Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Stilt Floor, 60%
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

Yash Enclaves Bldg 3 is a Residential / Group Housing project by RACHANA ENTERPRISES in Thane, Maharashtra, registered with MahaRERA as P51700004472 on 9 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameYash Enclaves Bldg 3
  • TypeResidential / Group Housing
  • Location
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421202
  • Pincode421202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700004472
  • ReraGenie IDRG-MH-24870

Builder

  • NameRACHANA ENTERPRISES
  • Entity typePartnership
  • PartnersRAJAN CHANDRAKANT MODAK, PRAFUL MANILAL SHAH, VINAY RAMCHANDRA DESHMUKH
  • Other registrations4 more →
  • Completed2 of 5
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed72 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Yash Enclaves Bldg 3NA290000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 60%.

Yash Enclaves Bldg 3: 66% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor60%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 19 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes20%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes41%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,769 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI8741.03
Proposed, not sanctioned8,741 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShankar Smruti Annex, Shubhash Rd, Dombivli-W

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRachana Shilp
EngineerRajesh A Thakare & Associates
PartnerRole in project
RACHANA ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700003975Dec 2019 → Dec 2020

Reason as filed by the promoter1. Increase in External Amenities which was not promised earlier such as Stack Parking, Puzzle Parking , Paving & Concreting around the building. Etc. Due to heavy rain during the year we could not erect the work of these increased amenities in external area. 2. Compound wall work in Proposed Ring Root Area is pending as demarcation was delayed by the Kalyan-Dombivali Municipal Corporation. 3. As per current status of work, we have completed RCC work, Brickwork, Plaster and all Internal Amenities upto 20th Floor with overhead water tanks, Fire fighting Systems and Lifts. 4. Now, Internal work

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Apr 2022

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf19 May 2023
Layout approvalFile: Layout 04-07-2019.pdf14 Dec 2022
Layout approvalFile: LAY OUT_21-25 Floor.pdf14 Dec 2022
Copy of Layout Approval (in case of layout)File: Layout 04-07-2019.pdf14 Dec 2022
Copy of Layout Approval (in case of layout)File: LAY OUT_21-25 Floor.pdf14 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Yash enclave.pdf13 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A mar 19.pdf17 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Jun 19.pdf17 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Sep 19.pdf17 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 Dec 19.pdf17 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form March 20.pdf17 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Jun 20.pdf17 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Sep 20.pdf17 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Dec 20.pdf17 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form Mar 21.pdf17 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf17 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Dec 19.pdf24 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - June 20.pdf24 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Sep 20.pdf24 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Dec 20.pdf24 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 20.pdf24 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 20.pdf24 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sep 20.pdf24 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 20.pdf24 May 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold flats.pdf20 May 2021
Certificates of CA (Form 3)File: Form 3 - yash enclave mar 20.pdf24 Mar 2021
Certificates of CA (Form 3)File: Form 3 - yash enclave jun 20.pdf24 Mar 2021
Certificates of CA (Form 3)File: form 3 yash enclave sep 20.pdf24 Mar 2021
Certificates of CA (Form 3)File: Form 3 yash enclave dec 20.pdf24 Mar 2021
Details of Restarting of Construction work post lockdownFile: restarting of construction work.pdf20 Jul 2020
Certificates of CA (Form 3)File: Form 3 Rachana Enter 31-12-2019_compressed.pdf6 Mar 2020
Certificates of CA (Form 3)File: Form 3 31-MARCH.pdf28 Jan 2020
Certificates of CA (Form 3)File: Form 3 30-JUNE.pdf28 Jan 2020
Certificates of CA (Form 3)File: Form 3 30-SEP.pdf28 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 2018-19.pdf13 Jan 2020
Certificates of CA (Form 3)File: form-3 Rachana Enterprises 31 DEC 18-compressed.pdf1 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Rachana Enterprises- Architect Certificate- June'18.pdf19 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Rachana Enterprises- Architect Certificate- Sept'18.pdf19 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rachana Enterprises- Engineers Certificate- June'18.pdf19 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rachana Enterprises- Engineers Certificate- Sep'18.pdf19 Jan 2019
Certificates of CA (Form 3)File: Rachana Enterprises 31-03-2018.pdf2 Jan 2019
Certificates of CA (Form 3)File: Rachana Enterprises 30-06-2018.pdf2 Jan 2019
Certificates of CA (Form 3)File: Rachana Enterprises 30-09-2018.pdf2 Jan 2019
Certificates of CA (Form 5)File: Rachana Form 5.pdf22 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rachana Architect Certificate-1-3.pdf19 Jul 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rachana Engineer Certificate-4-7-ilovepdf-compressed.pdf19 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1_30-09-2017-F.pdf19 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1_31-12-2017-F.pdf19 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_30-09-2017-F.pdf19 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_31-12-2017-F.pdf19 Feb 2018
Certificates of CA (Form 3)File: Form 3_30-09-2017-F.pdf19 Feb 2018
Certificates of CA (Form 3)File: Form - 3 Yash Enclave - 31-12-2017-F.pdf19 Feb 2018
PAN CardFile: Milind Deshmukh PAN.pdf28 Jul 2017
PAN CardFile: Praful Shah PAN.pdf28 Jul 2017
PAN CardFile: Rajan Modak PAN.pdf28 Jul 2017
PAN CardFile: Vinay Deshmukh PAN.pdf28 Jul 2017
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf28 Jul 2017
Proforma of Allotment letterFile: agreement for sale compressd-ilovepdf-compressed.pdf28 Jul 2017
Proforma of Allotment letterFile: DEED OF CONVEYANCE OF BUILDING STRUCTURE-ilovepdf-compressed.pdf28 Jul 2017
Proforma of Allotment letterFile: DEED OF CONVEYANCE-ilovepdf-compressed.pdf28 Jul 2017
Building plan approvalFile: IOD-ilovepdf-compressed.pdf27 Jul 2017
Layout approvalFile: 111.pdf27 Jul 2017
PAN CardFile: p01 (1).pdf27 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE-ilovepdf-compressed.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: 111.pdf27 Jul 2017
Building Plan Approval (IOD)File: IOD-ilovepdf-compressed.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC-5-6-ilovepdf-compressed (1).pdf27 Jul 2017
Declaration in FORM BFile: DECLARATION.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE.pdf27 Jul 2017
Certificates of CA (Form 3)File: C A CERTIFICATE.pdf27 Jul 2017
Proforma of Allotment letterFile: LETTER OF ALLOTMENT.pdf27 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
YASH ENCLAVEYASH ENCLAVE NEAR KHANDOBA MANDIR KUMBHARKHAN PADA SUBHAS ROAD DOMBIVLI WEST224CompletedFeb 2015Feb 2015

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Yash Enclaves Bldg 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DOMBIVLI7,600+ in Thane

2 kmYash Enclaves Bldg 3Completed 46Lapsed / revoked 38Other 60Dot size: filed unitsN

Filed coordinates, straight-line distance. 144 registered projects within 2 km.

Builder: RACHANA ENTERPRISES

RACHANA ENTERPRISES has 5 registrations on MahaRERA, including MANGALA RESIDENCY and Rachana Residency. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Yash Enclaves Bldg 3 is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Yash Enclaves Bldg 3?

The registered promoter entity is RACHANA ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Yash Enclaves Bldg 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Yash Enclaves Bldg 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Yash Enclaves Bldg 3?

The professionals named in the filing: Architect: Rachana Shilp; Engineer: Rajesh A Thakare & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Yash Enclaves Bldg 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Yash Enclaves Bldg 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Yash Enclaves Bldg 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.