Yashraj Pristine
RG-MH-03016 · RERA P51900021418 · Last updated on MahaRERA portal: 22 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 30 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Yashraj Pristine is a Others project by Shree Sai Datta Developers in Dadar, 400014, registered with MahaRERA as P51900021418 on 28 Jun 2019. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 30 months from the original filing. 3 of the 29 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.
At a glance
Project
- NameYashraj Pristine
- TypeOthers
- Location
- Road no.4 Parsi Colony
- Dadar
- 400014
- Pincode400014
- RERA no.P51900021418
- ReraGenie IDRG-MH-03016
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on28 Jun 2019
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2023)
- Buildings1 building record
- Documents filed108 files
Current status
Figures as on 22 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Yashraj Pristine | NA | 19 | 19 | 29 | 0 | 29 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.
Yashraj Pristine: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Progress on shared amenities15
As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Yashraj Pristine | NA | Rs 11.14 cr | Rs 4.94 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sumedha Gore |
| Engineer | SAGAR B BUGADE |
| Engineer | ACHYUT NARAYAN WATVE |
| Chartered Accountant | MAYANK CHHATBAR |
| Partner | Role in project |
|---|---|
| Shree Sai Datta Developers | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay in approval, replanning due to ongoing Pandemic of Covid-19
Reason as filed by the promoterThere are 14 flats for sale in our project out of that we have sold only 3 flats. In balance sale proceeding we are confident to have sufficient funds to complete the project and shall handover the newly constructed to the flat purchases till 31st December 2025.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Apr 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Jun 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Jun 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed108
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect's Certificate Qtr End March 2024.pdf | 22 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 Qtr End March 2024.pdf | 22 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Qtr End March 2026.pdf | 22 Jun 2026 |
| Withdrawal Update Form 1File: Architect's Certificate Qtr End March 2024.pdf | 19 Jun 2026 |
| Withdrawal Update Form 1File: Architect's Certificate Qtr End March 2024.pdf | 19 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 Qtr End March 2024.pdf | 19 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 Qtr End March 2024.pdf | 19 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Qtr End March 2026.pdf | 19 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Qtr End March 2026.pdf | 19 Jun 2026 |
| Form 1File: Form 1 Qtr End Dec 2025.pdf | 24 Feb 2026 |
| Form 2File: Form 2 Qtr End Dec 2025.pdf | 24 Feb 2026 |
| Form 3File: Form 3 Qtr End Dec 2025.pdf | 24 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Details Dec 2025.pdf | 24 Feb 2026 |
| Form 2A (FY 2024-2025)File: Form 2A30122025.pdf | 22 Jan 2026 |
| Form 1File: Form 1 July Sept 2025.pdf | 14 Jan 2026 |
| Form 2File: Form 2 Sept 2025.pdf | 14 Jan 2026 |
| Form 3File: Form 3 Qtr End Sept 2025.pdf | 14 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory 301225.pdf | 14 Jan 2026 |
| Form 1File: Form 1 - June 2025.pdf | 27 Nov 2025 |
| Form 2File: Form 2 - June 2025.pdf | 27 Nov 2025 |
| Form 3File: Form 3 Qtr End June 2025.pdf | 27 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold, Unsold Details 30 June,2025.pdf | 27 Nov 2025 |
| Certificates of CA (Form 3)File: Form 3 Qtr End March 2025.pdf | 13 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 March 2025.pdf | 28 May 2025 |
| Certificates of CA (Form 3)File: Form 3 Qtr End March 2025.pdf | 28 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 2025.pdf | 28 May 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold, Booked Inventory.pdf | 28 May 2025 |
| Details of encumbrancesFile: Form B - Yashraj Pristine2025.pdf | 21 Apr 2025 |
| Declaration in FORM BFile: Form B - Yashraj Pristine2025.pdf | 19 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 Qtr End Dec 2024.pdf | 19 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Qtr End Dec 2024.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold, Booked Inventory.pdf | 19 Apr 2025 |
| Other - TechnicalFile: Chart Balance Work Construction Schedule.pdf | 19 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 19 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA From 5_March 2024.pdf | 19 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 Dec 2024.pdf | 19 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 June 2024.pdf | 19 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Sept 2024.pdf | 19 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA From 5_March 2024.pdf | 19 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate Qtr End March 2024.pdf | 9 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Qtr End March 2024.pdf | 9 May 2024 |
| Certificates of CA (Form 3)File: Form 3 Qtr End March 2024.pdf | 9 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Qtr End Dec 2023.pdf | 24 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 Engineers Certificate - Dec 23.pdf | 24 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 Qtr End Dec 2023.pdf | 24 Apr 2024 |
| Layout approvalFile: Drawing (39) (1).pdf | 4 Apr 2024 |
| Copy of Layout Approval (in case of layout)File: Drawing (39) (1).pdf | 4 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Sept 2023.pdf | 11 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Sept 23compressed THANK YOU.pdf | 11 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3 Sai Datta - September 2023.pdf | 11 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA form 5_March 2023.pdf | 5 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ReraCertificateform1March2023.pdf | 4 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ReraCertificate from1 June2023.pdf | 4 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ReraCertificateform1March2023.pdf | 4 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate form2 Mar 23.pdf | 4 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate form2 Jun 23.pdf | 4 Sep 2023 |
| Certificates of CA (Form 3)File: Sai Datta March 2023 form3.pdf | 4 Sep 2023 |
| Certificates of CA (Form 3)File: Sai Dattaform3 June 2023.pdf | 4 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT_S_CERTIFICATE_March_2020.pdf | 15 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate_March_2021.pdf | 15 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate_March_2022.pdf | 15 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate_June_2022.pdf | 15 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT_S_CERTIFICATE_DEC_2022.pdf | 15 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT_S_CERTIFICATE_DEC_2022.pdf | 15 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate_Sept_2022.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - March 20- Engineers Certificate.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Architect_Certificate_March_2021.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Architect_Certificate_March_2022.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Architect_Certificate_June_2022.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Architect_Certificate_Sept_2022.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ARCHITECT_S_CERTIFICATE_DEC_2022.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 -March 21- Engineers Certificate.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 -March 21- Engineers Certificate.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Mar 22- Engineers Certificate.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - June 22- Engineers Certificate.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Sept 22- Engineers Certificate.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Dec 22- Engineers Certificate.pdf | 15 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 -March 21- Engineers Certificate.pdf | 15 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 -March 21- Engineers Certificate.pdf | 15 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 - Mar 22- Engineers Certificate.pdf | 15 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 108 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Yashraj Pristine on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dadar
Monopoli
Mathuresh Infrapro Private Ltd
The Baya Sunrise
RENAISSANCE SPACES
RA RESIDENCES
R A ASSOCIATES
PANCHRATNA-NX
SUDHIR KISHOR DESAI
Ratan Infinia
Shree Shankheshwar Enterprises
EL MEJOR
ARTH REALTECH SPACES PVT LTD
Builder: Shree Sai Datta Developers
Shree Sai Datta Developers has 3 registrations on MahaRERA, including Shree Swami Samartha Darshan and Govind Niwas. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What does it mean that Yashraj Pristine shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Yashraj Pristine is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Yashraj Pristine?
The registered promoter entity is Shree Sai Datta Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Yashraj Pristine?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Yashraj Pristine?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Yashraj Pristine?
The professionals named in the filing: Architect: Sumedha Gore; Engineer: SAGAR B BUGADE; Engineer: ACHYUT NARAYAN WATVE; Chartered Accountant: MAYANK CHHATBAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Yashraj Pristine?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback