Home / Developers / LAKSHMI BUILDERS AND DEVELOPERS
LAKSHMI BUILDERS AND DEVELOPERS: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
LAKSHMI BUILDERS AND DEVELOPERS has 6 registrations in this build, including OMKAR CHS LTD and BASERA CHS LTD. Its filings disclose 11 earlier MahaRERA projects: 5 of 11 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| OMKAR CHS LTD | Mumbai Suburban, Maharashtra | - | - | Completed |
| BASERA CHS LTD | Mumbai Suburban, Maharashtra | - | - | Completed |
| YASHASWATI CHS LTD | Mumbai Suburban, Maharashtra | - | - | Completed |
| Shantadurga | Mumbai City, Maharashtra | - | - | Completed |
| Saraswati Sadan | Mumbai Suburban, Maharashtra | - | - | Completed |
| LAKSHMI SOLITAIRE | Mumbai Suburban, Maharashtra | 38 | 32% | Completed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Shashi Chs Ltd | 15 Aug 2005 | 26 Oct 2005 | +2 months |
| Jeevan Sangam Chs Ltd | 3 Aug 2009 | 16 Dec 2009 | +4 months |
| Malhari Sadan Chs Ltd | 21 Jan 2010 | 30 Apr 2011 | +15 months |
| Puspkunj Chs Ltd | 25 Dec 2010 | 10 Mar 2011 | +2 months |
| ANUPAN CHS LTD | 21 Mar 2013 | 5 Jun 2017 | +51 months |
| Prakash Tower Chs Ltd | 22 Oct 2013 | 4 Dec 2013 | +1 months |
| Shantadurga P51900015604 | 30 Jan 2023 | 4 May 2022 | On time |
| BASERA CHS LTD P51800001959 | 1 Jul 2023 | 12 Mar 2020 | On time |
| YASHASWATI CHS LTD P51800001279 | 31 Jul 2023 | 26 Aug 2019 | On time |
| OMKAR CHS LTD P51800003558 | 30 Jun 2024 | 30 Oct 2023 | On time |
| Saraswati Sadan P51800026655 | 1 Jul 2024 | 27 Feb 2023 | On time |
Frequently asked questions
How do I verify LAKSHMI BUILDERS AND DEVELOPERS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with LAKSHMI BUILDERS AND DEVELOPERS?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.