 2026
Form 1File: Form 1 Q2 FY 24-25.pdf13 Jan 2026
Form 2File: Form 2 Q2 FY 24-25.pdf13 Jan 2026
Form 3File: Form 3 Q2 FY 24-25.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q2 Disclosure of sold and booked inventory com.pdf13 Jan 2026
Form 1File: Form 1 Q3 FY 24-25.pdf13 Jan 2026
Form 2File: Form 2 Q3 FY 24-25.pdf13 Jan 2026
Form 3File: Form 3 Q3 FY 24-25.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q3 Disclosure of sold and booked inventory com.pdf13 Jan 2026
Form 1File: Form 1 Q4 FY 24-25.pdf13 Jan 2026
Form 2File: Form 2 Q4 FY 24-25.pdf13 Jan 2026
Form 3File: Form 3 Q4 FY 24-25.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q4 Disclosure of sold and booked inventory com.pdf13 Jan 2026
Form 1File: Form 1 Q2 FY 17-18.pdf12 Jan 2026
Form 2File: Form 2 Q2 FY 17-18.pdf12 Jan 2026
Form 3File: Form 3 Q2 FY 17-18_compressed.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q2 Disclosure of sold and booked inventory.pdf12 Jan 2026
Form 1File: Form 1 Q3 FY 17-18.pdf12 Jan 2026
Form 2File: Form 2 Q3 FY 17-18.pdf12 Jan 2026
Form 3File: Form 3 Q3 FY 17-18_compressed.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q3 Disclosure of sold and booked inventory.pdf12 Jan 2026
Form 1File: Form 1 Q4 FY 17-18.pdf12 Jan 2026
Form 2File: Form 2 Q4 FY 17-18.pdf12 Jan 2026
Form 3File: Form 3 Q4 FY 17-18_compressed.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q4 Disclosure of sold and booked inventory.pdf12 Jan 2026
Form 1File: Form 1 Q1 FY 18-19.pdf12 Jan 2026
Form 2File: Form 2 Q1 FY 18-19.pdf12 Jan 2026
Form 3File: Form 3 Q1 FY 18-19_compressed.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q1 Disclosure of sold and booked inventory.pdf12 Jan 2026
Form 1File: Form 1 Q2 FY 18-19.pdf12 Jan 2026
Form 2File: Form 2 Q2 FY 18-19.pdf12 Jan 2026
Form 3File: Form 3 Q2 FY 18-19_compressed.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q2 Disclosure of sold and booked inventory.pdf12 Jan 2026
Form 1File: Form 1 Q3 FY 18-19.pdf12 Jan 2026
Form 2File: Form 2 Q3 FY 18-19.pdf12 Jan 2026
Form 3File: Form 3 Q3 FY 18-19_compressed.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q3 Disclosure of sold and booked inventory.pdf12 Jan 2026
Form 1File: Form 1 Q4 FY 18-19.pdf12 Jan 2026
Form 2File: Form 2 Q4 FY 18-19.pdf12 Jan 2026
Form 3File: Form 3 Q4 FY 18-19_compressed.pdf12 Jan 2026
Disclosure of Sold and Booked InventoryFile: Q4 Disclosure of sold and booked inventory.pdf12 Jan 2026
Form 1File: Form 1 Q1 FY 19-20.pdf12 Jan 2026

How this compares with Thane

35%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 60 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHOIR JEWELS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DOMBIVLI7,600+ in Thane

2 kmBHOIR JEWELSCompleted 71Lapsed / revoked 62Other 107Dot size: filed unitsN

Filed coordinates, straight-line distance. 240 registered projects within 2 km.

Builder: SHANKAR NAMAJI BHOIR

SHANKAR NAMAJI BHOIR has 1 registration on MahaRERA, including BHOIR JEWELS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if BHOIR JEWELS is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHOIR JEWELS?

The registered promoter entity is SHANKAR NAMAJI BHOIR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHOIR JEWELS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BHOIR JEWELS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BHOIR JEWELS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHOIR JEWELS?

The professionals named in the filing: Architect: P S GOKHALE; Engineer: MANOHAR PATIL; Chartered Accountant: Laxmikant Kabra & Co LLP; Chartered Accountant: Narendra Rajput. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHOIR JEWELS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHOIR JEWELS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHOIR JEWELS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.