Home / Browse projects / Mumbai Suburban, Maharashtra / YASHASWATI CHS LTD
YASHASWATI CHS LTD
By LAKSHMI BUILDERS AND DEVELOPERS
RG-MH-21085 · RERA P51800001279 · Last updated on MahaRERA portal: 2 Jul 2021
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
YASHASWATI CHS LTD is a Residential / Group Housing project by LAKSHMI BUILDERS AND DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001279 on 27 Jul 2017. The registration is recorded completed; possession was promised by 31 Jul 2023.
At a glance
Project
- NameYASHASWATI CHS LTD
- TypeResidential / Group Housing
- Location
- Kurla
- Mumbai Suburban
- 400075
- Pincode400075
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800001279
- ReraGenie IDRG-MH-21085
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on27 Jul 2017
- Promised completion31 Jul 2023
- Revised completionNone
- Buildings1 building record
- Documents filed28 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| YASHASWATI CHS LTD | NA | 18 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
YASHASWATI CHS LTD: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 2 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
| STACK PARKING | Yes | 100% |
Parking filed5
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| PANTNAGAR YASHASWATI CHS LTD | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Santosh Pendse |
| Engineer | Satish Kulkarni |
| Partner | Role in project |
|---|---|
| LAKSHMI BUILDERS AND DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 29 Aug 2019
Documents filed28
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of Formation of Legal Entity (Society/Co Op etc.)File: YASHASWATI.pdf | 2 Jul 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: RERA certificate 3-9-19.pdf | 17 Sep 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: ARCH - PENDSE -S S ANNEXE - 4_0001.pdf | 7 Sep 2020 |
| Certificates of CA (Form 5)File: Yashaswati Chs Form 5_compressed.pdf | 18 Oct 2019 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MHADA Full OC dted 26-08-2019_compressed.pdf | 29 Aug 2019 |
| Certificates of CA (Form 3)File: PROJECT YASHPARK_compressed.pdf | 8 Mar 2019 |
| Certificates of CA (Form 5)File: LBD-YASHASWATI.pdf | 15 Oct 2018 |
| Certificates of CA (Form 3)File: CA CERTIFICATE FOR YASH PARK.pdf | 31 Jul 2018 |
| Certificates of CA (Form 3)File: Yash ParkCA Certificate Dated as on 10-01-2018-ilovepdf-compressed.pdf | 11 Jan 2018 |
| Certificates of CA (Form 3)File: Yash park Project on 3-10-2017-ilovepdf-compressed.pdf | 4 Oct 2017 |
| Declaration in FORM BFile: yashswati notarize documents-ilovepdf-compressed (1).pdf | 24 Aug 2017 |
| Certificates of CA (Form 3)File: YASHPARK CA CERTIFICATE_1.pdf | 26 Jul 2017 |
| Layout approvalFile: Yash Park Approved plan_1.pdf | 25 Jul 2017 |
| Building plan approvalFile: Yash Park IOD.pdf | 25 Jul 2017 |
| PAN CardFile: PAN Lakshmi Builders and Dev.pdf | 25 Jul 2017 |
| Copy of the legal title reportFile: Yashpark Legal Title Sakhalkars.pdf | 25 Jul 2017 |
| Details of encumbrancesFile: Yashaswati CHSL - No Encumbrances.pdf | 25 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Yash Park Approved plan_1.pdf | 25 Jul 2017 |
| Building Plan Approval (IOD)File: Yash Park IOD.pdf | 25 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: YASHPARK CC.pdf | 25 Jul 2017 |
| Declaration in FORM BFile: YASHPARK FORM B DECLARATION_1.pdf | 25 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yashswati Architects Certificate.pdf | 25 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Yashaswati Engineer certificats_1.pdf | 25 Jul 2017 |
| Proforma of Allotment letterFile: Yashaswati declaration for agreement of sale.pdf | 25 Jul 2017 |
| Proforma of Allotment letterFile: Yashaswati model allotment letter.pdf | 25 Jul 2017 |
| OtherFile: Yashpark 7 X 12.pdf | 25 Jul 2017 |
| OtherFile: Yashpark Property card.pdf | 25 Jul 2017 |
| OtherFile: Yashaswati CHSL - No Litigation.pdf | 25 Jul 2017 |
Promoter's earlier projects10
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Saraswati SadanP51800026655 | Vile Parle East, Mumbai Suburban | 24 | Oct 2020 | Completed | Jul 2024 | Feb 2023 |
| OMKAR CHS LTDP51800003558 | Andheri, Mumbai Suburban | 61 | Aug 2017 | Completed | Jun 2024Registered original: Jul 2023 | Oct 2023 |
| BASERA CHS LTDP51800001959 | Andheri, Mumbai Suburban | 44 | Jul 2017 | Completed | Jul 2023 | Mar 2020 |
| ShantadurgaP51900015604 | Dadar Naigaum, Mumbai City | 29 | Mar 2018 | Completed | Jan 2023 | May 2022 |
| Prakash Tower Chs Ltd | Bal Goviudas Road situated at Village Mahim | 21 | - | Completed | Oct 2013 | Late, Dec 2013 |
| ANUPAN CHS LTD | Tejpal Scheme Rood No. 4 Vile Parle East | 29 | - | Completed | Mar 2013 | Late, Jun 2017 |
| Puspkunj Chs Ltd | Dr Dicit Road Opp Dhanukar Colage Vile Parle East | 19 | - | Completed | Dec 2010 | Late, Mar 2011 |
| Malhari Sadan Chs Ltd | Ajmal Road of Malaviya Road vile Parale East | 16 | - | Completed | Jan 2010 | Late, Apr 2011 |
| Jeevan Sangam Chs Ltd | Dadabhai Cross Road Andheri West | 28 | - | Completed | Aug 2009 | Late, Dec 2009 |
| Shashi Chs Ltd | Subhash Road Pandulskar Marg Vile Parle East | 19 | - | Completed | Aug 2005 | Late, Oct 2005 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 28 filed documents as one ZIP, foldered, with a manifest
Keep YASHASWATI CHS LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kurla6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 286 registered projects within 2 km.
THE VIEWS
AGNEL DEVELOPERS
THE VIEWS II
AGNEL DEVELOPERS
Drushti Emerald
SAMARTH DRUSHTI DEVELOPERS
East Syde
VL GAJAMUKH DEVELOPERS LLP
ROYAL ALTEZZA
SHRI GANESH DEVELOPERS
Damji Shamji Corporate Square - Wing C
Coronate Constructions
See every Mumbai Suburban project, with the district possession charts
Builder: LAKSHMI BUILDERS AND DEVELOPERS
LAKSHMI BUILDERS AND DEVELOPERS has 6 registrations on MahaRERA, including OMKAR CHS LTD and BASERA CHS LTD. Its filings disclose 11 earlier MahaRERA projects: declares 5 of 11 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if YASHASWATI CHS LTD is delayed beyond 31 Jul 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of YASHASWATI CHS LTD?
The registered promoter entity is LAKSHMI BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in YASHASWATI CHS LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for YASHASWATI CHS LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at YASHASWATI CHS LTD?
The professionals named in the filing: Architect: Santosh Pendse; Engineer: Satish Kulkarni. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in YASHASWATI CHS LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.